You are on page 1of 4

How to Plan a Large

Tilt-Up Project
To ensure a successful job, don’t overlook these five important steps

BY RAY KNOTTS

mplementing a bulletproof

I plan is critical to the success of


a tilt-up project, especially on
a large, fast-track job. A missed
date on material deliveries, a mis-
figured crew requirement, a spe-
cialty tool breaking down or a post-
poned panel pour can put your
project in jeopardy.
As the founder of Concrete Con-
cepts Co., a tilt-up contracting firm
in Kings Mountain, N.C., I’ve
learned from experience what it
takes to develop an effective plan
for large, complex tilt-up jobs. The
a ve rage size of our projects is
70,000 to 100,000 square feet, but
some projects are as large as
750,000 square feet. Preparing for
such big jobs often requires coor-
dinating the activities of as many as
50 workers, so it’s necessary to start
planning early to make sure every-
one involved knows what to do and
when. A good plan must also have
contingencies for common jobsite
problems that can lead to costly
project delays, such as equipment
breakdowns. The following five
steps are essential to developing an
effective plan.
Figure 1. Staging plan for grocery-facility project.
1. REVIEW THE STRUCTURAL
DRAWINGS • Chamfers • Reinforcing-steel location, size
Thoroughly review the structural • Door swings and spacing
drawings to make sure the archi- • Surface finishes • Lifting and bracing insert book
tect’s plans agree with the engi- (from your insert supplier) and
neer’s intent. Details to check in- 2. PREPARE SHOP DRAWINGS panel embeds (from your struc-
clude: AND MATERIALS SUBMITTALS tural-steel supplier)
• Panel size, thickness and weight Shop drawings for a tilt-up pro- • Panel fabrication and erection
• Reveals ject should clearly show: sequences
(with special attention given to
their compatibility)
• Form liners and reveal details
(size, shape and composition)
• Grouting and patching materials
• Any other materials integrated
into the panel
3. PLAN JOBSITE STAGING
Once the architect has approved
the submittals, you can begin stag-
ing the jobsite. This step involves
choosing strategic locations for
toolsheds, equipment, materials
and temporary casting beds. You
must also establish access routes
for ready-mix trucks, concrete
pumps and cranes. Figure 1 shows
a staging plan for a tilt-up project
One way Concrete Concepts Co. adheres to its tilt-up plans is by using efficient involving four separate buildings
equipment. Sporting custom-designed rolling outriggers, this crane eliminates totaling over 1 million square feet.
problems with floor-slab cracking and lets crews set panels up to 50% faster. The importance of the staging
process is often overlooked, even
( For examples of shop dra w i n g s, Materials submittals should in- though effective staging can dra-
see “Ti l t - Up Ba s i c s,” C o n c re t e clude specifications for: matically increase construction
C o n s t r u c t i o n , May 1993, pp. • Concrete mix design productivity once panel fabrication
337-344.) • Bond breakers and curing agents begins. Planning access routes for

MODIFIED CRANE REDUCES PANEL SETTING TIME

Knotts believes the safest,


most efficient way to crane-set tilt-
up panels is from the concrete Rotation
floor slab. But the weight that’s
applied to the crane’s two rear
outriggers during panel lifting can
crack the slab.
11'-8 11⁄16" CONCRETE
To solve this problem, Knotts CONCEPTS

Link-Belt
spent the winter of 1995 design- Model 218-A
100 Ton
ing and fabricating a custom set
of rolling outriggers that disperses
the total lifting load over 16 points
3'-4" 58" 16'-10" 58" 60-1⁄8"
instead of just two (see drawing).
10' 10'-6" 13'- 3⁄8" 1'-107⁄8"
In March 1996, the conventional
outrigger pads on the company’s 35'-10 78⁄ "
100-ton Link-Belt crane were re-
placed with rolling dollies that al-
low the operator to keep the boom ting panels has increased produc- the ability to stay closer to his
at a sharper angle while lifting a tion by as much as 50%.” load,” Knotts claims.
panel, then simply roll the crane Because the rolling outriggers Since the crane was equipped
back before lowering the panel to allow the crane operator to carry with the special outriggers, crews
its final destination. the weight of the panel closer to have used it to place more than a
“The rolling outriggers greatly the crane’s center pin, it’s easier thousand panels, all set from
decrease the pound-per-square- to stay inside the load limit of the floor slabs ranging in thickness
inch load you typically have under crane. “Panels in the 50-ton range from 4 to 8 inches. They haven’t
conventional stationary outrigger that would have required a mon- experienced any cracking prob-
pads,” explains Knotts. “In addi- ster crane can now be set with a lems in floors that have been
tion to solving the floor-slab crack- smaller, lighter, more mobile properly installed on well-consoli-
ing problem, this method of set- crane because the operator has dated subbases.
TYPICAL CREW SEQUENCING AND BASIC TASKS

Sequence Crew No. of Workers Basic Tasks


1 Floor preparation 2 Cleans floor surface, fills contraction
joints and applies bond breaker. Keeps
work area clean and organized.

2 Panel layout 2 Establishes chalk lines for panel perime-


ters, doors, windows, louvers, lifting and
brace inserts, joist pockets, reveals and
any other items to be installed before
concrete placement.

3 Formwork installation 4-6 Installs all formwork and form liners,


chamfers, reveals, and door and window
blockouts.

4 Rebar installation 4 Installs all panel reinforcing per shop


drawings, including any additional rebar
required for lifting. Installs all lifting and
bracing inserts and miscellaneous steel
embeds.

5 Panel inspection 1 Checks that panels meet the require-


ments specified in the structural plans
and shop drawings before concrete
placement. Tags each panel with a “pour
card,” which tells the concrete crew that
the panel is ready to pour.

6 Concrete placement 8-12 Places, on average, about 200 to 300


cubic yards (enough for about 20 to 25
panels) twice a week. The crew size
needed depends on the type of finish
required on the inside panel face and how
much jointing and detail work the panels
receive.

7 Pre-erection 4-6 Cleans out the lifting and bracing inserts,


strips forms, attaches braces, sets
footing pads and clears crane access
ways.

8 Panel erection 6-8 This is the crew that makes it all happen,
using a crane to lift into place as much as
400 lineal feet of wall panels in one day.

9 Panel grouting 6-8 Using aerial lifts, a skilled crew should be


and patching able to patch and grout 25,000 square
feet of tilt-up walls in one week, primarily
to correct surface imperfections that
paint won’t hide.

10 Punch list 2 Takes care of the last-minute details that


make the difference between having a
satisfied customer or a long list of call-
backs. Typical activities include panel
touchup, patching holes in the floor slab
and cleaning floor joints.
just working on the panel phase.
Unless you have ample tools, equip-
ment and materials available, your
labor costs can skyrocket, since just
one broken tool can stop the whole
40-person train. The key is to have a
backup if an important tool or piece
of equipment goes down.
Every contractor has a preferred
way of doing things. To find the
equipment and methods that work
best for you, it’s often necessary to
do some experimenting. For exam-
ple, my crews recently began using
air-powered tools because the
cords and switches on electric tools
were inconvenient. We also cus-
tomized a Link-Belt 100-ton mobile
crane, outfitting it with a special
rolling outrigger designed specifi-
cally for tilt-up work (see box on
Figure 2. Typical production schedule for a 12-week project. page 570). Concrete Concepts is
constantly finding faster, more effi-
trucks and equipment is especially carefully to ensure that the project cient ways to build tilt-up struc-
critical on restricted jobsites or in goes according to schedule. Too few tures.
wet or wintry weather. workers on a crew can cause delays,
Typically, the total square footage and too many workers can overrun
needed for materials staging equals the production of the crew that Ray Knotts, president of Concrete
approximately 20% of the floor works ahead of it. The table plots the Concepts Co., has been a concrete
area. If the floor slab isn’t large crew sequencing—including the ap- contractor since 1974.
enough for casting all the panels proximate number of workers per
and you don’t want to stack them, crew—for a typical panel-fabrication
designate areas for temporary cast- process. Figure 2 shows a typical pro-
ing beds in the staging plan. These duction schedule.
beds should be located as close as
possible to the floor slab. 5. PLAN TOOL AND
EQUIPMENT NEEDS
4. PLAN CREW SIZE AND Almost as important as having the
SEQUENCING right crew size and sequencing is
Because a number of crews, each having the right tools and equip-
with different responsibilities, are re- ment for the job. During periods of PUBLICATION #C970569
quired for a large tilt-up job, crew size peak production, it’s not uncom- Copyright © 1997, The Aberdeen Group
and sequencing must be planned mon to have as many as 40 people All rights reserved

You might also like