You are on page 1of 9

Wood CONTRACT No: 3850 Client Document Cat: 3c

Client CONTRACT No: 2457 Client Document Number: HOLD 2


CLIENT: Preemraff Wood Document Class: 1
LOCATION: Gothenburg, Sweden Wood Document Number: 3850-8470-DS-3807
PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED Page: 1 of 9

EQUIPMENT DATASHEET

CPI SEPARATOR PACKAGE


38T-5A/B

REV DATE DESCRIPTION ORIGINATOR CHECKER APPROVER


O1 11/15/2022 Issued for Review

DSN: 2079
System of Units S.I.

EQUIPMENT DATASHEET

Wood CONTRACT No: 3850 PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED
Client CONTRACT No: 2457 SERVICE: CPI SEPARATOR PACKAGE

Rev.
CLIENT: Preemraff ITEM No.: 38T-5A/B No. REQD: Two (Duty / Standby)
LOCATION: Gothenburg, Sweden Wood Document No.3850-8470-DS-3807
REV O1
DATE 15/11/2022 PAGE: 2 OF 9
1 TYPE OF EQUIPMENT Corrugated Plate Interceptor (CPI) Package (Note P2)
2 MANUFACTURER / MODEL STA
3 OPERATING IN ( Alone/ Parallel/ Series) Duty / Standby (Note P5)
4
5
6 PROCESS DATA / SPECIFICATION REQUIREMENT SUPPLIER DATA
7 The CPI Separator Package shall be designed for the following feed flow and quality
8 INLET FEED STREAM FLUID Waste Water (Notes P3 & P4) STA
9 DESIGN FLOWRATE m3/h 350 STA
10 TEMPERATURE °C less than 56 STA
11 PRESSURE barg 2.0 STA
12 VISCOSITY cP 0.587 STA
13 pH 6 to 9 STA
14 TOC mg/l 109 (max value 1000) STA
15 TOTAL SUSPENDED SOLIDS (TSS) mg/l 40 (max value 97) STA
16 TOTAL NITROGEN mg/l 31 STA
17 TOTAL PHOSPHORUS mg/l 0.5 STA
18 HYDROCARBON OIL INDEX (HOI) mg/l 22 (max value approx 100) STA
19
20
21 DISCHARGE DESIGN FLOWRATE m3/h 350 STA (range/capacity)
22 TEMPERATURE °C less than 56 STA
23 PRESSURE barg 2.0 STA
24 VISCOSITY cP 0.587 STA
25 pH 6 to 9 STA
26 TOTAL TOC mg/l 109 STA
27 SOLUBLE TOC mg/l STA STA
28 TOTAL SUSPENDED SOLIDS (TSS) mg/l 40 STA
29 TOTAL NITROGEN mg/l 31 STA
30 TOTAL PHOSPHORUS mg/l 0.5 STA
31 HYDROCARBON OIL INDEX (HOI) mg/l 20 STA
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59 ABBREVIATIONS
60 STA = SUPPLIER TO ADVISE N/A = NOT APPLICABLE
DSN: 2079
System of Units S.I.

EQUIPMENT DATASHEET

Wood CONTRACT No: 3850 PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED
Client CONTRACT No: 2457 SERVICE: CPI SEPARATOR PACKAGE

Rev.
CLIENT: Preemraff ITEM No.: 38T-5A/B No. REQD:Two (Duty / Standby)
LOCATION: Gothenburg, Sweden Wood Document No.3850-8470-DS-3807
REV O1
DATE 11/15/2022 PAGE: 3 OF 9
1 MECHANICAL DATA / SPECIFICATION REQUIREMENT SUPPLIER DATA
2
3 Corrugated Plate Interceptor (CPI) Seperator Package (38T-5A/B) 2 off (DUTY/STANDBY) STC
4 Make & Model No. STA STA
5 Capacity m3/hr 0 to 350 m3/hr STA
6 Operating Pressure barg STA STA
7
8 Plate Pack type STA STA
9 Spacing mm STA STA
10 Angle Degrees STA STA
11 Length x width x depth mm STA STA
12
13 Oil Skimmer Type STA STA
14 Make & Model STA STA
15 Oil recovery capacity m3/hr STA STA
16 Size mm STA STA
17 Driven Power Electric or Compressed Air STA
18 Power or Air Consumption kW or m3/hr STA STA
19
20
21 Overall Unit Size (length x width x depth) mm STA STA
22 Weights STA STA
23 Tank Empty kg STA STA
24 Operating kg STA STA
25 Heaviest maintenance item kg STA STA
26 Nozzle Sizes & Numbers off of each STA STA
27 Tank Inlet (Effluent) Inches STA STA
28 Tank Outlet (Discharged effluent) Inches STA STA
29 Sludge Outlet Inches STA STA
30 Skimmed Oil Outlet Inches STA STA
31 Nitrogen Gas blanket connection Inches STA STA
32 Nozzle Flange Specification ANSI B16.5 150 lbs RF STA
33 Tank Design and Manufacturing Standard STA STA
34
35 Winterisation See Note M16 STA
36
37 Materials of Construction
38 Tank body and basin 316L Stainless Steel STA
39 Tank internals 316 / 304 Stainless Steel STA
40 Tank Support Structure Carbon Steel STA
41 Tank access platform and stairs Carbon Steel STA
42 Plate Pack STA STA
43 Plate Pack spacers STA STA
44 Oil Skimmer 316L Stainless Steel STA
45 Piping
46 Feed / Discharge 316L Stainless Steel STA
47 Compressed Air / Nitrogen 316L Stainless Steel STA
48 Skimmed Oil Carbon Steel + 1.6mm CA STA
49 Instrument tubing 316L Stainless Steel Minimum STA
50 Drain / Sludge Valves Alloy 410 (API 600 Valve Trim) STA
51 Package Inlet Valves 316 SS (API 600 Valve Trim) STA
52 Air/Nitrogen filter/regulator sets Alloy 410 (API 600 Valve Trim) STA
53
54 Nameplate Preem STDD-602 STA
55 Earthing Lug(s) Preem STDD-603 STA
56
57
58
59 ABBREVIATIONS
60 STA = SUPPLIER TO ADVISE STC = SUPPLIER TO CONFIRMN/A = NOT APPLICABLE
DSN: 2079
System of Units S.I.

EQUIPMENT DATASHEET

Wood CONTRACT No: 3850 PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED
Client CONTRACT No: 2457 SERVICE: CPI SEPARATOR PACKAGE

Rev.
CLIENT: Preemraff ITEM No.: 38T-5A/B No. REQD:Two (Duty / Standby)
LOCATION: Gothenburg, Sweden Wood Document No.3850-8470-DS-3807
REV O1
DATE 11/15/2022 PAGE: 3 OF 9
1 MECHANICAL DATA / SPECIFICATION REQUIREMENT SUPPLIER DATA
2
3 Electrical & Instrumentation
4 Packaged Category (Project Spec 3850-8550-SP-6006) Category A STA
5 Control Panel or Main Interface Junction Box(es) Required at Package boundary STA
6 IP Rating IP 65 Minimum STA
7 Material of Construction Stainless Steel STA
8 Instrument Panel STA STA
9 Unit cabling to Project Specs 3850-8550-SP-6004 (control) and 3850-8530-SP-6003 (electri Compliance with Project Specs STA
10 Power Supply 400V 3ph 50Hz & 230V 1ph 50Hz STA
11 Instrumentation Power 24V DC & 230V 1ph 50Hz UPS STA
12 Solenoid Valves 110V DC UPS STA
13 Motor Starters By BUYER STA
14
15 ATEX Certification for Package Refer to Notes P11.2 & M11 STA
16 CE Marking & Documentation See Material Requisition STA
17 Inspection & Testing See Note M21 STA
18 Painting / Surface Protection To Preem ES15 STA
19 Packing, Preservation & Preparation for Delivery See Material Requisition STA
20 Start up & Commissioning Spares Required STA
21 Capital/Insurance Spares STA STA
22 Special Tools If required for STA
23 installation/maintenance

24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59 ABBREVIATIONS
60 STA = SUPPLIER TO ADVISE N/A = NOT APPLICABLE
DSN: 2079
System of Units S.I.

EQUIPMENT DATASHEET

Wood CONTRACT No: 3850 PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED
Client CONTRACT No: 2457 SERVICE: CPI SEPARATOR PACKAGE

Rev.
CLIENT: Preemraff ITEM No.: 38T-5A/B No. REQD:Two (Duty / Standby)
LOCATION: Gothenburg, Sweden Wood Document No.3850-8470-DS-3807
REV O1
DATE 11/15/2022 PAGE: 5 OF 9
1 Process Notes
2 P1 The process data on this Mechanical data sheet is based on Process data sheet no. 3850-8110-PS-3807 Rev O1.
3
4 P2 Purpose
5 The CPI package is required to provide oil and heavy solids removal of the industrial wastewater at Preem’s Gothenburg refinery and forms part of the new
6 Wastewater Treatment Plant (WWTP).
7 Immediately upstream of the CPI is the inlet basin to the treatment process.
8 Immediately downstream of the CPI is CPI Sump and Buffer Tanks.
9 Figure 1_1 below shows a simplified schematic of the proposed treatment of the overall WWTP.
10
11
12
13
14
INLET BASIN CPI BUFFER TANKS PRIMARY DNF COOLING
15 SYSTEM

16
17 MBBR (5
STAGE)
18
19 SAND FILTERS SECONDARY
DAF
20
21
22 P3 Feed Streams
23 As general background, Preem’s HVO project will produce 2 additional streams going to the WWTP (GFU and HCU) and will modify the existing main refinery
24 wastewater stream. Higher values in Total Nitrogen are expected in the existing stream together with a flow increase. TOC and Total Nitrogen can vary a lot
25 depending on the processed crudes (H2S Scavenger) and when there is a turnaround in the refinery. The values can be high during shut down and start up
26 and with lower load in between. Stream 2 (GFU) will come from the sour wastewater stripper. Stream 3 (HCU) will be distilled water from evaporation and
27 may contain fatty acids <20ppm. At present the information available is minimal for this Stream 3.
28 The CPI unit is the first treatment step in the process, the wastewater has only passed through the inlet basin at this stage.
29
30 P4 Feed Stream Assumptions to CPI Unit (HOLD1)
31 At this stage, the following assumptions have been made to define the feed quality as a worse case:
32 l Effects of diluting worst quality stream 1 with streams 2 and 3 not taken into account.
33 Assumptions will be refined as the overall WWTP design progresses.
34
35 P5 Two CPI units will be required in this package – each sized for 350m3/h. Under normal operation these will operate in duty/standby however in times of high
36 flow there must be the option to operate in parallel.
37 The following list outlines the main equipment required within each CPI package (See also Note M22):
38 · CPI body & basin
39 · Weirs - adjustable inlet weir is desirable
40 · Skimmer
41 · Sludge removal equipment
42 · Internal plates and Internal supports for components
43 · Airtight cover (for Nitrogen blanketing) – including nitrogen inlet
44
45 P6 The SUPPLIER shall confirm the concentrations of the following in the effluent leaving the CPI Unit:
46 l HOI
47 l Total TOC and Soluble TOC
48 l TSS
49 l Total P and Total N
50 l pH
51
52 P7 Mass Balance
53 The SUPPLIER shall provide a mass balance which shall report the following for each stream:
54 l Flow including average, peak and minimum (m3/h and kg/h)
55 l Temperature (oC) and pressure (bar)
56 l pH
57 l Key parameters including TOC, TSS and HOI (kg/day, kg/h and mg/l)
58 l Demulsifier dosing flowrate (m3/h)
59 ABBREVIATIONS Continued….......
60 STA = SUPPLIER TO ADVISE N/A = NOT APPLICABLE
DSN: 2079
System of Units S.I.

EQUIPMENT DATASHEET

Wood CONTRACT No: 3850 PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED
Client CONTRACT No: 2457 SERVICE: CPI SEPARATOR PACKAGE

Rev.
CLIENT: Preemraff ITEM No.: 38T-5A/B No. REQD:Two (Duty / Standby)
LOCATION: Gothenburg, Sweden Wood Document No.3850-8470-DS-3807
REV O1
DATE 11/15/2022 PAGE: 6 OF 9
1 P8 Availability
2 The CPI Package as part of WWTP is required to provide continuous wastewater treatment capacity during normal process plant operations.
3
4 P9 General Process Design Standards
5 The SUPPLIER shall incorporate international best practice for the design and specification of CPI Package, to ensure operability and achievement of the
6 requirements without excessive cost and shall pay special attention to the aspects of the performance which shall be guaranteed by the SUPPLIER.
7 The oil removal process, and unit operations shall be robust and suitable for automatic, unattended operation for extended periods of time with minimal
8 maintenance in the local conditions. The equipment shall be the SUPPLIER standard except where specifically identified in the documentation package.
9 Requirements for operator intervention shall be minimised in as far as is practicable within the CPI Package.
10 SUPPLIER shall demonstrate prior experience and competence with the technologies required, including appropriate design and commissioning/operational
11 competence in the local environment.
12 The SUPPLIER shall demonstrate that the selected equipment has been used successfully and sustainably over extended time periods in multiple plants in
13 equivalent applications in equivalent operating environments.
14
15 P10 316L SS has been specified for the externals of the CPI unit, internals (where appropriate) are to be made with 304 or 316L SS . The material used in the
16 corrugated plates shall be specified by SUPPLIER.
17 The SUPPLIER shall specify the materials of construction in accordance with the above or propose others which they consider to more robust and suitable for
18 the duty and local conditions and shall incorporate appropriate good engineering practice and international standards.
19
20 P11 Operations, Control and Instrumentation
21 P11.1 The CPI Separator Package will be located in a refinery and shall be suitable for remote emergency shutdown / isolation to de-energised safe conditions in case of a
22 chemical / gas leak alarm. (Note M7)
23 P11.2 Hazardous area classifications shall be assumed as follows (Note M11):
24 l Externally located equipment, where hydrocarbon vapours are assessed to be present: Zone 2, Gas Group IIB, Temperature Class T3.
25 l Internal covered vessels: Zone 0, Gas Group IIB, Temperature Class T3.
26 P11.3 The SUPPLIER shall confirm all the instrumentation required for the DNF package. (Notes M8 & M9)
The package shall operate automatically and unattended for extended periods of time under the control of the site DCS except during activities for which
27 P11.4
operator
28 intervention is essential. (Note M9)
29
30 P12 Process Guarantee
31 Guarantees shall be provided for the following:
32 l hydraulic capacity (flow)
33 l operating performance of all equipment items within the CPI Package
34 l quality of all streams
35 l consumption of utilities, chemicals and consumables
36 l on-line availability of all equipment items within the CPI Package
37
38 P13 Summery of Operating Data
39 In addition to the data requested in Material Requisition, the SUPPLIER shall provide the following Summary of Operating Data with the proposal.
40
41 Parameter Units Value
42 Geometry of CPI Package n/a STA
43 Package effective area / length, width, height m2/m STA
44 Dimensions m STA
45 Water Depth m STA
46 Total package footprint (plot space) required m2 STA
47 Demusifier dosing rate Concentration/kg per year STA
48 Anticipated Sludge waste m3/hr STA
49 Total connected electrical load kW STA
50 Peak electrical load kW STA
51
52 The SUPPLIER shall not limit their data to the list above and shall provide other relevant data, as required.
53
54 HOLDS
55 1. Confirmation of Process Feed assumptions
56 2. Preem Document number to be confirmed
57
58 Continued….............
59 ABBREVIATIONS
60 STA = SUPPLIER TO ADVISE N/A = NOT APPLICABLE
DSN: 2079
System of Units S.I.

EQUIPMENT DATASHEET

Wood CONTRACT No: 3850 PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED
Client CONTRACT No: 2457 SERVICE: CPI SEPARATOR PACKAGE

Rev.
CLIENT: Preemraff ITEM No.: 38T-5A/B No. REQD:Two (Duty / Standby)
LOCATION: Gothenburg, Sweden Wood Document No.3850-8470-DS-3807
REV O1
DATE 11/15/2022 PAGE: 7 OF 9
1 MECHANICAL / PACKAGE NOTES
2
This data sheet shall be read in conjunction with the Material Requisition 3850-1946F/01, which describes the overall scope of supply, general technical
3 M1
requirements and
4 contains reference documents/specifications, as applicable to this package. This data sheet mainly provides specific details relating to the Primary CPI Separator package duty
5 requirements and any specific technical clarification which may override the requirements of the Material Requsition and its referenced documents in order to the avoid the risk
6 of any potential conflicting requirements.
7
8 M2 Unless noted otherwise within this data sheet, the CPI Separator Package will be generally to SUPPLIER standard design for the specified duty, however, any specific deviations
9 / exceptions made by SUPPLIER to the requirements this data sheet, Material Requisition and referenced documents shall be subject to acceptance by BUYER.
10
11 M3 For documentation requirements for bid submission and post-order award, please refer to the material requisition. Data requested in the preceding pages shall be completed
12 and submitted by SUPPLIER.
13
14 M4 Package shall be designed for an operational design life of 20 years minimum based on running reliably for 24 hours/day, 365 days/year, except for routine
15 maintenance as recommended by SUPPLIER.
16
17 M5 Unless stated otherwise in this data sheet, fabrication/construction of the package shall be in accordance with good engineering practice and appropiate international
18 standards, generally in accordance with the general technical requirements and referenced specifications and standards of the material requisition.
19
For Climatic, Environmental and Utility Data, Preem Specification ES02-GOR applies to local site conditions. Electrical Specification for Package Units 3850-
20 M6
8530-SP-6003
21 provides details of available electrical power supplies
22
23 M7 CPI Separator Package isolation and emergency shutdown shall be in accordance with Project Specifications 3840-8110-PH-7002 and 3840-8120-PH-7001.
24
Controls and Instrumentation shall be supplied in accordance with Project Specification 3850-8550-SP-6006 for Packaged Equipment and Preem Standards
25 M8
ES11-20 and
26 ES11-40.
27
28 M9 SUPPLIER shall provide a local ICSS interface control panel for the package and all necessary controls/instrumentation to facilitate Category "A" control, monitoring and
29 safeguarding in accordance with the general operating philosophy of Project Specification 3840-8120-PH-7002 and C&I Package Equipment Specification 3850-8550-SP-6006.
30
31 M10 Electrical equipment within each Reactor stage, such as on-skid cabling, junction boxes, motors etc shall be supplied in accordance with Project Specification
32 3850-8530-SP-6003 and its referenced standards.
33
34 M11 All equipment located within hazardous classified areas shall be ATEX certified for use within the specified hazardous area conditions. For plant standardisation, minimum
35 requirements for instrumentation and electric motors located within hazardous areas shall be Zone 1 IIC T3.
36
37 M12 If supplied, Rotating equipment (eg. Pumps, blowers and mixers) shall be supplied in accordance with Preem Standard ES10-GOR.
38
39 M13 Pressure vessels shall be designed and manufactured to EN13445 and Preem Spec ES05, and CE marked in accordance with the PED.
40
41 M14 Pipework material class shall be selected based on the relevant service/duty and supplied in accordance with the relevant Pipe Class of Preem Piping Spec ES08 and ES08-01,
42 as amended by Project Specification 3850-8230-SP-6002 and shall comply with PED, where applicable. Piping design code shall be EN13480, where applicable. Pipework shall
43 termimate with a flange connection at package boundary/skid edge.
44
45 M15 The equipment supplied by the SUPPLIER shall be designed for easy and safe access for routine servicing, inspection and maintenance activities. Should maintenance and
46 access platforms and ladders be required, they should be provided by SUPPLIER complete with safety railing. Site standard details are provided within the attachments of the
47 Material Requisition.
48
49 M16 SUPPLIER shall be responsible for determining the items and pipe streams within the Package which require insulation and/or heat tracing for process, winterisation or
50 personnel protection reasons based on the Preem Basic Data and Site Information ES02-GOR and Preem Insulation Specification ES14. However, insulation and heat tracing
51 will be supplied and installed at site by OTHERS, but SUPPLIER to confirm design requirements and provide all necessary insulation supports where required by ES14.
52
53 M17 Minimum Design Material Temperature (MDMT) shall be based on -29OC for unsulated equipment and 0OC for insulated equipment.
54
The maximum allowable noise level (SPL) is 85 dB(A) @ 1 metre distance for the complete assembled Package. Any noise abatement device(s) necessary to
55 M18
reach the
56 above limit shall be included in the SUPPLIER’s scope of supply as an option in accordance with Preem Standard ES10-GOR.
57
58
59 Continued….............
60 STA = SUPPLIER TO ADVISE N/A = NOT APPLICABLE
DSN: 2079
System of Units S.I.

EQUIPMENT DATASHEET

Wood CONTRACT No: 3850 PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED
Client CONTRACT No: 2457 SERVICE: CPI SEPARATOR PACKAGE

Rev.
CLIENT: Preemraff ITEM No.: 38T-5A/B No. REQD:Two (Duty / Standby)
LOCATION: Gothenburg, Sweden Wood Document No.3850-8470-DS-3807
REV O1
DATE 11/15/2022 PAGE: 8 OF 9
1
2 M19 In order to meet the required design life and SUPPLIER's equipment guarantees, SUPPLIER shall select and specify the materials of construction within the SUPPLIER package
3 suitable for the specified feed compositions and environmental conditions. SUPPLIER shall provide full details of the materials of construction based on EN Standards in
4 proposal.
5
6 M20 The Package unit shall be constructed such that the majority of the equipment items are mounted on a minimum number of structures or skids for ease of installation.
7
8 M21 Inspection and Testing shall be in accordance with the requirements of the Material Requisition and its referenced documents and specifications.
9 As a minimum, the following works testing shall be included by SUPPLIER:
10 l Hydrostatic testing of all pressure containing items/parts
11 l Leak testing of relatively low pressure (atmospheric) items
12 l Mechanical run test of rotating machinery
13 l Performance testing of rotating machinery
14 l Functional testing to verify operation of control items/panels/systems
15 l Factory Acceptance Testing (FAT)
16 A Site Acceptance Test (SAT) will be required to verify overall process performance of the CPI Separator Package with actual waste water as feed.
17
18 M22 The SUPPLIER Package battery limits is shown on Page 9 of this data sheet and is based on Process Flow Diagram 3850-8110-20-3001, which is attached to the Material
19 Requisition. SUPPLIER shall be responsible for and include all necessary equipment, pipework and E&I materials within the designated Package boundary battery limits in
20 order to meet the requirements of this data sheet. Full detailed scope of supply will be detailed within the Material Requisition 3850-1946F/02.
21
22
23
24
25
26
27
28
29 ABBREVIATIONS
30 Abbreviation Definition
31 ATEX Equipment intended for use in explosive atmospheres
32 BPCS Basic Process Control System
33 C Carbon
34 C&I Control and Instrumentation
35 CPI Corrugated Plate Interceptor
36 DAF Dissolved Air Flotation
37 DCS Distributed Control System
38 DNF Dissolved Nitrogen Flotation
39 DS Dry Solids
40 ESD Emergency Shutdown System
41 FEED Front End Engineering Design
42 GFU Green Feed Unit
43 HCU Hydrothermal Clean-up Unit
44 HOI Hydrocarbon Oil Index
45 HPU2 Hydrogen Production Unit number 2
46 HRT Hydraulic Retention Time
47 HVO Hydrotreated Vegetable Oil
48 MBBR Moving Bed Biofilm Reactor
49 N Nitrogen
50 N/A Not Applicable
51 PED Pressure Equipment Directive
52 PFAS Per- and polyfluoroalkyl substances
53 PFOS Perfluorooctane sulfonic acid
54 SPL Sound Pressure Level
55 STA SUPPLIER to advise
56 TN Total Nitrogen
57 TOC Total Organic Carbon
58 TP Total Phosphorous
59 TSS Total Suspended Solids
60 WWTP Wastewater Treatment Plant
DSN: 2079
System of Units S.I.

EQUIPMENT DATASHEET

Wood CONTRACT No: 3850 PROJECT TITLE: Hydrotreated Vegetable Oil (HVO) FEED
Client CONTRACT No: 2457 SERVICE: CPI SEPARATOR PACKAGE

Rev.
CLIENT: Preemraff ITEM No.: 38T-5A/B No. REQD:Two (Duty / Standby)
LOCATION: Gothenburg, Sweden Wood Document No.3850-8470-DS-3807
REV O1
DATE 11/15/2022 PAGE: 9 OF 9
1
2 SKETCH SHOWING BASIC PACKAGE BATTERY LIMITS
3
4
5
6
7
8
9
10 Nitrogen Gas supply for
blanket under tank cover
11
12
13
Demulsifier Feed
14
15
16
Bypass to
17 CPI Clean Water
18 Sump (38D-7)
19
20
21
22 Waste Water Feed
from existing Inlet To CPI Clean
23 Basin Water Sump
(38D-7)
24
25
26
27
28
29 CPI SUPPLIER
30
31
BUYER
32
33
34 To Oil Sump (38D-12) CPI Sludge to Desludge Pump
35 (38G-6A/B)
& Sludge Thickener (38D-24)
36
37
38
39
40 Points to Note:
41 1. SUPPLIER shall provide flanged connections for all piped terminations at package boundary limits (Note M14).
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
DSN: 2079