Design Procure prototype parts Assemble test Laboratory test Field test Adjust design Order stock components

est Laboratory test Field test Adjust design Order stock components Assemble test production unit Test unit Document results
Start: Mar 29 '22 ID: 1 Start: Apr 12 '22 ID: 2 Start: May 03 '22 ID: 4 Start: May 09 '22 ID: 5 Start: May 18 '22 ID: 6 Start: Jun 02 '22 ID: 7 Start: Jun 14 '22 ID: 8 Start: Jul 05 '22 ID: 10 Start: Jul 19 '22 ID: 11 Start: Jul 26 '22 ID: 12
Finish: Apr 11 '22 Dur: 10 days Finish: Apr 29 '22 Dur: 10 days Finish: May 06 '22 Dur: 4 days Finish: May 17 '22 Dur: 7 days Finish: Jun 01 '22 Dur: 10 days Finish: Jun 10 '22 Dur: 6 days Finish: Jun 27 '22 Dur: 10 days Finish: Jul 18 '22 Dur: 10 days Finish: Jul 25 '22 Dur: 5 days Finish: Jul 28 '22 Dur: 3 days
Res: Res: Res: Res: Res: Res: Res: Res: Res: Res:

Order custom components


Start: Jun 14 '22 ID: 9
Finish: Jul 04 '22 Dur: 15 days
Res:

Fabricate parts
Start: Apr 12 '22 ID: 3
Finish: Apr 27 '22 Dur: 8 days
Res: