est Laboratory test Field test Adjust design Order stock components Assemble test production unit Test unit Document results
Start: Mar 29 '22 ID: 1 Start: Apr 12 '22 ID: 2 Start: May 03 '22 ID: 4 Start: May 09 '22 ID: 5 Start: May 18 '22 ID: 6 Start: Jun 02 '22 ID: 7 Start: Jun 14 '22 ID: 8 Start: Jul 05 '22 ID: 10 Start: Jul 19 '22 ID: 11 Start: Jul 26 '22 ID: 12
Finish: Apr 11 '22 Dur: 10 days Finish: Apr 29 '22 Dur: 10 days Finish: May 06 '22 Dur: 4 days Finish: May 17 '22 Dur: 7 days Finish: Jun 01 '22 Dur: 10 days Finish: Jun 10 '22 Dur: 6 days Finish: Jun 27 '22 Dur: 10 days Finish: Jul 18 '22 Dur: 10 days Finish: Jul 25 '22 Dur: 5 days Finish: Jul 28 '22 Dur: 3 days
Res: Res: Res: Res: Res: Res: Res: Res: Res: Res:
Fabricate parts
Start: Apr 12 '22 ID: 3
Finish: Apr 27 '22 Dur: 8 days
Res:
Project: MS Project emilie Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Apr 03 '22
Page 1