STATEMENT AND
LIFTING PROCEDURE FOR
SCRAP MATERIAL
DISMANTLE
TABLE OF CONTENTS
1) INTRODUCTION
2) ITEM TO BE HANDLED
3) PROPOSED MACHINERIES
4) LIFTING PLANNING
7) ATTACHMENT
a) Organization chart
b) Manpower details
c) Crane and Operator details
d) Crane Maintenance report
e) Lifting gear certification
1) INTRODUCTION
a. Purpose
This specific procedure for the lifting is prepared in order to ensure that the
lifting job is done in a proper and safely manner. All aspects of works have been
studied and considered. As the lifting contractor, this procedure will be the
guideline during executing of any tasks and completion of the works.
b. Objective
After safety induction and documentation are completed the crane lifting crew need
to gain access to the lifting area. They have to survey, study and analyzed thecrane
and the transporter lifting position and movement to ensure the safe execution of
the lift.
A supervisor and the crane crew will do this survey on the site area to determine if
any obstructions exist along the path of the crane and transporter movement.
Besides that, the crane crew will also make the actual marking on site to place the
steel support plate for the crane. These marks will help the other project crews to
place the steel plates earlier and ensure the smooth operation.
The following equipment are required for the preparation of the mobilization
access and the crane path area.
b. Other preparations
i. Execution meeting
All equipment shall undergo OWNER’s Safety Inspection and must fully
comply with client’s requirement. Documents to be submitted for
inspection:
• Crane’s 25 Ton
• Operators driving license
• Insurance cover notes
• DOSH certificates
• PUSPAKOM certificates
• Crane load chart
3) ITEM TO BE HANDLED
LIFTING PLANNING
TADANO TR-250M
DOC. NO. : ADMETAL/LP/001
MAX. BOOM LENGTH 30.5 Meter
22 mtr
TOTAL CAPACITY 25 Tonne
W. BOOM LENGTH 23.5 Meter 66°
WORKING RADIUS 10 Meter
CRANE CAPACITY 7400 kg
10 mtr
12 mtr
3500 kg
EQUIP. WEIGHT 2000 kg PART OF LINE
BIG BLOCK WEIGHT 0 kg ACTUAL LOAD/
2110 kg
SMALL BLOCK WEIGHT 60 kg PART OF LINE
RIGGING WEIGHT 50 kg
BUNDLE PULLER N/A kg
TOTAL WEIGHT 2110 kg
PERCENT OF CHAT
CAPACITY 28.51 %
SAFETY FACTOR 3.51 66°
CRANE
10 mtr
RIGGING GEAR 3t X 6m X 2nos Tonne & Qty 25 ton
SHACKLES N/A Tonne & Qty
radius 10 mtr
CRANE LOAD CHART
Refer to Load Chart TADANO TR-250M
LIFTING PLAN
To lifting Beam
PREPARED BY : SYAHRUNNIZAM SHAFIE APPROVED BY :
A A
9.5m 16.5m 23.5m 30.5m 9.5m 16.5m 23.5m 30.5m
B B
3.5m 25.0 19.0 12.5 7.0 3.5m 25.0 19.0 12.5 7.0
4.0m 23.0 19.0 12.5 7.0 4.0m 23.0 19.0 12.5 7.0
4.5m 21.2 18.0 12.5 7.0 4.5m 21.2 18.0 12.5 7.0
5.0m 19.4 16.7 12.5 7.0 5.0m 19.4 16.7 12.5 7.0
5.5m 17.8 15.6 11.85 7.0 5.5m 17.8 15.6 11.85 7.0
6.0m 16.3 14.6 11.2 7.0 6.0m 16.3 14.6 11.2 7.0
6.5m 15.1 13.8 10.6 7.0 6.5m 15.1 13.8 10.6 7.0
7.0m 13.7 13.0 10.1 7.0 7.0m 13.0 12.6 10.1 7.0
a ( °) 0 ∼ 83 a ( °) 0 ∼ 83
− 414 −
TR-250M-7-00101
JI
B
JI
B
NOTES:
1. The deflection of the boom is not incorporated in the figure above.
2. The figure above is for the case where the outriggers are fully extended (360°).