MH-7560-00-02 Rev. 0 Page 3 of 14
PURPOSE
This method statement is intended to outline the activities for lifting overturning and
erection of Tube BUNDLE with roof panel in to Evaporator bottom sections. The major
works includes but not limited to Hiring / procurement of lifting equipments and tools,
Equipment location arrangements for Lifting and Erection of BUNDLE
RESPONSIBILITIES
Production/Site Manager:
Production / Site Manager is fully on behalf of Project Manager to manage all the
activities happen on site, directly report to the Project Manager with Responsible for
ensuring that all works are performed in accordance with this procedure
Project Engineer:
Responsible for the overall planning, coordination and control of the job
Production Engineer:
Responsible for field erection work implementation and maintaining acceptable quality
standard.
Safety Engineer:
Responsible for ensuring that all activities are carried out in a safety manner and
compliance with the established safety procedure
MATERIALS LIST
1 Main Lift Crane: Crawler Crane 350 MT Capacity 1
2 Tailing Crane: Crawler Crane 110 MT Capacity 1
3 Service Crane-1: Mobile Crane 100 MT Capacity 1
4 Service Crane-2: Mobile Crane 50 MT Capacity 1
5 Spreader Beam Capacity 90 Metric Ton 18 Meter Length 1
6 Spreader Beam Capacity 40 Metric Ton 20 Meter Length 1
7 70 mm Dia Wire Rope Length 12000mm 4
8 35 Ton Capacity Wire Rope Length 12000mm 4
9 33 Ton Capacity Wire Rope Length 3000mm 8
10 70 mm Dia Wire Rope Length 6000mm 2
11 Shackles 55 Ton Capacity 6
12 Shackles 35 Ton Capacity 24
MH-7560-00-02 Rev. 0 Page 4 of 14
SAFETY
1. Rigging must be made on Day Time and the wind must be below 30KmPh
2. Bearing Surface of Pins of Shackles and Lug Eyes of Slings Etc that turn during
erection are to be greased before making lift
3. One authorized person only will give instruction to the operators and Lifting
Crew.
4. The workers working on job site must be equipped with minimum PPE
TECHNICAL INFORMATION
Item No : Evaporator Roof Bundle (13 Nos.)
Size (L x B x H)
: 24400 x 11700 x 4500
Maximum
Weight of Largest
: 76000 Kgs. (Maximum Weight)
Bundle
TAILING CRANE
CRANE : 110 Metric Ton KOBELCO Crane
Boom Length : 24400mm
Working Radius : 5000mm
Lifting Capacity : 77000 Kgs at 5000mm WR & Boom Lg 24400mm)
Counter Weight : 34500 Kgs
Weight of Lifting Gears : 8000 Kgs (Spreader Beam, Slings, Shackles Etc)
Weight of Crane Hook : ~1700 Kgs (120 Ton Cap. Hook)
Total Rigging Weight : 92000 Kgs
SERVICE CRANES
CRANE- 1 : 100 Metric Ton MOBILE Crane
CRANE- 2 : 50 Metric Ton MOBILE Crane
Total Rigging Weight : 92000 Kgs
MH-7560-00-02 Rev. 0 Page 5 of 14
BUNDLE LIFTING
Preparation-1: 90 Ton Spreader Beam and Slinging Arrangement
Positioning of 350 Ton Capacity Lifting Crawler Crane, outfitted with 90 Ton
Spreader Beam, slings, shackles etc. as per below Sketch
Transport the bundle by 650 Ton SPMT, to designated erection area and
positioned as indicated in above sketch. Connect securely all slings from both
cranes to the BUNDLE lifting pad eyes as indicated in the above sketches.
MH-7560-00-02 Rev. 0 Page 8 of 14
Sequence
Lift the BUNDLE slightly by main Lifting Crane and Tailing Crane including 2
service cranes, Simultaneously in order to release SPMT
After releasing the SPMT, Slowly raise the BUNDLE in tandem, until it is in
the position indicated in the Sketch-1
Main Crane (350MT) slowly raise the BUNDLE upwards, while the tail crane
and 2 service cranes slowly release the hooks, until the bundle reach in
vertical position as indicated in the sketch-1
ELEVATION showing the First Lift of BUNDLE with Main Lift Crane & Tailing
Cranes
MH-7560-00-02 Rev. 0 Page 9 of 14
BUNDLE OVERTURN
Sequence
Boom Swing ~55° as indicated below Sketch
Adjust the Boom while rotating the Bundle in order to maintain the safe
working radius.
MH-7560-00-02 Rev. 0 Page 10 of 14
Once the bundle reach in lifting position, connect Tailing Crane with 4 Nos
33Ton X 3000mm Long wire rope (Remove existing 12000mm long rope) and 2
Service Cranes for 90° Vertical Turn as shown below sketch.
Sequence
Connect the Tailing Crane at center and 2 service cranes either sides
Min Lift crane Boom up and hook down slowly until in order to reach the
bundle in horizontal position as shown below sketch
BUNDLE ERECTION
After the BUNDLE reach in horizontal position at 12500mm level, release 2
service cranes in order to march both Main Lift Crawler Crane and Tailing
Crawler cranes with BUNDLE as shown below layout
MH-7560-00-02 Rev. 0 Page 14 of 14
Sequence
Slowly move both Main Lift crawler crane and Tailing Crawler Crane
simultaneously, towards the bottom section location.
Move the Bundle up to directly above position on the top of the Bottom
Section Assembly
Once the alignments and match markings are accepted, slowly erect the
Roof Bundle in to the Bottom Section
-------00000------