Professional Documents
Culture Documents
TABLE OF CONTENT
Scope
Reference Documents
Responsibility
Sequence of HYDROTEST
SEQUENCE: 3
Technical Data
Hydrotest Apparatus
Hydrotest Preparations
Pressure Gauges
Test Procedures
Pressurizing
Inspection of Evaporator
Draining
REFERENCE DOCUMENTS
• ASME SECTION VIII (2010 Ed)
• TEMA C (9th Ed.) & Manufacturer’s Standards
• 70-GDG-MTC-001 : Evaporator General Assembly
• 70-GDG-MTC-069 to 75: WATER BOX RECOVERY Section
• PR-7560-PRT-001 : Pressure test Procedure
RESPONSIBILITY
After completion of all welding, Pickling, Passivation of SS areas and required
inspection activities, the site construction Department shall carry out the necessary
arrangements for conducting the hydrostatic test as detailed in this procedure. The QC
Department is responsible for the inspection and to inform Clients Inspector to witness
testing.
SEQUENCE OF HYDROTEST
The proposed Hydro test sequence shall be as follows
• Sequence 6: Shell Side Hydro Pneumatic test- Stage 1 to 26 & Deaerator (MH-
7560-00-07-SEQ1)
MH-7560-00-07-SEQ-3 Rev. 0 Page 4 of 10
METHOD STATEMENT FOR EVAPORATOR HYDRO TEST
SEQUENCE 3:
Tube Side Hydro test- Stage 18 to 13
2. BOLT TORQUE (Valid for RECOVERY Section Inlet and Out Let Flanges)
Location Flange Size Bolt A540-B23 Torque (KgM)
Stage 18 to 13
(Brine Side and
Distillate side)
M33 x 265 mm
Double Water 3244 x 3812 x (75 +75) 210 to 250
Lg x 114 Nos
box to
Intermediate
Piece
Stage 18, 13
(Distillate Side)
Dummy Water M33 x 265 mm
3244 x 3812 x (75 +75) 210 to 250
Box and Lg x 114 Nos
Intermediate
Piece
2” ASME 150# x 6 5/8” x 90mm x 4 Standard
Vent Nozzles
Sets Each Each Torque
3” ASME 150# x 6 5/8” x 100mm x Standard
Drain Nozzles
Sets Each 4 Each Torque
MH-7560-00-07-SEQ-3 Rev. 0 Page 6 of 10
METHOD STATEMENT FOR EVAPORATOR HYDRO TEST
4. TEST PRESSURE-
See Below Pressure Test Chart
10 Wrench
MH-7560-00-07-SEQ-3 Rev. 0 Page 8 of 10
METHOD STATEMENT FOR EVAPORATOR HYDRO TEST
11 Hydro Test Manifolds (Filling Line,
Pressure Indicator and Pressure
Relief Valve)
PRESSURE GAUGES
• Two numbers of dial indicating gauges shall be directly connected to coil, one at
the upper portion and the other at the lower portion.
• The gauges shall be calibrated against a standard deadweight tester.
• The pressure gages shall be graduated over a range of about double the
intended pressure but in no case shall the range be less than neither 1.5 nor
more than 4 times that the test pressure.
TEST PROCEDURE
PRESSURIZING
• The test pressure shall not be applied until the metal and water are about the
same temperature.
• Before applying pressure, the Water box bundle shall be examined to see that it
is tight and that all low pressure filling lines and other appurtenances that should
not be subjected to the pressure have been disconnected.
• The Water box surface temperature shall be maintained minimum 10 ° C
throughout the testing cycle.
• The pressure shall increase slowly to the required test pressure as indicated in
above pressure Test Chart.
MH-7560-00-07-SEQ-3 Rev. 0 Page 10 of 10
METHOD STATEMENT FOR EVAPORATOR HYDRO TEST
• Hydrostatic pressure shall be held for a minimum 10 Minute, at the design
pressure. During this period, the RECOVERY tube bundles and water boxes
shall have no leakages.
• Check any leakage or water tracing from both brine and distillate side Tube
expansions. This can be inspected from inside of Trough stage 18 to 13
• Once the inspection found satisfactory, the hydro test pressure then shall be
increased up to 11.27 Bar G. Measured on the shell top of the stage 13. (See
Hydro test Layout)
• The test pressure shall be maintained for 30 Minutes. During this period, the
RECOVERY tube bundles and water boxes shall have no leakages.
DRAINING
• After completion of hydrostatic pressure holding time, the pressure shall be
released slowly from top point by opening the vent.
• When the pressure inside the water boxes is equal to -0- Bar G, each water box
vent connection shall be sequentially open staring from stage 18 to 13
RECOVERY SECTION CONSERVATION
After completion of draining and venting of the tube bundle, close all the
connections nozzles used for draining / venting of the tube bundle shall be closed
properly in order to prevent the entry of dust and other contaminations. These
stages shall be maintained in this closed condition till the final piping connection
------0-----