EPA BUILDING: SUMMARY OF COMPLETION BILL (PHASE 2)

1. Completion of Works by a nominated Sub Contractor - - 6,733,733.36

2. Add 5% Consultancy - - - - - - - 336, 686.67

3. Add Additional Works including Green House


Construction & Installation - - - - - - 1,450,000.00

4. Project Management - - - - - - - 800,000.00

5. Project Financing & Fund Syndication - - - - 2,895,794.90

TOTAL - - - - - - - - - N12,216,214.93
EPA BUILDING: SUMMARY OF COMPLETION BILL (PHASE 1 & 2)

(A) Preliminaries - - - - - - - - - 797,000.00

(B) Main Building Works - - - - - - - 6,993,564.17

(C) Drivers Room/Security Post - - - - - - 47,167.46

(D) External Works - - - - - - - - 1,894,340.60

(E) PS & PC - - - - - - - - - 879, 890.00

(F) Sub – Total - - - - - - - - 10,611,962.23

(G) Add GST - - - - - - - - - 12,203,756.57

(H) Add Phase 1 Consultancy - - - - - - 433,761.86

(I) Add Phase 2 Consultancy - - - - - - 336,686.67

(J) Additional Works: Green House, etc - - - - - 1,450,000.00

(K) Project Management - - - - - - - 800,000.00

(L) Project Financing and Fund Syndication - - - - 2,2895,794.97

TOTAL - - - - - - - - - 18,120,000.00
DRAWINGS:

(Produced by Tropical Environmental Design Associates)

Drawings considered satisfactory.

BILL OF QUANTITIES

(Produced by Tropical Environmental Design Associates)

BOQ considered satisfactory.

PHASE 1 CONSTRUCTION

(Construction by Sierra Leone Construction Company Ltd) Construction

Considered Ok; but necessary QA/QC tests to be carried out by Contransar International.

CABINET LETTER

Comment: Letter Ok, Except that it should not be specific that Government funding is 0%.

We recommend: Government direct funding is zero as this is a special vessel BOT/PPP Project

for a period of 10 years only. Monies for paying back funds raised to complete the project will

come from other sources such as climate change fund, etc.