NOTE NO -1

Name of the Work :- Construction of Sudhanwa DebBarma Memorial H.S.School at


Jampuijala,Sepahijala District,Tripura/SH:-Building portion including internal water supply and sanitary
installation(Ground floor only).

Name of the Agency:- Sri Jahar Sur Chowdhury


Agmt. No:- 28/AGGMT/B/PC(PD-II)/SE-IV/EE-BRG/PWD/2016-2017

Ref : No.F.18(1))/SE-IV/W/(S-4)/2574-75, Dated: 06/07/2018 of the Superintending Engineer, 4th


Circle, PWD(R&B), Agartala.Tripura West.

Tentative Deviation statement in Higher side along-with Tentative extra item and Tentative Substitute
item statement of `Rs 27,99,962.00,Rs 32,74,307.00 and Rs2,51,338.00 respectively respectively has
been forwarded to the Chief Engineer, PWD(Building),Agartala by the SE, 4th Circle, PWD(R&B)
Agartala.

Concerned EE & SE already provisionally approved their respective financial power and the
balanced amount of Tentative deviation,Tentative extra item and Tentative substitute items of
Rs.21,19,962.00, Rs 25,97,381.00 and Rs 2,51,338.00 respectively required for kind approval of the
Competent Authority.

During Scrutiny of the Statement following observations are found :-

A Estimated cost put to tender on SoR-2011 Rs.3,78,54,442.00

B Agreement Amount Rs.4,12,27,273.00


C Clause-XII. [ On TSR-2011 ] @8.91% above
D Total Tentative Extra item amount (higher side) Rs.32,74,307.00

i) Approved by the EE, Bishramganj PWD(R&B) Division. [against Rs.78,766.00


E.I. No.19,20,21,22 only ]
ii) Approved by the SE,4th Circle, PWD (R&B), Agartala, Tripura Rs 5,98,160.00
[against E.I. No. 1 ,2,4,17,18 and 26)

Balance amount Rs 25,97,381.00

iii) Balance amount is required to be approved by the Addl. Chief Rs 9,06,940.00


Engineer, Project Unit, PWD(Buildings).
[against E.I. No. 5,6,7,8,9,10,11,12,13,14,15,16,23,24,25,27)

iv) Balance amount is required to be approved by the Chief Engineer, Rs 16,90,441.00


PWD(Buildings).
Chief Engineer, Project Unit, PWD(Buildings).
[against E.I. No.3)

E Total Tentative Substitute item amount (higher side) Rs 2,51,338

1 of 14
i) Approved by the EE, Bishramganj PWD(R&B) Division. Nil

ii) Approved by the SE,4th Circle, PWD (R&B), Agartala, Tripura Nil

Balance amount Rs 2,51,338

iii) Balance amount is required to be approved by the Addl. Chief Rs,5129.00


Engineer, Project Unit, PWD(Buildings)[against S.I. No.2).

iv) Balance amount is required to be approved by the Chief Engineer, Rs 2,46,209.00


PWD(Buildings). [against S.I. No.1(a),1(b)

G Total amount to be executed. Rs.4,40,27,235.00

(which is @ 6.79% on
Higher side)
H Total Tentative deviation Amount( D – B) Rs.27,99,962.00
i) Approved by the EE, Bishramganj PWD(R&B) Division. Rs,80,000.00

ii) Approved by the SE,4th Circle, PWD (R&B), Agartala, Tripura Rs,6,00,000.00

Balance amount Rs 21,19,962.00


iii) Balance amount is required to be approved by the Rs 10,00,000.00
Addl. Chief Engineer, Project Unit, PWD(Buildings).
iv) Balance amount is required to be approved by the Rs,11,19,962.00
Chief Engineer, PWD(Buildings).

(I) TANTATIVE EXTRA ITEMS STATEMENT :

Rate Considered for Extra item no 1,2,4 to 19 as TSR-2011 - @ 8.91 % above ( Agg. Clause -
XII),Hence rate may be accepted

Rate Considered for Extra item no 20 to 25 as DWS SoR-2010- @ 8.91 % above ( Agg. Clause -
XII ),Hence rate may be accepted

Rate Considered for Extra item no 26,27 as analysis rate,Hence rate may be accepted

Rate Considered for Extra item no 3 are based on TSR 2011


Final rate of Extra item no 3 arrived as = rate as TSR-2011 - 50 mtr manual head(from Basic rate of
carriage as per SOR 2011) - not use of road roller(as per TSR 2011) + 2.00 km mechanical transport
( from Basic rate of carriage as per TSR 2011),Hence rate may be accepted

(J)TANTATIVE SUBSTITUTE ITEMS STATEMENT :


Rate Considered for all Substitute Items as SoR-2011 - @ 8.91 % above ( Agg. Clause -XII)

K) Quantum of deviation of agreement item:-


Item wise specific reasons for deviation in savings in the agreement items are explained in the
tentative deviation statement.

2 of 14
The few Agreement items are tabulated below whose amounts exceeds more than Rs. 2.00 lakhs
from the agreement amount
A.I.N
O Agreement items Amount(Rs) Remarks
A.I.N Earth work in excavation in over As per requirement of site,item has beem executed hence excess
o:- areas
1(b). b)by Mechanical means 314764.00

A.I.N Reinforcement for RCC work The Building drawing and design has been propared for
o:-13. Thermo mechanically treated bar double/tripple storied.At this stage,the building has been
constructed in single storied.Further extension of double storied
635886.00 192 nos column steel has been extended in minimum 1.5 metre
height over ground floor roof i.e 1st foor.Accordingly excess

A.I.N Centering and shuttering As per necessity of item has been executed.Hence excess
o:-16. e)Column and pillars 218136.00

A.I.N. Polished vitrified floor tiles


-47 size of tile 60x60 cm This item has been executed as per architect proposed in the
321569.00 approved drawing and plan.But provision of estimate in lower
side accordingly excess.

Extra items are tabulated below


Amount in
SL No Description of items Remarks
execution (Rs)
E.I.No Supplying chemical emulsion For construction of new building ,these items are abosolutely
:-1. i)Chloryriphose/Lindane mandatory but it was beyond the scope of Agreement,hence
emulsitiable concentrate of 20% executed as extra items
190353.00

E.I.No Diluting and injecting chemical For construction of new building ,these items are abosolutely
:-2. emulsion for preconstruction mandatory but it was beyond the scope of Agreement,hence
anti-termite 175437.00 executed as extra items
treatement(excluding the const
fo chemical emulsion

E.I.No Earth work in rough Considering the site condition and also for beautification of the
:-3. excavation(by mechanical courtyard & the building surroundings,mechanical earth filling is
means) lead upto 2.00 km and extremely needed.But this item of mechanical earth fillling is
lift upto 1.50 m beyond the scope of Agreement.hence treated as extra item.The
1690441.00
matter was also discussed & intimated with the higher authority
vide this office letter no.F.5(51)/SDO?PWD/TKJ dated
07/11/2017

E.I.No half brick masonry work with Plinth protectin in/c drain work,this item is necessary but this
:-4. first class brick in foundation(1): 69643.00 item beyond the socpe of agreement.Hence executed as an extra
item.

E.I.No Cutting holes upto 15 x15 cm in Rain water and other drainage pipe has been fitted & fixed for
:-5. rcc floors and roofs clearing of rain water and other foreign materials.At the time of
14644.00 execution this item is needed.But this item beyond the scope of
agreement.hence ececuted as an extra item.

E.I.No Cutting holes upto 30 x30 cm in Rain water and other drainage pipe has been fitted & fixed for
:-6. wall in/c clearing of rain water and other foreign materials.At the time of
26910.00 execution this item is needed.But this item beyond the scope of
agreement.hence ececuted as an extra item.

3 of 14
E.I.No providing and laying rectified This item has been executed as per architect proposed in the
:-7. glazed ceramic floor tiles 758697.00 approved drawing and plan.But this item beyond the scope of
300x300 mm agreement.hence ececuted as an extra item
E.I.No Providing and fixing panelling This item is necessary for Doors clearestory portions but it was
:-8. &glazing in doors and windows 11995.00 beyond the scope of Agreement,hence executed as extra items

E.I.No Plain bend of required degree As per necessity of sanitary & waste pipe lines,this item has been
:-9. 100 mm 15042.00 executed. but it was beyond the scope of Agreement,hence
executed as extra items

E.I.No Bend of required degree with as per necessity of sanitary & waste pipe lines,this item has been
:-10 acces doors 11496.00 executed. but it was beyond the scope of Agreement,hence
100 mm executed as extra items

E.I.No White vitreous china flat back No such provision in the agreement for gents toilets urinal
:-11. urinal basin of 430x260x350 basin.But at the time of execution( as per architect drawing)
mm and 340x410x265 mm 6928.00 8(eight) nos urinal basin have been provided in the toilet of
gents.hence as an extra item.
E.I.No Providing and fixing white No such provision in the agreement ladies toilet squatting
:-12. vitreous china squatiting plate plate..But at the time of execution( as per architect drawing)
urinal with integral rim 4620.00 8(eight) nos urinal basin have been provided in the toilet of
longitudinal flush pipe gents.hence as an extra item.

E.I.No Unplasticised pvc connection as per necessity ,this item has been executed. but it was beyond
:-13 pipe with brass 2799.00 the scope of Agreement,hence executed as extra items
15 mm nominal bore

E.I.No PTMT pillar cock as per necessity ,this item has been executed. but it was beyond
:-14. 15 mm nominal bore 2545.00 the scope of Agreement,hence executed as extra items

E.I.No PTMT grating of approved as per necessity ,this item has been executed. but it was beyond
:-15. quality 1673.00 the scope of Agreement,hence executed as extra items
100 mm nominal bore

E.I.No Aluminium tower bolts isi as per necessity ,this item has been executed. but it was beyond
:-16. marked 1478.00 the scope of Agreement,hence executed as extra items
a)100x10 mm

E.I.No steel work in build up tubular The school building drawing and design has been made for
:-17. trusses double/tripple storied.But at this stage work has been executed in
single storied.In this regards stair room roof has been constructed
50575.00 semi-permanent.Before GI sheet roofing tubular trusses work is
necessary,accordingly executed as an extra item.

E.I.No G.S sheet roofing The school building drawing and design has been made for
:-18. 0.63mm thick with zinc coating double/tripple storied.But at this stage work has been executed in
81102.00 single storied.In this regards stair room roof has been constructed
semi-permanent i.e GI sheet roofing.Hence executed as an extra
item.

E.I.No Sheet covering over expansion This item is absolutely mandatory for expansion portions.But
:-19. joints with inon scres 39319.00 this item is not included in the aggt,Hence it is treated as extra.

E.I.No Drilling and boring pilot hole There is no sustainable water source for providing portable
:-20. drinking water to the new school building.As a result,we have
executed SBDTW(By manual means) assembly to the under
12808.00 ground reservoir and boosting the same to the overhead
tanks(sintex).Hence as an extra item.

4 of 14
E.I.No Reaming of pilot hole to an There is no sustainable water source for providing portable
:-21. enlarged bore hole drinking water to the new school building.As a result,we have
executed SBDTW(By manual means) assembly along with all
16129.00 accessories for clear water raising to the under ground reservoir
and boosting the same to the overhead tanks(sintex).Hence as an
extra item.

E.I.No Providing and lowering of upvc There is no sustainable water source for providing portable
:-22. pipe drinking water to the new school building.As a result,we have
A)CM casing pipe i) 100 mm executed SBDTW(By manual means) assembly along with all
dia 10510.00 accessories for clear water raising to the under ground reservoir
and boosting the same to the overhead tanks(sintex).Hence as an
extra item.

E.I.No Washing and development of There is no sustainable water source for providing portable
:-23. tube well by using hand pump drinking water to the new school building.As a result,we have
executed SBDTW(By manual means) assembly along with all
1339.00 accessories for clear water raising to the under ground reservoir
and boosting the same to the overhead tanks(sintex).Hence as an
extra item.

E.I.No providing and shrouding of the There is no sustainable water source for providing portable
:-24 deep tube well assembly drinking water to the new school building.As a result,we have
i) Pea gravels obtained from executed SBDTW(By manual means) assembly along with all
Durgapur,west bengal 7462.00 accessories for clear water raising to the under ground reservoir
and boosting the same to the overhead tanks(sintex).Hence as an
extra item.

E.I.No Installation of submersible pump There is no sustainable water source for providing portable
:-25 motor upto a depth of 100 ft by drinking water to the new school building.As a result,we have
G.I pipe executed SBDTW(By manual means) assembly along with all
20913.00 accessories for clear water raising to the under ground reservoir
and boosting the same to the overhead tanks(sintex).Hence as an
extra item.

E.I.No fixing of 2HP(kiloskar make There is no sustainable water source for providing portable
:-26 submersible pump set drinking water to the new school building.As a result,we have
executed SBDTW(By manual means) assembly along with all
31050.00 accessories for clear water raising to the under ground reservoir
and boosting the same to the overhead tanks(sintex).Hence as an
extra item.

E.I.No fixing of 2HP Manu Block pump Lifting of water from underground water reservoir to last roof of
:-27 set the building(i.e sintax tank),motor & pump is necessary.but this
18399.00 item beyond the scope of agreement hence executed as an extra
item

Substitute items are tabulated below


Amount in
SL No Description of items Remarks
execution (Rs)
S.I.No Providing and fixing 18 mm These items have been executed in stair step,landing and
:-1(a). thick marble stone in floor Ent.Corridor portion.But as per agreement provision has been
221918.00 kept for granite marble stone.Hence executed 18 mm thick
marble stone in lieu of granite stone.Accordingly substitute

S.I.No Extra for providing edge These items have been executed in stair step,landing and
:-1(b). moulding to 18 mm thick marble Ent.Corridor portion.But as per agreement provision has been
stone 24291.00 kept for granite marble stone.Hence executed 18 mm thick
marble stone in lieu of granite stone.Accordingly substitute

S.I.No PTMT towel ring trapezoidal At the time of execution of work agreemental material was not
:-2. shape 215 mm long 5129.00 available in the local market.Hence executed as substitute item.

5 of 14
L.)REMARKS & RECOMMENDATION :

Concerned EE & SE has approved full financial power as per DFPRT-2011

Now Additional Chief Engineer , Project unit, PWD(Building) has to approve:

Balanced amount of Tentative Extra item (higher side)= Rs 9,06,940.00


Balanced amount of Tentative Substitute item (higher side)= Rs.5129.00
Balanced amount of Tentative Deviation (higher side)= Rs10,00,000.00

Now Chief Engineer , PWD(Building) has to approve:


Balanced amount of Tentative Extra item (higher side)= Rs 16,90,441.00
Balanced amount of Tentative Substitute item (higher side)=Rs,2,46,209.00
Balanced amount of Tentative Deviation (higher side)=Rs 11,19,962.00

Put up for your kind perusal & necessary action please.

(Er. D.Sarkar)
Assistant Engineer
Project Unit, PWD(Buildings)
Agartala, Tripura (W)

6 of 14
EXTRA ITEMS ANALYSIS OF RATES SHOWING THE CALCULATION FOR FINDING OUT THE FINAL RATES
INCLUDING LOADING, UNLOADING & HAULAGE
Name of work:- Renovation of P.W.D. sub-divisional office building , Kathalia during the year 2011-2012. No.3/DNIT/E.E/SNM/2011-2012
ITE BRIEF UNIT MATERIALS
QTY. OF MATERIALS
LOADING HAULAGE
DESCRIPTIO RATE&ITEM
M N REQUIRED REQUIRED UNLOADING
NO.AS PER
NO SOR-2008 Gravelled Katcha Final -
Rate Rate
FOR In cum/t Weight In t Amount Amount Surfaced road road track Amount Rate(Rs.)
BUILDING
WORKS co-
efficient
Km. Rate Km. Rate Km. Rate
1 Earthwor
k in
excavatio
n 82.5 cum _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 82.5
Filling in
2 trenches 35.5 cum _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 35.5
sand
3 filling 411.2 cum sand 1.2 1.84 2.208 25.3 55.862 15.5 34.224 10 2.1 0 2.7 0 4.5 46.368
55.862 34.224 46.368 547.654
4 pcc(1:3:6) 4278 cum cement 0.22 1 0.22 60.4 13.288 60.4 13.288 20 2.1 0 2.7 0 4.5 9.24
fine sand 0.45 1.84 0.828 25.3 20.948 15.5 12.834 10 2.1 0 2.7 0 4.5 17.399

stone aggt 4514.747


20mm 0.675 1.9 1.282 49.5 63.483 25.3 32.434 20 2.1 0 2.7 0 4.5 53.844
97.719 58.556 80.472
5 RCC for slab cement 0.4 1 0.4 60.4 24.16 60.4 24.16 20 2.1 0 2.7 0 4.5 16.8
(1:1.5:3) 7209.3 cum sand 0.45 1.84 0.828 25.3 20.948 15.5 12.834 10 2.1 0 2.7 0 4.5 17.388
stone aggt 0.9 1.9 1.71 49.5 84.645 25.3 43.263 20 2.1 0 2.7 0 4.5 71.82
125.753 80.257 106.008 7521.315
RCC for
6 columns
(1:1.5:3) 7973.8 cum cement 0.4 1 0.4 60.4 24.16 60.4 24.16 20 2.1 0 2.7 0 4.5 16.8
sand 0.45 1.84 0.828 25.3 20.948 15.5 12.834 10 2.1 0 2.7 0 4.5 17.388
stone aggt 0.9 1.9 1.71 49.5 84.645 25.3 43.263 20 2.1 0 2.7 0 4.5 71.82
125.753 80.257 106.008 8285.833
ITE BRIEF UNIT MATERIALS LOADING HAULAGE
DESCRIPTIO RATE&ITEM QTY. OF MATERIALS
M N NO.AS PER REQUIRED
NO SOR-2008 REQUIRED UNLOADING Final -
Gravelled Katcha
FOR
In cum/t In t Rate Amount Rate Amount Surfaced road road track Amount Rate(Rs.)
BUILDING
WORKS Weight co-
efficient Km. Rate Km. Rate Km. Rate
7 RCC for
bands 8392.6 cum cement 0.4 1 0.4 60.4 24.16 60.4 24.16 20 2.1 0 2.7 0 4.5 16.8
sand 0.45 1.84 0.828 25.3 20.948 15.5 12.834 10 2.1 0 2.7 0 4.5 17.388
stone aggt 0.9 1.9 1.71 49.5 84.645 25.3 43.263 20 2.1 0 2.7 0 4.5 71.82
125.753 80.257 106.008 8704.615
8 TMT Bars 64 kg TMT Bars 0.0011 1 0.0011 64.4 0.07 64.4 0.07 20 2.1 0 2.7 0 4.5 0.0462
0.07 0.07 0.0462 64.186
9 Brick works 3170.1 cum cement 0.05 1 0.05 60.4 3.02 60.4 3.02 20 2.1 0 2.7 0 4.5 2.1
sand 0.2 1.84 0.368 25.3 9.31 15.5 5.704 10 2.1 0 2.7 0 4.5 7.728
12.33 8.724 9.828 3200.982

Premium
10 acrylic paint 70.7 sqm paints 0.0004 1 0.0004 71.3 0.0285 66.6 0.0266 20 2.1 0 2.7 0 4.5 0.0168
0.0285 0.0266 0.0168 70.771
11 steel works 61.4 kg MS Flat 0.0007 1 0.0007 64 0.0448 64 0.0448 20 2.1 0 2.7 0 4.5 0.029
MS bar
12mm dia 0.0004 1 0.0004 64 0.025 64 0.025 20 2.1 0 2.7 0 4.5 0.016
Priming coat 0.001 1 0.001 73.3 0.0733 66.6 0.0666 20 2.1 0 2.7 0 4.5 0.042
0.143 0.136 0.087 61.766
Pointing in
brick
12 flooring cement 0.0046 1 0.0046 60.4 0.27784 60.4 0.27784 20 2.1 0 2.7 0 4.5 0.1932
with cement
mortar 1:3 71.5 sqm sand 0.00115 1.84 0.0022 25.3 0.05566 15.5 0.0341 20 2.1 0 2.7 0 4.5 0.0924
0.3335 0.31194 0.2856 72.431
FINAL EXTRA ITEM STATEMENT
NAME OF WORK :- Renovation of P.W.D. sub-divisional office building , Kathalia during the year 2011-2012. No.3/DNIT/E.E/SNM/2011-2012
Agreement No :- 10/E.E/SNM/2011-2012 Name of Agency :- Md. Sultan Miah
ITE HOW THE COST
HOW THE RATE
M DESCRIPTION OF ITEMS QUANTITY RATE UNIT AMOUNT REMARKS
ARRIVED WILL BE MET UP
NO
(SOR-2008+CL-
XII,i.e.7%Above)
1 2 3 4 5 6 7 8 9
Earthwork in excavation in all kinds of soil over areas (exceeding average depth
of 30 cm, 1.5 m in width as well as 10 sqm on plan ) including disposal of
The newly constructed office building
excavated earth lead up to 50 m outside the periphery of the area and lift upto
for office of the SDO, P.W.D.(R&B)
1.5 m, disposed earth to be leveled and neatly dressed as per clauses of
Kathalia sub-division is left uncrard.
Chapter - 2 of CPWD specification. a)
Against the The construction of boundary wall is
Without dewatering
E.I. sanctioned of essential for protection of the Govt.
asset. In addition extra quantity
No: 93.975 88.275 cum 8296.00 82.5+5.275 construction of
required for construction of
-1 kathalia office
drain,boundary wall,columns in the old
building
PWD office complex.Since all the
items are not provided in the
agreement. This will be executed by
way of extra item.

Filling in trenches, plinth, under floor, sides of foundations etc. with available
E.I. excavated suitable soil in regular horizontal layers, each not exceeding 200 mm
No: in depth with all lead and lifts, consolidating each layer by watering and 37.985 37.985 cum 2380.00 35.5+2.485 - Do - - Do -
-2 ramming with steel rammers or 1/2 tonne roller as per clauses of Chapter - 2 of
CPWD specification.

Filling in trenches, plinth, under floor, foundations etc. as per design with sands
E.I. with all lifts, transporting to site, spreading in regular horizontal layers, watering,
No: grading to required slope and compacting each layer by using plate compactor
or by any suitable method as per clauses of Chapter - 2 of CPWD specificatio 12.685 585.989 cum 7433.00 547.654+38.33
5
- Do - - Do -
-3 ii) with fine sand
obtained from local qaurry.

Providing and laying in position cement concrete of specified grade


including the cost of Form work, all work upto plinth level as per
E.I. clauses of Chapter - 4 of CPWD specification.
No: v) 1 : 3 : 6 ( 1 cement : 3 fine sand 10.812 4830.779 cum 52230.00 4514.747+316.
032
- Do - - Do -
-4 : 6 graded stone aggregate of 20 mm nominal size)
70339.00
Providing and laying in position reinforced cement concrete of
specified grade including the cost of Form work, but excluding The quantity considered in the
finishing and reinforcement, all work upto plinth level as per clauses of tentative deviation was not sufficient
E.I. Chapter - 5 of CPWD specification. as per actual requirement. Additional
No: ii) 1 : 1.5 : 3 ( 1 cement : 1.5 fine sand : 3 graded stone 13.859 8047.807 cum 111535.00 7521.315+526. - Do -
492 quantity beyond the approved
-5 aggregate of 20 mm nominal size) deviation was executed as per actual
requirement.

Providing and laying in position reinforced cement concrete of specified


grade including the cost of Form work, but excluding finishing and
reinforcement, upto floor five level as per clauses of Chapter - 5 of CPWD The quantity considered in the
E.I. specification. tentative deviation was on higher
No: B) 4.626 8865.833 cum 41013.00 8285.833+580 - Do - side. Item executed as per actual
-6 in plinth & skirting courses, fillets, columns, pillars, post & struts etc. requirement.
ii) 1 : 1.5 : 3 ( 1 cement : 1.5 fine sand : 3
graded stone aggregate of 20 mm nominal size)

Providing and laying in position reinforced cement concrete of


specified grade in beams, lintels, bands, plain window sills, stair
cases, spiral stair cases excluding pre-cast spiral stair case,etc. upto
E.I. floor five level including the cost of frame work, but excluding finishing Additional quantity required
No: and reinforcement, as per clauses of Chapter - 5 of CPWD 6.553 9313.938 cum 61034.00 8704.615+609.3
23 - Do - for providing top band of the
-7 specification. boundary wall.
ii) 1:1.5:3 (1 cement : 1.5 fine sand : 3 graded stone aggregate of 20
mm nominal size)

E.I. Reinforcement for RCC works including straightening, cutting,


Quantity consumed as per
No: bending, placing in position & binding all complete upto floor five level, 2119.114 68.679 kg 145539.00 64.186+4.493 - Do -
actual requirement.
-8 as per clauses of Chapter - 5 of CPWD specification.
(i) TMT bars
First class brick work in superstructure above plinth level upto floor
E.I. five level including cost of all materials required and as per clauses of Additional quantity required for
No: chapter-6 of CPWD specification. 28.278 3425.05 cum 96854.00 3200.982+224.
068
- Do - boundary wall in the old PWD
-9 (iii) In Cement mortar 1:4 ( 1 cemeny : complex.
4 fine sand)
Finishing walls with premium acrylic smooth exterior paint of required
E.I. shade of approved brand and manufacture on new work ( two or more
No: coats applied @ 1.43 kg/10 sqm ) over and including base coat water 403.022 75.724 sqm 30518.00 70.771+4.953 - Do - - Do -
-10 proofing cement paint applied @ 2.20 kg/10 sqm complete including
cost of materials required and as per clauses of chapter 13 of CPWD
specification.

556832

Providing and fixing steel work in welded built up sections / framed


E.I. work including cutting, hoisting, fixing in position and applying a
Quantity consume as per
No: priming coat of approved steel primer using structural steel etc. as 839.791 66.089 kg 55501.00 61.766+4.323 - Do -
actual requirement.
-11 required complete as per clauses of chapter-10 of CPWD
specification.
(ii) In grating, frames, guard bar, ladders, railing brackets, gates &
similar works.

E.I. Pointing in brick work or brick flooring with cement mortar 1:3 ( 1 cement :
No: 3 fine sand ) complete as per clauses of chapter 13 of CPWD specification.
(iii) Raised
52.750 77.501 sqm 4088.00 72.431+5.07 - Do - - Do -
-12 and cut pointing

T=Rs. 616609.00

(Ruppes Six lakh Sixteen Thousand Six Hundred and Nine ) only .
EXTRA ITEMS , RATE ANALYSIS FOR FINDING OUT FINAL RATE WITH HAULAGE, LOADING,UNLOADING & STACKING

Name of sub-Division:- Kathalia, Sub-Division(P.W.D)

Name of work :- Renovation of P.W.D. sub-divisional office building , Kathalia during the year 2011-2012. No.3/DNIT/E.E/SNM/2011-2012

MATERIALS SOURCE LEAD IN KM

SURFACE ROAD UN-SURFACE ROAD KATCHA TRACK

Stone aggregate Sub-Divisional head Quarter 20 0 0


Bitumen Emulsion P.W.D. Store at Agartala 90 0 0
/Bitumen(S-90)
Cement/Steel/All steel Sub-Divisional head Quarter 20 0 0
materials/Paints etc.
Fine sand Atr Quarry 10 0 0
Jhama Briack Aggre- At Kiln 10 0 0
gate/Briacks