-PROJ 1002-Assignment 1A
2.2- Estimation
In our project The Canadian Insider we will use the PERT technique for the estimation of the
budget in the metric of hours. The total cost estimate of our project is 214 Hrs. After
considering risk factors with this project, we will consider a 20% budget for contingency
reserve which is 43 Hrs, so our cost baseline of the project is 257 Hrs. In this project, we also
allocate 10% of our cost baseline budget for unknown reserves which are known as
management reserves. Our management reserve for this project is 26 Hrs. After considering
all the reserves for our budget, the project budget is 283 Hrs.