Hi Experts,
I have checked the threads, but don't find relevant answer for the above error message.
While executed the CKMSTART - Set valuation area as productive occurred the
following error message:
Cost component structure for period 001 / 2017 in plant BAD1 not found
Diagnosis
No cost component structure was found in valuation 1 for period 001 / 2017 in plant
BAD1.
Bhoom
Best Answer
0
Vote up Vote down
PATIL PRASAD
Apr 19, 2017 at 06:17 AM
Dear Bhoom,
Regards
Prasad
Add a Comment
Alert Moderator
Share
Vote down
Can Kucukkarakurt
Apr 19, 2017 at 01:54 PM
Hi,
Please check SAP Note also 206629 - Cost component structure not found for actual
CCS.
Actual costing uses the same cost component structure which is used in Product Cost
Planning as well.This ensures that the standard price used for preliminary valuation and
the periodic unit price calculated at the period-end can be compared to each other cost
component by cost component.So as to enforce this, no separate setting option for
actual costing is available in Customizing.
The system searches for the cost component structure to be used as follows:
1. The system determines the costing type which is used for updating the
standard price in the affected valuation.
2. To find a valuation variant the system proceeds as follows:
a) The system searches for the valuation variant for which an allowance for
marking has been issued in the affected period and valuation.
b) If this has not yet been done, the system searches for an issued allowance for
marking in the previous periods.
3. For this costing type and this valuation variant, several costing variants can
have been defined.However, the system enforces that always the same cost
component structure is assigned to these costing variants in the affected period
and plant (or company code).It is precisely this cost component structure which is
also used for actual costing.
However, if the above procedure (search via allowance for marking) could not
determine a valuation variant, the system finally checks whether it is always the same
cost component structure which has been defined for each costing variant for the
standard cost estimate in Customizing.If this is the case, this cost component structure
is of course used.
Solution
1. Check in the Customzing of the product cost planning to make sure that a
costing type has been defined for the affected valuation view (Transaction OKKI).
2. Check to make sure that a costing variant exists which refers to this costing
type (Transaction OKKN).
3. Issue an allowance for marking for the affected period and costing variant in
your company code (Transaction CK24).
4. Then carry out the production startup (SAPRCKMJ or MLCCS_STARTUP)
again.
Kind Regards,