RAB

Proyek : RENOVASI
Lokasi : BEVERLY
KONTRAKTOR : PT.BBJ
HARGA
NO URAIAN PEKERJAAN TOTAL
SATUAN
1 2 3 4

STRUKTUR
A PEKERJAAN AWAL
1 Direksi kit + gudang 48,710 m2 445.000,00 21.675.950,00
2 Pengukuran BouwPlank 42,000 m' 27.000,00 1.134.000,00
B PEKERJAAN TANAH
1 Galian Tanah Pondasi 20,736 m³ 65.000,00 1.347.840,00
2 Galian Tanah Sloof 7,170 m³ 65.000,00 466.050,00
3 Urug Tanah Kembali 1,440 m³ 25.000,00 36.000,00
4 Urug Pasir Dibawah Pondasi 1,440 m³ 206.000,00 296.640,00
5 Lantai Kerja K100 1,440 m³ 690.000,00 993.600,00
C PEKERJAAN BETON K 225
1 COR PONDASI
- Pondasi P 1 125 x 125 x 25 6,140 m³ 3.400.000,00 20.876.000,00
2 COR SLOOF
- S1 20 X 30 2,868 m³ 3.400.000,00 9.751.200,00
3 COR KOLOM LANTAI I
-K1 20 x 35 7,840 m³ 3.400.000,00 26.656.000,00
4 COR BALOK LANTAI II
-B1 20 X 30 9,250 m³ 3.400.000,00 31.450.000,00
5 COR RING BALOK
-B1 15 X 25 4,720 m³ 3.400.000,00 16.048.000,00
COR PELAT LANTAI
12 MM 6,012 m³ 3.400.000,00 20.440.800,00
6 COR TANGGA LANTAI I
- Pondasi Tangga 0,900 m³ 3.400.000,00 3.060.000,00
- Pelat Tangga T = 12 cm 6,250 m³ 3.400.000,00 21.250.000,00
ARSITEKTUR
A PEKERJAAN DINDING
1 Pasangan Bata 1 : 5 145,000 m² 125.000,00 18.125.000,00
2 Plesteran 1 : 5 + Acian 290,000 m² 55.000,00 15.950.000,00
B PEKERJAAN KERAMIK
1 Lantai I 100,240 m² 122.400,00 12.269.376,00
2 Lantai KM + dinding 5,780 m² 123.600,00 714.408,00
C PEKERJAAN TANGGA
Finishing Lantai Tangga 14,600 m² 92.400,00 1.349.040,00
D PEKERJAAN RAILING & HANDRILL
1 Railing Tangga Lantai 16,000 m' 210.000,00 3.360.000,00
E PEKERJAAN KUSEN PINTU & JENDELA
1 Kusen Jendela 200 x 180 cm 2,000 unit 3.750.000,00 7.500.000,00
2 Kusen Jendela 200 x 180 cm 2,000 unit 2.300.000,00 4.600.000,00
HARGA
NO URAIAN PEKERJAAN TOTAL
SATUAN
1 2 3 4
3 Kusen Jendela 40 x 135 cm 1,000 unit 450.000,00 450.000,00
F PEKERJAAN DAUN PINTU & JENDELA
1 Daun Pintu 75 x 215 cm (Panil)
P1 (1 lubang) 2,000 unit 1.300.000,00 2.600.000,00
2 Daun Jendela 70 x 50 cm (Kaca)
BV (bv) 2,000 unit 180.000,00 360.000,00
G PEKERJAAN PENGECATAN
1 Cat Dinding 290,000 m2 19.500,00 5.655.000,00
H PEKERJAAN TANGGA
Finishing Lantai Tangga 14,600 m² 92.400,00 1.349.040,00
I PEKERJAAN RAILING & HANDRILL
1 Railing Tangga Lantai 7,900 m' 210.000,00 1.659.000,00
J PEKERJAAN PLAFON
1 Plafon GYPSUM + Rangka 56,000 m² 49.000,00 2.744.000,00
2 Kornis Gypsum 156,000 m' 21.450,00 3.346.200,00
K PEKERJAAN ATAP
1 Atap spandek motif genteng 24,000 m² 80.000,00 1.920.000,00
2 Gording baja C 24,000 m' 40.208,00 964.992,00
3 Teras 8,920 m² 1.600.000,00 14.272.000,00
M& E
I PEKERJAAN ELEKTRIKAL
A PEKERJAAN ELEKTRIKAL
1 Pengadaan KWH meter 2,000 ls 2.750.000,00 5.500.000,00
2 Instalasi Lampu TL 40 VA 12,000 titik 126.500,00 1.518.000,00
3 Instalasi Lampu PIJAR 25 VA 2,000 titik 126.500,00 253.000,00
4 Instalasi Stop Kontak 3,000 titik 132.000,00 396.000,00
5 Box MCB 2,000 bh 363.000,00 726.000,00
6 Saklar tunggal 3,000 bh 6.600,00 19.800,00
7 Saklar double 3,000 bh 13.200,00 39.600,00
II PEKERJAAN MEKANIKAL
D PEKERJAAN AIR BERSIH + KOTOR + HUJAN
1 Pipa Giv 2" ( Pipa Hawa ) T 4,000 bh 20.000,00 80.000,00
2 Pipa PVC 1/2 " D 25,000 m' 12.500,00 312.500,00
3 Sambungan Pipa PVC 1/2 " 24,000 bh 7.000,00 168.000,00
4 Pipa PVC 3 " D 16,000 m' 16.000,00 256.000,00
5 Sambungan PVC Pipa 3 " 19,000 bh 9.000,00 171.000,00
6 Pipa PVC 4 " D 18,000 m' 20.000,00 360.000,00
7 Sambungan Pipa PVC 4 " 29,000 bh 11.000,00 319.000,00
E PEKERJAAN SANITASI
1 Pasang Closet DUDUK 2,000 unit 2.700.000,00 5.400.000,00
2 Keran air 2,000 bh 25.000,00 50.000,00
3 Floor Drain 2,000 bh 15.000,00 30.000,00

TOTAL 290.269.036,00
PEMBULATAN 290.269.000,00