RENCANA ANGGARAN BIAYA (RAB)


GEDUNG ASRAMA PONDOK PESANTREN FATHUL MUNA

No. URAIAN PEKERJAAN SATUAN VOLUMEHARGA SATUANJUMLAH


(Rp) (Rp)
A. PERSIAPAN
a. Survei LS 10,00 500,000,00 35.000.000
b. Mobilitas LS 10,00 500,000,00 50.000.000
Sub Total 85.000.000
B. PEKERJAAN PONDASI
a. Pling # 200 x 200 mm Unit 62,00 2,500,000,00 155,000,000,00
b. Beton pile cap K-250 M3 9,37 2,300,000,00 21,551,000,00
c. Besi pile cap Kg 3085,74 12,500,000,00 38,571,750,00
d. Beton p tapak K-250 M3 6,83 2,000,000,00 13,660,000,00
e. Besi p tapak Kg 726,45 12,500,000,00 9,080,625,00
f. Beton stump K-250 M3 0,66 1,700,000,00 1,122,000,00
g. Beton stump Kg 150,56 12,500,000,00 1,882,000,00
Sub total 240,867,375,00
C. PEKERJAAN SLOFF & KOLOM
LANTAI 1
a. Beton K-250, sloff M3 28,06 2,500,000,00 70,150,000,00
b. Besi beton sloff Kg 3319,18986 12,500,000,00 41,489,837,00
c. Beton K-250, kolom lantai 1 M3 21,77 2,500,000,00 54,425,000,00
d. Besi beton, kolom lantai 1 Kg 5553,76 12,500,000,00 69,422,000,00
Sub Total 235,486,837,00
D. PEKERJAAN BALOK & KOLOM
LANTAI 2
a. Beton balok lantai 2 K-250 M3 40,79 2,600,000,00 106,054,000,00
b. Besi untuk balok lantai 2 Kg 6594,46 12,500,000,00 82,430,750,00
c. Beton plat lantai 2 K-250 M3 94,88 2,400,000,00 227,712,000,00
d. Beton plat lantai 2 Kg 6862,84 12,500,000,00 85,755,000,00
e. Beton kolom lantai 2 K-250 M3 13,67 2,500,000,00 34,175,000,00
f. Besi beton kolom lantai 2 Kg 3468,46 12,500,000,00 43,355,750,00
Sub Total 579,483,000,00
E. PEKERJAAN ATAP
a. Beton ring balok K-250 M3 13,97 300,000,00 4,191,000,00
b. Besi untuk ring balok Kg 3433,75 12,500,000,00 42,921,875,00
c. Beton talang dak M3 30,24 1,500,000,00 45,360,000,00
d. Besi dak atap Kg 2624,83 12,500,000,00 32,810,375,00
e. Pas gording 2” x 5” Ton 4,60 3,500,000,00 16,100,000,00
f. Atap Spandek M2 698,00 120,000,00 83,760,000,00
Sub Total 363,862,250,00
F. PEKERJAAN TANGGA
a. Beton tangga lantai 1 K-250 M3 6,38 2,500,000,00 15,950,000,00
b. Besi untuk tangga lantai 1 Kg 1172,10 12,500,000,00 14,651,250,00
Sub Total 30,601,250,00
G. PEKERJAAN DINDING
a. Pasang bata merah M2 436,00 125,000,00 54,500,000,00
b. Plaster & cat dinding M2 872,00 75,000,00 65,400,000,00
Sub Total 119,900,000,00
H. PEKERJAAN LANTAI KERAMIK
a. Plester & aci lantai 2-3 M2 846,00 75,000,00 63,450,000,00
b. Cor lantai 1 (K-175) M3 19,89 750,000,00 14,917,000,00
c. Pasang keramik kamar mandi M2 291,60 150,000,00 43,740,000,00
Sub Total 122,107,000,00
I. PEKERJAAN PINTU & JENDELA
a. Pintu type 1 Unit 9,00 1,750,000,00 15,750,000,00
b. Pintu type 2 Unit 8,00 1,500,000,00 12,000,000,00
c. Jendela type 1 Unit 32,00 500,000,00 16,000,000,00
d. Jendela type 2 Unit 32,00 750,000,00 24,000,000,00
e. BV Unit 14,00 600,000,00 8,400,000,00
Sub Total 76,150,000,00
J. PEKERJAAN PENGUNCI
a. Kunci pintu utama / panel Ex Sinar 18,00 300,000,00 5,400,000,00
kunci
b. Kunci pintu teakwood milaminto Ex Sinar 6,0 250,000,00 1,500,000,00
kunci
c. Kait angin Ex Sinar 12,00 50,000,00 600,000,00
kunci
d. Engsel pintu 4” Ex Sinar 72,00 70,000,00 5,500,000,00
kunci
e. Engsel jendela 3” Ex Sinar 36,00 70,000,00 2,500,000,00
kunci
Sub Total 15,500,000,00
K. PEKERJAAN PENGECETAN
a. Cat dinding dalam Cat tembok 900,2 40,000,00 36,008,000,00
ex
Jotun
b. Cat dinding luar Cat 950,00 40,000,00 38,000,000,00
weather
shield
c. Cat kusen 36,00 75,000,00 2,700,000,00
d. Cat pintu & jendela 18,00 75,000,00 1,300,000,00
e. Cat plafound multipleks 950,00 40,000,00 38,000,000,00
f. Cat list plafound kayu 336,00 40,000,00 13,400,000,00
Sub Total 129,408,000,00
L. PEKERJAAN INSTALASI LISTRIK
a. Titik lampu + titik stop kontak NYM 2 x 2 60,00 125,000,00 7,500,000,00
½+
NYM 3 x 2
½
b. Saklar ganda Ex clipsal 15,00 125,000,00 1,800,000,00
series
c. Fiting stop lampu Ex clipsal 45,00 125,000,00 5,600,000,00
series
d. Fiting titik lampu Ex clipsal 60,00 125,000,00 7,500,000,00
series
e. Box MCB Ex harger 8 2,0 300,000,00 600,000,00
group
f. Pekerjaan sanitair
Sub Total 23,000,000,00
Total Keseluruhan (A - L)
TOTAL 1.878.547.000
PPN 216.032.905
JUMLAH TOTAL KESELURUHAN 2.094.579.905

Mengetahui
Pengasuh Ponpes Fathul Muna

SYAHRIFIN SANTOSO, S.Ag