10-Contoh PBP-BC-TS BGN Gedung @IK Tirtayasa
10-Contoh PBP-BC-TS BGN Gedung @IK Tirtayasa
I PEKERJAAN PERSIAPAN
1 Pengadaan Staff 1 ls Rp 300,000,000.00 Rp 300,000,000.00
2 Mobilisasi & Demobilisasi 1 ls Rp 100,000,000.00 Rp 100,000,000.00
3 Jalan Masuk ke Proyek 12 m' Rp 600,000.00 Rp 7,200,000.00
4 Land Clearing 2000 m2 Rp 12,000.00 Rp 24,000,000.00
5 Pagar Pengaman Proyek 180 m' Rp 225,000.00 Rp 40,500,000.00
6 Direksi Keet 48 m2 Rp 1,350,000.00 Rp 64,800,000.00
7 Listrik Kerja 1 ls Rp 15,000,000.00 Rp 15,000,000.00
8 Air Kerja 1 ls Rp 11,000,000.00 Rp 11,000,000.00
9 Keamanan 1 ls Rp 6,000,000.00 Rp 6,000,000.00
10 Asuransi Tenaga Kerja 1 ls Rp 17,500,000.00 Rp 17,500,000.00
Rp 586,000,000.00
II PEKERJAAN TANAH
1 Setting Out dan Bouwplank 1 ls Rp 22,500,000.00 Rp 22,500,000.00
2 Galian Basement 6000 m3 Rp 35,000.00 Rp 210,000,000.00
3 Galian Pondasi Pile Cap 115 m3 Rp 45,000.00 Rp 5,175,000.00
4 Urugan kembali 540 m3 Rp 17,500.00 Rp 9,450,000.00
5 Pemadatan Tanah 2000 m2 Rp 11,000.00 Rp 22,000,000.00
Rp 269,125,000.00
III PEKERJAAN BETON BERTULANG
A Lantai Basement
1 Bored Pile Ø 30 beton K-300 210 m' Rp 350,000.00 Rp 73,500,000.00
2 Pile Cap Beton K-300 105 m3 Rp 1,100,000.00 Rp 115,500,000.00
3 Balok Sloof (Tie Beam) K-300 34.8 m3 Rp 1,100,000.00 Rp 38,280,000.00
4 Kolom K1 beton K-300 7.2 m3 Rp 1,100,000.00 Rp 7,920,000.00
5 Kolom K2 beton K-300 7.92 m3 Rp 1,100,000.00 Rp 8,712,000.00
6 Plat Lantai Basement 240 m3 Rp 1,100,000.00 Rp 264,000,000.00
7 Dinding Basement 60 m3 Rp 1,100,000.00 Rp 66,000,000.00
Tangga Beton 1.749 m3 Rp 1,200,000.00 Rp 2,098,800.00
8 Waterproofing Integral 439.8 m3 Rp 150,000.00 Rp 65,970,000.00
Rp 641,980,800.00
B Lantai Dasar
1 Balok Beton K-300 B1 12 m3 Rp 1,100,000.00 Rp 13,200,000.00
2 Balok Beton K-300 B2 20 m3 Rp 1,100,000.00 Rp 22,000,000.00
3 Balok Beton K-300 B3 14.175 m3 Rp 1,100,000.00 Rp 15,592,500.00
4 Plat Lantai Dasar 72 m3 Rp 1,100,000.00 Rp 79,200,000.00
5 Tangga Beton 1.749 m3 Rp 1,200,000.00 Rp 2,098,800.00
6 Kolom K1 beton K-300 7.2 m3 Rp 1,100,000.00 Rp 7,920,000.00
7 Kolom K2 beton K-300 7.92 m3 Rp 1,100,000.00 Rp 8,712,000.00
Rp 148,723,300.00
C Lantai Satu
1 Balok Beton K-300 B1 12 m3 Rp 1,150,000.00 Rp 13,800,000.00
2 Balok Beton K-300 B2 20 m3 Rp 1,150,000.00 Rp 23,000,000.00
3 Balok Beton K-300 B3 14.175 m3 Rp 1,150,000.00 Rp 16,301,250.00
4 Plat Lantai Satu 72 m3 Rp 1,100,000.00 Rp 79,200,000.00
5 Tangga Beton 1.749 m3 Rp 1,200,000.00 Rp 2,098,800.00
6 Kolom K1 beton K-300 7.2 m3 Rp 1,100,000.00 Rp 7,920,000.00
7 Kolom K2 beton K-300 7.92 m3 Rp 1,100,000.00 Rp 8,712,000.00
Rp 151,032,050.00
D Lantai Dua
1 Balok Beton K-300 B1 12 m3 Rp 1,150,000.00 Rp 13,800,000.00
2 Balok Beton K-300 B2 20 m3 Rp 1,150,000.00 Rp 23,000,000.00
3 Balok Beton K-300 B3 14.175 m3 Rp 1,150,000.00 Rp 16,301,250.00
4 Plat Lantai Dua 72 m3 Rp 1,150,000.00 Rp 82,800,000.00
5 Tangga Beton 1.749 m3 Rp 1,200,000.00 Rp 2,098,800.00
6 Kolom K1 beton K-300 7.2 m3 Rp 1,150,000.00 Rp 8,280,000.00
7 Kolom K2 beton K-300 7.92 m3 Rp 1,150,000.00 Rp 9,108,000.00
Rp 155,388,050.00
E Lantai Atap
1 Balok Beton K-300 B1 12 m3 Rp 1,150,000.00 Rp 13,800,000.00
2 Balok Beton K-300 B2 20 m3 Rp 1,150,000.00 Rp 23,000,000.00
3 Balok Beton K-300 B3 14.175 m3 Rp 1,150,000.00 Rp 16,301,250.00
4 Plat Lantai Atap 72 m3 Rp 1,150,000.00 Rp 82,800,000.00
5 Dinding Parapeth 15 m3 Rp 1,300,000.00 Rp 19,500,000.00
Rp 155,401,250.00
Total Rp 2,107,650,450.00
Kontraktor
PT Jaya Maju Kusuma
PROYEK GEDUNG MAYA ABADI
I PEKERJAAN PERSIAPAN
1 Pengadaan Staff 1 ls Rp 300,000,000.00 Rp 300,000,000.00 14.2339 %
2 Mobilisasi & Demobilisasi 1 ls Rp 100,000,000.00 Rp 100,000,000.00 4.7446 %
3 Jalan Masuk ke Proyek 12 m' Rp 600,000.00 Rp 7,200,000.00 .3416 %
4 Land Clearing 2000 m2 Rp 12,000.00 Rp 24,000,000.00 1.1387 %
5 Pagar Pengaman Proyek 180 m' Rp 225,000.00 Rp 40,500,000.00 1.9216 %
6 Direksi Keet 48 m2 Rp 1,350,000.00 Rp 64,800,000.00 3.0745 %
7 Listrik Kerja 1 ls Rp 15,000,000.00 Rp 15,000,000.00 .7117 %
8 Air Kerja 1 ls Rp 11,000,000.00 Rp 11,000,000.00 .5219 %
9 Keamanan 1 ls Rp 6,000,000.00 Rp 6,000,000.00 .2847 %
10 Asuransi Tenaga Kerja 1 ls Rp 17,500,000.00 Rp 17,500,000.00 .8303 %
Rp 586,000,000.00 27.8035 %
II PEKERJAAN TANAH
1 Setting Out dan Bouwplank 1 ls Rp 22,500,000.00 Rp 22,500,000.00 1.0675 %
2 Galian Basement 6000 m3 Rp 35,000.00 Rp 210,000,000.00 9.9637 %
3 Galian Pondasi Pile Cap 115 m3 Rp 45,000.00 Rp 5,175,000.00 .2455 %
4 Urugan kembali 540 m3 Rp 17,500.00 Rp 9,450,000.00 .4484 %
5 Pemadatan Tanah 2000 m2 Rp 11,000.00 Rp 22,000,000.00 1.0438 %
Rp 269,125,000.00 12.7690 %
III PEKERJAAN BETON BERTULANG
A Lantai Basement
1 Bored Pile Ø 30 beton K-300 210 m' Rp 350,000.00 Rp 73,500,000.00 3.4873 %
2 Pile Cap Beton K-300 105 m3 Rp 1,100,000.00 Rp 115,500,000.00 5.4800 %
3 Balok Sloof (Tie Beam) K-300 34.8 m3 Rp 1,100,000.00 Rp 38,280,000.00 1.8162 %
4 Kolom K1 beton K-300 7.2 m3 Rp 1,100,000.00 Rp 7,920,000.00 .3758 %
5 Kolom K2 beton K-300 7.92 m3 Rp 1,100,000.00 Rp 8,712,000.00 .4134 %
6 Plat Lantai Basement 240 m3 Rp 1,100,000.00 Rp 264,000,000.00 12.5258 %
7 Dinding Basement 60 m3 Rp 1,100,000.00 Rp 66,000,000.00 3.1314 %
Tangga Beton 1.749 m3 Rp 1,200,000.00 Rp 2,098,800.00 .0996 %
8 Waterproofing Integral 439.8 m3 Rp 150,000.00 Rp 65,970,000.00 3.1300 %
Rp 641,980,800.00 30.4595 %
B Lantai Dasar
1 Balok Beton K-300 B1 12 m3 Rp 1,100,000.00 Rp 13,200,000.00 .6263 %
2 Balok Beton K-300 B2 20 m3 Rp 1,100,000.00 Rp 22,000,000.00 1.0438 %
3 Balok Beton K-300 B3 14.175 m3 Rp 1,100,000.00 Rp 15,592,500.00 .7398 %
4 Plat Lantai Dasar 72 m3 Rp 1,100,000.00 Rp 79,200,000.00 3.7577 %
5 Tangga Beton 1.749 m3 Rp 1,200,000.00 Rp 2,098,800.00 .0996 %
6 Kolom K1 beton K-300 7.2 m3 Rp 1,100,000.00 Rp 7,920,000.00 .3758 %
7 Kolom K2 beton K-300 7.92 m3 Rp 1,100,000.00 Rp 8,712,000.00 .4134 %
Rp 148,723,300.00 7.0564 %
C Lantai Satu
1 Balok Beton K-300 B1 12 m3 Rp 1,150,000.00 Rp 13,800,000.00 .6548 %
2 Balok Beton K-300 B2 20 m3 Rp 1,150,000.00 Rp 23,000,000.00 1.0913 %
3 Balok Beton K-300 B3 14.175 m3 Rp 1,150,000.00 Rp 16,301,250.00 .7734 %
4 Plat Lantai Satu 72 m3 Rp 1,100,000.00 Rp 79,200,000.00 3.7577 %
5 Tangga Beton 1.749 m3 Rp 1,200,000.00 Rp 2,098,800.00 .0996 %
6 Kolom K1 beton K-300 7.2 m3 Rp 1,100,000.00 Rp 7,920,000.00 .3758 %
7 Kolom K2 beton K-300 7.92 m3 Rp 1,100,000.00 Rp 8,712,000.00 .4134 %
Rp 151,032,050.00 7.1659 %
D Lantai Dua
1 Balok Beton K-300 B1 12 m3 Rp 1,150,000.00 Rp 13,800,000.00 .6548 %
2 Balok Beton K-300 B2 20 m3 Rp 1,150,000.00 Rp 23,000,000.00 1.0913 %
3 Balok Beton K-300 B3 14.175 m3 Rp 1,150,000.00 Rp 16,301,250.00 .7734 %
4 Plat Lantai Dua 72 m3 Rp 1,150,000.00 Rp 82,800,000.00 3.9285 %
5 Tangga Beton 1.749 m3 Rp 1,200,000.00 Rp 2,098,800.00 .0996 %
6 Kolom K1 beton K-300 7.2 m3 Rp 1,150,000.00 Rp 8,280,000.00 .3929 %
7 Kolom K2 beton K-300 7.92 m3 Rp 1,150,000.00 Rp 9,108,000.00 .4321 %
Rp 155,388,050.00 7.3726 %
E Lantai Atap
1 Balok Beton K-300 B1 12 m3 Rp 1,150,000.00 Rp 13,800,000.00 .6548 %
2 Balok Beton K-300 B2 20 m3 Rp 1,150,000.00 Rp 23,000,000.00 1.0913 %
3 Balok Beton K-300 B3 14.175 m3 Rp 1,150,000.00 Rp 16,301,250.00 .7734 %
4 Plat Lantai Atap 72 m3 Rp 1,150,000.00 Rp 82,800,000.00 3.9285 %
5 Dinding Parapeth 15 m3 Rp 1,300,000.00 Rp 19,500,000.00 .9252 %
Rp 155,401,250.00 7.3732 %
Dibuat Oleh :
PT Jaya Maju Kusuma
TIME SCHEDULE
PROYEK GEDUNG MAYA ABADI
Agustus 2014 September 2014 Oktober 2014 November 2014 Desember 2014
No. ITEM PEKERJAAN BOBOT Ket
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
I. PEKERJAAN PERSIAPAN
1 Pengadaan Staff 14.2339 % 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189
2 Mobilisasi & Demobilisasi 4.7446 % 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063
3 Jalan Masuk ke Proyek .3416 % 0.3416
4 Land Clearing 1.1387 % 0.5694 0.5694
5 Pagar Pengaman Proyek 1.9216 % 0.9608 0.9608
6 Direksi Keet 3.0745 % 1.5373 1.5373
7 Listrik Kerja .7117 % 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309
8 Air Kerja .5219 % 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227
9 Keamanan .2847 % 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124
10 Asuransi Tenaga Kerja .8303 % 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361
II PEKERJAAN TANAH
1 Setting Out dan Bouwplank 1.0675 % 0.5338 0.5338
2 Galian Basement 9.9637 % 3.3212 3.3212 3.3212
3 Galian Pondasi Pile Cap .2455 % 0.0818 0.0818 0.0818
4 Urugan kembali .4484 % 0.1495 0.1495 0.1495
5 Pemadatan Tanah 1.0438 % 0.3479 0.3479 0.3479
B Lantai Dasar
1 Balok Beton K-300 B1 .6263 % 0.3131 0.3131
2 Balok Beton K-300 B2 1.0438 % 0.3479 0.3479 0.3479
3 Balok Beton K-300 B3 .7398 % 0.3699 0.3699
4 Plat Lantai Dasar 3.7577 % 1.2526 1.2526 1.2526
5 Tangga Beton .0996 % 0.0996
6 Kolom K1 beton K-300 .3758 % 0.1879 0.1879
7 Kolom K2 beton K-300 .4134 % 0.2067 0.2067
C Lantai Satu
1 Balok Beton K-300 B1 .6548 % 0.3274 0.3274
2 Balok Beton K-300 B2 1.0913 % 0.3638 0.3638 0.3638
3 Balok Beton K-300 B3 .7734 % 0.3867 0.3867
4 Plat Lantai Satu 3.7577 % 1.2526 1.2526 1.2526
5 Tangga Beton .0996 % 0.0996
6 Kolom K1 beton K-300 .3758 % 0.1879 0.1879
7 Kolom K2 beton K-300 .4134 % 0.2067 0.2067
D Lantai Dua
1 Balok Beton K-300 B1 .6548 % 0.3274 0.3274
2 Balok Beton K-300 B2 1.0913 % 0.3638 0.3638 0.3638
3 Balok Beton K-300 B3 .7734 % 0.3867 0.3867
4 Plat Lantai Dua 3.9285 % 1.3095 1.3095 1.3095
5 Tangga Beton .0996 % 0.0996
6 Kolom K1 beton K-300 .3929 % 0.1964 0.1964
7 Kolom K2 beton K-300 .4321 % 0.2161 0.2161
E Lantai Atap
1 Balok Beton K-300 B1 .6548 % 0.2183 0.2183 0.2183
2 Balok Beton K-300 B2 1.0913 % 0.3638 0.3638 0.3638
3 Balok Beton K-300 B3 .7734 % 0.3867 0.3867
4 Plat Lantai Atap 3.9285 % 1.3095 1.3095 1.3095
5 Dinding Parapeth .9252 % 0.4626 0.4626
Dibuat Oleh :
PT Jaya Maju Kusuma
TIME SCHEDULE S-CURVE
PROYEK GEDUNG MAYA ABADI
Agustus 2014 September 2014 Oktober 2014 November 2014 Desember 2014 Ket
No. ITEM PEKERJAAN BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
I. PEKERJAAN PERSIAPAN
1 Pengadaan Staff 14.2339 % 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189 0.6189
2 Mobilisasi & Demobilisasi 4.7446 % 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063 0.2063
3 Jalan Masuk ke Proyek .3416 % 0.3416
4 Land Clearing 1.1387 % 0.5694 0.5694
5 Pagar Pengaman Proyek 1.9216 % 0.9608 0.9608
6 Direksi Keet 3.0745 % 1.5373 1.5373
7 Listrik Kerja .7117 % 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309 0.0309
8 Air Kerja .5219 % 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227 0.0227
9 Keamanan .2847 % 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124 0.0124
10 Asuransi Tenaga Kerja .8303 % 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361 0.0361
II PEKERJAAN TANAH
1 Setting Out dan Bouwplank 1.0675 % 0.5338 0.5338
2 Galian Basement 9.9637 % 3.3212 3.3212 3.3212
3 Galian Pondasi Pile Cap .2455 % 0.0818 0.0818 0.0818
4 Urugan kembali .4484 % 0.1495 0.1495 0.1495
5 Pemadatan Tanah 1.0438 % 0.3479 0.3479 0.3479
B Lantai Dasar
1 Balok Beton K-300 B1 .6263 % 0.3131 0.3131
2 Balok Beton K-300 B2 1.0438 % 0.3479 0.3479 0.3479
3 Balok Beton K-300 B3 .7398 % 0.3699 0.3699
4 Plat Lantai Dasar 3.7577 % 1.2526 1.2526 1.2526
5 Tangga Beton .0996 % 0.0996
6 Kolom K1 beton K-300 .3758 % 0.1879 0.1879
7 Kolom K2 beton K-300 .4134 % 0.2067 0.2067
C Lantai Satu
1 Balok Beton K-300 B1 .6548 % 0.3274 0.3274
2 Balok Beton K-300 B2 1.0913 % 0.3638 0.3638 0.3638
3 Balok Beton K-300 B3 .7734 % 0.3867 0.3867
4 Plat Lantai Satu 3.7577 % 1.2526 1.2526 1.2526
5 Tangga Beton .0996 % 0.0996
6 Kolom K1 beton K-300 .3758 % 0.1879 0.1879
7 Kolom K2 beton K-300 .4134 % 0.2067 0.2067
D Lantai Dua
1 Balok Beton K-300 B1 .6548 % 0.3274 0.3274
2 Balok Beton K-300 B2 1.0913 % 0.3638 0.3638 0.3638
3 Balok Beton K-300 B3 .7734 % 0.3867 0.3867
4 Plat Lantai Dua 3.9285 % 1.3095 1.3095 1.3095
5 Tangga Beton .0996 % 0.0996
6 Kolom K1 beton K-300 .3929 % 0.1964 0.1964
7 Kolom K2 beton K-300 .4321 % 0.2161 0.2161
E Lantai Atap
1 Balok Beton K-300 B1 .6548 % 0.2183 0.2183 0.2183
2 Balok Beton K-300 B2 1.0913 % 0.3638 0.3638 0.3638
3 Balok Beton K-300 B3 .7734 % 0.3867 0.3867
4 Plat Lantai Atap 3.9285 % 1.3095 1.3095 1.3095
5 Dinding Parapeth .9252 % 0.4626 0.4626
Dibuat Oleh :
PT Jaya Maju Kusuma