You are on page 1of 2

OUTDOOR COOLING UNIT FOR FOUR

SEASONS RESTAURANT

Supply, Installation, Testing & Commissioning of Outdoor Cooling System for Four Seasons Restaurant

WORK INSPECTION REPORT (WIR)


Reference Number: FSOC-HEMC-WIR-ME-001 Rev 00 Date 28-03-2023
Subject of the Inspection: MOCK-UP INSATALLATION OF DUCT Time of Inspection: 9:00AM
Area: JEAN GEORGE RESTAURANT Date of Inspection: 29-03-2023
Reference Documents: N/A
ITP No & Activity No: N/A
Attachments: PHOTOS

Item to be Inspected Location Elevation Discipline/Works

INSPECTION REQUEST FOR MOCK-UP INSTALLATION JEAN GEORGE Elec


OF DUCT ALONG WITH INSULATION AND RESTAURANT ✔ Mech
ACCESSORIES FROM AHU TO RESTAURANT AT JEAN ID/Fit-Out
GEORGE RESTAURANT
CCTV-A/V-DATA
Others

Four Seasons Remarks


Refer to the attached Layouts & Approvals

We request your presence for inspection I test according to above s c h ed ul e


Engineer's Comments:

Notes:
Engineer's Inspection shall occur only after the Inspection Request Form is signed off by Contractor QC Representative
confirming acceptance of the work.

For HEMC Signatories

Requestor: Site QC Engineer / Quality Inspector Project QA/QC Manager

For Engineers Approval & Signatories:

Approval Code: (Please Tick the Approval Status)

1. Approved 2. Approved as Noted 3. Rejected I Resubmit

FOUR SEASON / QA-QC ENGINEER Date