Location : Lot 9, Blk. 23, Donna Monserat Street, Gran Plains Subd., Jaro, Iloilo City
Owner : Mr. Michael William J. Hechanova
Items/Description Quantity Unit Unit Cost Labor Mat. & Labor Sub-Total
1.0 Earth Works
1.0.1 Clearing 1.00 lot 5,000.00 5,000.00 5,000.00
1.0.2 Staking and Lay outing 1.00 lot 2,500.00 2,500.00 2,500.00
1.0.3 Excavation 28.75 cu.m 350.00 350.00 10,062.50
1.0.4 Backfill and compaction of Excavated matterials
28.75 cu.m 250.00 250.00 7,187.50
1.0.5 Backfill and compaction 47.89 cu.m 320.00 250.00 570.00 27,295.88
1.0.6 Gravel Bed and Compaction 10.00 cu.m 1,200.00 250.00 1,450.00 14,500.00
1.0.7 Temporary Facilities 1.00 lot 12,000.00 5,000.00 17,000.00 17,000.00
1.0.8 Soil Poisoning 100.00 sq.m 50.00 40.00 90.00 9,000.00
3.0 Column
3.0.1 Conc. 5.76 cu.m 4,200.00 1,470.00 5,670.00 32,659.20
3.0.2 RSB 16mm diam.x9m 54.00 length 573.00 171.90 744.90 40,224.60
3.0.3 Ties 10mm diam.x6m 82.50 length 152.00 45.60 197.60 16,302.00
3.0.4 Tie wire #16 22.42 kg 56.00 16.80 72.80 1,631.82
3.0.5 Formworks 288.00 m 220.00 100.00 320.00 92,160.00
12.0 Stairs
12.0.1 Conc. 2.65 cu.m 4,200.00 1,470.00 5,670.00 15,025.50
12.0.2 RSB 12mm diam.x6m 28.00 length 232.00 81.20 313.20 8,769.60
12.0.3 Temp. 10mm diam.x6m 24.00 length 152.00 53.20 205.20 4,924.80
12.0.4 Tie wire #16 2.00 kg 56.00 19.60 75.60 151.20
12.0.5 Formworks 19.00 sq.m 420.00 280.00 700.00 13,300.00