Professional Documents
Culture Documents
Financial Proposal - 3units
Financial Proposal - 3units
in 1,000 USD
Tendered Alternative
Item
Total Local Foreign Total Local Foreign
1 GENERAL ITEMS and INFRASTRUCTURES 153,640.87 55,310.72 98,330.15 158,320.58 56,995.41 101,325.17
1.2 Contractor's General items 92,131.27 33,167.26 58,964.01 92,131.27 33,167.26 58,964.01
1.3 Facilities for the Employer camp and offices (Logistic support ) 16,816.30 6,053.87 10,762.43 16,824.04 6,056.65 10,767.39
3.1 Excavation Dam site 2,109.97 759.58 1,350.39 3,556.94 1,280.50 2,276.44
3.2 Diversion And Bottom outlet 14,489.95 5,216.37 9,273.58 16,619.54 5,983.03 10,636.51
5.2 Surge Chamber Headrace 11,430.75 4,115.06 7,315.69 8,290.79 2,984.67 5,306.12
1/32
in 1,000 USD
Tendered Alternative
Item
Total Local Foreign Total Local Foreign
5.5 Surge Chamber Tailrace 8,544.13 3,075.89 5,468.24 11,420.67 4,111.44 7,309.23
6.1 Main Access Tunnel 4,703.48 1,693.25 3,010.23 9,010.53 3,243.78 5,766.75
6.3 Power Station And Transformer Cavern 1,691.70 609.00 1,082.70 6,002.32 2,160.83 3,841.49
6.6 Cable Tunnel And Culvert 1,401.05 504.38 896.67 15,426.18 5,553.43 9,872.75
7 HYDROMECHANICAL PLANT AND EQUIPMENT 21,760.44 4,352.07 17,408.37 21,760.44 4,352.07 17,408.37
7.1 Diversion & Bottom outlet 6,919.10 1,383.81 5,535.29 6,919.10 1,383.81 5,535.29
7.3 Headrace & penstock 8,618.70 1,723.74 6,894.96 8,618.70 1,723.74 6,894.96
2/32
in 1,000 USD
Tendered Alternative
Item
Total Local Foreign Total Local Foreign
8.5 33kv Power Supply (Local Supply) 10,696.46 1,604.47 9,091.99 10,696.46 534.82 10,161.63
14 Provisional sum 5% of the 16km underground tunnel bid price. 6,030.01 2,170.80 3,859.21 5,163.41 1,858.83 3,304.58
15 VAT taxes 15% of the Bid price. 91,304.43 28,760.63 62,543.81 93,414.83 28,307.10 65,107.34
3/32
SCHEDULE 1D- UNIT RATES, PRICES AND BILL OF ESTIMATED QUANTITIES
The Bidder to fill the unit rates and prices in the attached Bill Of Estimated Quantity only for the purpose of Bid evaluation and to be used in case the Employer wishes to instruct
additional works.
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
1000 USD 1000 USD 1000 USD 1000 USD 1000 USD 1000 USD
1 GENERAL ITEMS and INFRASTRUCTURES 153,640.87 55,310.72 98,330.15 158,320.58 56,995.41 101,325.17
1.1.1 Permanent access road km 55 43800.44 15,768.16 28,032.28 56.86 45,281.69 16,301.41 28,980.28
1.1.2 Temporary access road km 8 705.31 253.91 451.40 14.94 1,317.17 474.18 842.99
1.2 Contractor's General items 92,131.27 33,167.26 58,964.01 92,131.27 33,167.26 58,964.01
1.2.4 Water supply system LS 1 1489.29 536.14 953.15 1 1,489.29 536.14 953.15
1.2.5 Power supply system LS 1 4576.67 1,647.60 2,929.07 1 4,576.67 1,647.60 2,929.07
4/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
Facilities for the Employer camp and offices
1.3 16,816.30 6,053.87 10,762.43 16,824.04 6,056.65 10,767.39
(Logistic support )
1.3.1 Employer's camp, office service building 9,419.41 3,391.00 6,028.41 9,427.15 3,393.78 6,033.37
1.3.1.1 Service Building m² 2900 2243.6 807.70 1,435.90 2,910.00 2,251.34 810.48 1,440.86
1.3.1.2 House For the Employer representative m² 1936 1384.33 498.36 885.97 1,936.00 1,384.33 498.36 885.97
1.3.1.3 House For the Employer m² 4824 3449.41 1,241.79 2,207.62 4,824.00 3,449.41 1,241.79 2,207.62
Internal Infrastructure (Water, Electric,
1.3.1.4 LS 1 1990.41 716.55 1,273.86 1 1,990.41 716.55 1,273.86
Road Sewerage, Fence, Parking Area
1.3.1.5 House furniture and utilities LS 1 351.66 126.60 225.06 1 351.66 126.60 225.06
1.3.2 Office furniture and office equipment 1,679.50 604.61 1,074.89 1,679.50 604.61 1,074.89
1.3.3.1 All Service Building LS 1 202.56 72.92 129.64 1 202.56 72.92 129.64
1.3.3.2 Renovate Building to handover LS 1 211 75.96 135.04 1 211.00 75.96 135.04
1.3.4.2 Operation & Maintenance of Vehicle Months 48 1125.33 405.12 720.21 48 1,125.33 405.12 720.21
5/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
Consumables for all housing, offices,
1.3.5 Months 48 264.73 95.30 169.43 48 264.73 95.30 169.43
canteen
Man
1.3.6 Driver and unskilled labours 4000 1031.56 371.36 660.20 4000 1,031.56 371.36 660.20
month
2 SITE AND RESERVOIR 7,427.73 2,673.99 4,753.74 7,427.73 2,673.99 4,753.74
2.2 Site Clearing, easy Ha 600 4282.71 1,541.78 2,740.93 600 4,282.71 1,541.78 2,740.93
2.3 Site Clearing, medium vegetation Ha 130 1445.79 520.48 925.31 130 1,445.79 520.48 925.31
2.4 Site Clearing, heavy vegetation Ha 70 1113.13 400.73 712.40 70 1,113.13 400.73 712.40
3.1.1 Clearing and grubbing m² 81200 131.54 47.35 84.19 118,120.25 191.35 68.89 122.46
3.1.4 Soft excavation (difficult) m³ 67600 204.83 73.74 131.09 92,262.66 279.56 100.64 178.92
3.1.6 Rock excavation dam foundation m³ 60000 818.4 294.62 523.78 211,669.30 2,887.17 1,039.38 1,847.79
6/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
3.2.5 Structural concrete C35 outdoor m³ 18733 7589.48 2,732.21 4,857.27
3.2.7 Rock bolt 5m, d28 pcs 7200 595.37 214.33 381.04
3.2.8 Rock bolt 4m, d22 pcs 4600 269 96.84 172.16
3.2.14 Rock bolt L=3.0m, d25 pcs 173.80 7.65 2.75 4.90
3.2.15 Rock bolt L=5.0m, d25 pcs 7,907.20 597.86 215.23 382.63
7/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
3.3.1 Cofferdam fill m³ 81600 385.94 138.94 247.00
Filter fill, crushed rock,(D=0-60mm,T=
3.3.2 m³ 8160 242.52 87.31 155.21
1.5m)
3.3.3 Impermeable material m² 7200 40.25 14.49 25.76
3.3.15 Rock block for slope protection m³ 2,680.00 89.49 32.22 57.27
3.4.2 Structural concrete C35 outdoor m³ 35000 14179.89 5,104.76 9,075.13 9,004.20 3,647.96 1,313.27 2,334.69
3.4.3 Grout curtain m² 13750 689.97 248.39 441.58 32,739.42 1,642.86 591.43 1,051.43
3.4.4 Rockbolts grouted, L =4M m³ 3000 175.44 63.16 112.28 3,569.50 208.74 75.15 133.59
8/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
3.4.5 Asphalt core m³ 17640 8838.35 3,181.81 5,656.54 22,237.20 11,141.73 4,011.02 7,130.71
Filter fill, crushed rock,(D=0-60MM, T
3.4.6 m³ 88200 2621.31 943.67 1,677.64 110,446.09 3,282.46 1,181.69 2,100.77
= 1.5M)
3.4.7 Transition fill (D=0-200mm, T-4.0M) m³ 235200 3490.36 1,256.53 2,233.83 240,468.54 3,568.55 1,284.68 2,283.87
3.4.8 Rock fill (D=0-0.3m) m³ 500000 6975 2,511.00 4,464.00 500,000.00 6,975.00 2,511.00 4,464.00
3.4.9 Rockfill Drainage layer(D=0.03-0.2M) m³ 187830 2755.47 991.97 1,763.50 301,237.78 4,419.16 1,590.90 2,828.26
3.4.10 Rock fill Type B (D=0.1.0m) m³ 2126000 23237.18 8,365.38 14,871.80 1,892,427.52 20,684.23 7,446.32 13,237.91
3.4.11 Rip-Rap toe protection m³ 33275 395.31 142.31 253.00 63,639.38 756.04 272.17 483.87
3.4.12 Rip-Rap Slope protection m³ 129197 4264.79 1,535.32 2,729.47 38,230.83 1,262.00 454.32 807.68
3.4.13 Dam safety monitor Ls 1 1406.65 506.39 900.26 1.00 1,406.65 506.39 900.26
3.4.14 Wire mesh ton 20 42.67 15.36 27.31 20.00 42.67 15.36 27.31
3.4.15 Shot crete with mesh c20, 10cm ton 180 88.79 31.96 56.83 180.00 88.79 31.96 56.83
3.4.16 Rock bolt 5m, d28 pcs 680 56.23 20.24 35.99 680.00 56.23 20.24 35.99
3.4.17 Reinforcement ton 760 1621.5 583.74 1,037.76 485.63 1,036.12 373.00 663.12
3.4.18 Consolidation grouting m 800 99.3 35.75 63.55 2,805.00 348.16 125.34 222.82
3.5.1 Clearing and grubbing m² 307 0.5 0.18 0.32 43,673.70 70.75 25.47 45.28
3.5.2 Stripping of topsoil m² 14000 17.22 6.20 11.02 21,836.85 26.86 9.67 17.19
3.5.3 Soft excavation (easy) m² 28000 26.32 9.48 16.84 127,827.26 120.16 43.26 76.90
3.5.4 Rock excavation (normal) m³ 240000 2949.6 1,061.86 1,887.74 488,068.04 5,998.36 2,159.41 3,838.95
9/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
3.5.5 Impermeable material m² 3111 17.39 6.26 11.13 -
3.5.6 Excavation of tunnel lm 300 397.71 143.18 254.53 100.00 132.57 47.73 84.84
3.5.10 Structural concrete C35 outdoor m³ 32000 13335.68 4,800.84 8,534.84 35,998.20 15,001.89 5,400.68 9,601.21
3.5.11 Reinforcement steel ton 1200 2560.27 921.70 1,638.57 1,031.94 2,201.70 792.61 1,409.09
3.5.13 Concrete bridge, one lane (span <15m) lm 35 313.02 112.69 200.33 48.00 429.29 154.54 274.75
3.5.14 Shotcrete m³ 1000 493.28 177.58 315.70 7,264.95 3,583.65 1,290.11 2,293.54
3.5.15 Wire mesh ton 13 27.74 9.99 17.75 318.57 679.69 244.69 435.00
3.5.16 Consolidation grouting m 21700 2693.41 969.63 1,723.78 23,343.60 2,897.41 1,043.07 1,854.34
3.5.17 Rock bolt 5m, d28 pcs 23000 1901.86 684.67 1,217.19 6,777.75 560.45 201.76 358.69
4.1 Clearing and grubbing m² 3850 6.23 2.24 3.99 5,440.28 8.81 3.17 5.64
4.3 Soft excavation (normal) m³ 2500 6.65 2.39 4.26 7,221.75 19.21 6.92 12.29
4.4 Rock excavation (normal) m³ 35000 498.75 179.55 319.20 64,995.71 926.19 333.43 592.76
10/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
4.9 Plain vertical formwork m² 1450 -
4.13 Structural concrete C35 outdoor m³ 17000 6305.64 2,270.03 4,035.61 12,459.11 4,621.33 1,663.68 2,957.65
4.14 Reinforcement steel ton 1200 2560.25 921.69 1,638.56 872.14 1,860.75 669.87 1,190.88
5.1.7 Shotcrete with fiber, behind face m³ 13000 8468.6 3,048.70 5,419.90 4,440.47 2,892.66 1,041.36 1,851.30
5.1.8 Shotcrete m³ 143 74.35 26.77 47.58 2,823.13 1,467.77 528.40 939.37
11/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.1.9 Cement grouting ton 143 271.08 97.59 173.49
5.1.10 Concrete in plug m³ 1200 346.44 124.72 221.72 1,541.33 444.98 160.19 284.79
5.1.11 Concrete in tunnel lining C35 m³ 18000 9680.06 3,484.82 6,195.24 4,962.30 2,668.63 960.71 1,707.92
5.1.12 Rockbolts grouted, 5m d25 pcs 10000 756.1 272.20 483.90 12,643.40 955.97 344.15 611.82
5.1.13 Consolidation grouting m 36000 3412.08 1,228.35 2,183.73 1,364.00 129.28 46.54 82.74
5.1.14 Reinforcement steel ton 2800 5973.93 2,150.61 3,823.32 496.23 1,058.73 381.14 677.59
5.2 SURGE CHAMBER HEADRACE 11,430.75 4,115.06 7,315.69 8,290.79 2,984.67 5,306.12
5.2.10 Concrete in tunnel lining C35 m³ 2100 927.88 334.04 593.84 6,224.22 2,750.17 990.06 1,760.11
12/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.2.13 Reinforcement steel ton 1000 2133.54 768.07 1,365.47 373.45 796.77 286.84 509.93
5.2.14 Rockbolts grouted, L=3m No 1730 69.52 25.03 44.49 214.50 8.62 3.10 5.52
5.2.15 Spiling rockbolt, L=6m grouted No 865 82.07 29.55 52.52 3,582.70 339.93 122.37 217.56
5.2.16 Shotcrete with fibers m³ 2550 1631.36 587.29 1,044.07 1,170.27 748.68 269.52 479.16
5.2.17 Shotcrete m³ 1100 563.79 202.96 360.83 72.97 37.40 13.46 23.94
5.2.18 Consolidation grouting m 7800 739.29 266.14 473.15 2,983.20 282.75 101.79 180.96
5.3.4 Rockbolts grouted, L=3m No 160 6.43 2.31 4.12 835.22 33.57 12.09 21.48
5.3.10 Shotceret C20 10Cm m³ 2244 1148.38 413.42 734.96 627.76 321.26 115.65 205.61
5.3.11 Concrete C15 m³ 4000 1378.39 496.22 882.17 3,452.77 1,189.82 428.34 761.48
13/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.3.13 Curtain grouting m 1200 237.21 85.40 151.81 594.00 117.42 42.27 75.15
5.4.4 Rockbolts grouted, L=3m No 90 3.62 1.30 2.32 191.40 7.69 2.77 4.92
5.4.7 Concrete in tunnel lining C35 m³ 624 315.73 113.66 202.07 1,330.88 673.39 242.42 430.97
5.4.8 Reinforcement steel ton 62 132.28 47.62 84.66 133.09 283.95 102.22 181.73
5.5 SURGE CHAMBER TAILRACE 8,544.13 3,075.89 5,468.24 11,420.67 4,111.44 7,309.23
5.5.6 Shotcrete with fiber, behind face m³ 1000 641.07 230.79 410.28 2,148.36 1,377.25 495.81 881.44
5.5.7 Shotcrete m³ 1000 525.24 189.09 336.15 264.68 139.02 50.05 88.97
14/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.5.8 Rockbolts grouted, L=3m No 2000 80.4 28.94 51.46 70.40 2.83 1.02 1.81
5.5.10 Spilling rockbolt, L=6m grouted No 40 3.8 1.37 2.43 7,076.30 671.40 241.70 429.70
5.6.1 Excavation of TBM tunnel D=9 m lm 11300 52392.9 18,861.44 33,531.46 11,300.00 52,392.90 18,861.44 33,531.46
5.6.4 Rockbolts grouted, L=4 m No 2260 87.46 31.49 55.97 36,940.00 1,429.58 514.65 914.93
5.6.8 Reinforcement steel ton 2900 6187.29 2,227.42 3,959.87 2,193.96 4,680.92 1,685.13 2,995.79
5.6.9 Consolidation grouting m 43000 4075.55 1,467.20 2,608.35 15,822.40 1,499.65 539.87 959.78
15/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.6.11 Steel Ribs ton 73.71 150.91 54.33 96.58
5.7.1 Clearing and grubbing m² 8500 13.77 4.96 8.81 8,500.00 13.77 4.96 8.81
5.7.2 Stripping of topsoil m² 8500 10.46 3.77 6.69 8,500.00 10.46 3.77 6.69
5.7.3 Soft excavation (easy) m³ 60000 159.59 57.45 102.14 20,840.00 55.43 19.95 35.48
5.7.4 Rock excavation (normal) m³ 55000 543.4 195.62 347.78 83,360.00 823.60 296.50 527.10
5.7.5 Stabilizing rock slopes m² 120 8.44 3.04 5.40 120.00 8.44 3.04 5.40
5.7.6 Shotcrete with fiber m³ 140 89.1 32.08 57.02 702.00 446.77 160.84 285.93
5.7.10 Structural concrete C35 outdoor m³ 1100 431.76 155.43 276.33 4,151.00 1,629.31 586.55 1,042.76
5.7.11 Reinforcement steel ton 91 194.15 69.89 124.26 302.30 644.97 232.19 412.78
5.7.12 Fences, parking lots etc. LS 1 70.33 25.32 45.01 1.00 70.33 25.32 45.01
6.1 MAIN ACCESS TUNNEL 4,703.48 1,693.25 3,010.23 9,010.53 3,243.78 5,766.75
16/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.1.1 Excavation of tunnel A=50m², lm 1150 3544.26 1,275.93 2,268.33 1,515.95 4,672.10 1,681.96 2,990.14
6.1.3 Shotcrete with fibers m³ 1150 735.37 264.73 470.64 1,412.57 903.27 325.18 578.09
6.1.4 Rockbolts grouted, L=4 m No 2875 167.15 60.17 106.98 7,876.00 457.91 164.85 293.06
6.1.10 Concrete in tunnel lining C35 m³ 230 128.69 46.33 82.36 1,923.52 1,076.27 387.46 688.81
6.1.11 Reinforcement steel ton 23 49.07 17.67 31.40 115.41 246.23 88.64 157.59
6.1.14 Concrete for bottom slab C25 m³ 2,163.15 617.86 222.43 395.43
6.2.1 Excavation of tunnel A=50m², lm 420 1382.44 497.68 884.76 703.62 2,315.99 833.76 1,482.23
6.2.2 Excavation of tunnel A=30m², lm 160 383.2 137.95 245.25 731.58 1,752.13 630.77 1,121.36
17/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.2.3 Excavation of shaft A=10m², lm 170 169.02 60.85 108.17 -
6.2.6 Rockbolts grouted, Ø25,L=3m No 2550 111.89 40.28 71.61 3,296.70 144.66 52.08 92.58
6.2.12 Concrete in tunnel lining C35 m³ 204 111.04 39.97 71.07 1,549.66 843.51 303.66 539.85
6.2.13 Reinforcement steel ton 20 42.67 15.36 27.31 92.98 198.38 71.42 126.96
6.2.17 Concrete for bottom slab C25 m³ 1,922.25 549.05 197.66 351.39
18/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.3.1 Excavation of tunnel A=35m², lm 110 304.31 109.55 194.76
6.3.11 Shotcrete with fibers m³ 288 184.54 66.43 118.11 1,724.81 1,105.20 397.87 707.33
6.3.12 Rockbolts grouted, L=4 m No 721 41.92 15.09 26.83 333.00 19.36 6.97 12.39
6.3.13 Rockbolts grouted, L=6 m No 240 22.65 8.15 14.50 906.00 85.49 30.78 54.71
6.3.15 Rock bolts grouted, φ28mm,5m pcs. 232.00 19.18 6.90 12.28
6.3.16 Rock bolts grouted, φ40mm,L=10m pcs. 232.00 83.03 29.89 53.14
6.3.17 Prestressed anchor rope ,L=20m,100t pcs. 79.00 500.42 180.15 320.27
19/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.4.2 Plain vertical formwork UG m² 8160 -
6.4.4 Reinforcement steel ton 1920 4096.41 1,474.71 2,621.70 1,577.57 3,365.82 1,211.70 2,154.12
6.4.5 Grouted dowels for anchoring 25mm m 2000 29.07 10.47 18.60 -
6.4.8 Plastering, Painting walls & ceiling m² 11000 134.13 48.29 85.84 -
6.4.14 Steel structure ton 50 191.55 68.96 122.59 72.60 278.13 100.13 178.00
20/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.5.9 Reinforcement steel ton 25 53.34 19.20 34.14
6.5.13 Plastering, Painting walls and ceiling m² 700 8.54 3.07 5.47
6.6 CABLE TUNNEL and CULVERT 1,401.05 504.38 896.67 15,426.18 5,553.43 9,872.75
6.6.9 Shotcrete with fibers m³ 396 253.11 91.12 161.99 795.31 508.33 183.00 325.33
6.6.10 Rock bolts grouted, L=3m No 875 64.76 23.31 41.45 4,599.10 340.38 122.54 217.84
21/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.6.14 Plain curved formwork UG m² 53 -
6.6.15 Concrete in tunnel lining C35 m³ 70 35.27 12.70 22.57 912.23 459.69 165.49 294.20
6.6.16 Reinforcement steel ton 7 14.93 5.37 9.56 54.73 116.77 42.04 74.73
6.6.18 Concrete for bottom slab C25 m³ 1,189.98 452.17 162.78 289.39
Culvert
22/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
7.1.3 Service gate for Bottom outlet service LS 1 1130.61 226.12 904.49 1 1,130.61 226.12 904.49
7.1.4 Trash rack for Bottom outlet . LS 1 946.95 189.39 757.56 1 946.95 189.39 757.56
7.2.4 Wheel Roller gate for Intake LS 1 179.35 35.87 143.48 1 179.35 35.87 143.48
7.2.5 Hydraulic hoist for Intake gate LS 1 1415.65 283.13 1,132.52 1 1,415.65 283.13 1,132.52
7.3 Headrace & penstock 8,618.70 1,723.74 6,894.96 8,618.70 1,723.74 6,894.96
7.3.1 Adit gate with embedded parts LS 1 495.48 99.10 396.38 1 495.48 99.10 396.38
7.4.1 Sliding gate with embedded parts LS 2 672.91 134.58 538.33 2 672.91 134.58 538.33
7.5.1 Stop logs with embedded parts LS 1 606.91 121.38 485.53 1 606.91 121.38 485.53
23/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
8.1.1 Turbines and valves LS 1 8757.46 1,313.62 7,443.84 1 8,757.46 437.87 8,319.59
Main inlet valve with hydraulic control
8.1.2 LS 1 7338.74 1,100.81 6,237.93 1 7,338.74 366.94 6,971.80
system
8.1.3 Governor sys. PID electrohydrauilic LS 1 940.86 141.13 799.73 1 940.86 47.04 893.82
8.1.4 Powerhouse crane 290t/20ton LS 1 1686.7 253.01 1,433.70 1 1,686.70 84.34 1,602.37
8.1.5 Cooling water system LS 1 1578.21 236.73 1,341.48 1 1,578.21 78.91 1,499.30
8.1.6 Compressed air system LS 1 413.96 62.09 351.87 1 413.96 20.70 393.27
8.1.7 Drainage and dewatering system LS 1 609.57 91.44 518.13 1 609.57 30.48 579.09
8.1.8 Hydraulic oil system LS 1 106.26 15.94 90.32 1 106.26 5.31 100.95
8.1.9 Mobile oil treatment plant LS 1 81.51 12.23 69.28 1 81.51 4.08 77.44
8.1.12 Workshop maintenance equipment LS 1 111.85 16.78 95.07 1 111.85 5.59 106.26
8.2 ELECTRICAL 40,300.57 6,045.11 34,255.49 38,748.82 1,937.32 36,808.94
8.2.6 Control and Protection equipment LS 1 1502.24 225.34 1,276.90 1 1,502.24 75.11 1,427.13
24/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
8.2.7 Station service Transformers LS 1 190.13 28.52 161.61 1 190.13 9.51 180.62
8.2.15 Mobile oil treatment plant LS 1 54.34 8.15 46.19 1 54.34 2.59 49.18
8.3 HVAC 1,548.21 232.23 1,315.98 1,548.21 77.41 1,470.80
8.3.3 Cooling system incl. Piping LS 1 390.65 58.60 332.05 1 390.65 19.53 371.12
8.3.4 Automatic control system LS 1 87.76 13.16 74.60 1 87.76 4.39 83.37
25/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
8.5.1 33kV Transmission line double circuit LS 1 8415.46 1,262.32 7,153.14 1 8,415.46 420.77 7,994.68
8.5.3 Stand by Diesel generator LS 1 177.14 26.57 150.57 1 177.14 8.86 168.28
8.6.2 Stand by Diesel generator LS 1 218.4 32.76 185.64 1 218.40 10.92 207.48
8.6.2 230KV Switchyard civil work LS 1 2159.94 777.58 1,382.36 1 2,159.94 777.58 1,382.36
9.1 Civil works for mini hydro LS 1 1357.58 488.73 868.85 1 1,357.58 488.73 868.85
9.2 Mini hydro plant and equipment LS 1 1374.98 206.25 1,168.73 1 1,374.98 68.75 1,306.23
11.1 Site investigation works LS 1 2702.02 972.73 1,729.29 1 2,702.02 972.73 1,729.29
12.1 Engineering and design LS 1 10168.25 2,033.65 8,134.60 1 10,168.25 2,033.65 8,134.60
Provisional sum 5% of the 16km
13 LS 1 6030.01 2,170.80 3,859.21 1 5,163.41 1,858.83 3,304.58
underground tunnel bid price.
Total 608,696.23 219,130.64 389,565.59 622,765.50 224,195.58 398,569.92
26/32
SHEDULES – 2D :
SCHEDULE OF PRICES FOR EMPLOYER‘S FACILITIES TO BE PROVIDED BY THE CONTRACTOR
The Bidder shall complete the following schedule of prices for all work covered by Logistical Support for Employer.
( In 1,000USD)
Table -1
No. Description Unit Qty Total Local Foreign.
Employer‘s facilities
27/32
Table -1
2 For all House For the Employer representative LS 1 62.96 22.67 40.29
28/32
Table -1
2 All House For the Employer representative Month 48.5 30.98 11.15 19.83
3 All House For the Employer Month 48.5 77.18 27.78 49.4
4 Other facilities Month 48.5 48.00 17.28 30.72
2 All House For Employer representative Mont 48.5 32.52 11.71 20.81
5 Consumables for all housing, offices, canteen month 48 264.73 95.3 169.43
man.
6 Driver and unskilled labor 4000 1,031.56 371.36 660.2
month
Provisional and contingency budget to be
7 taken out 5% of the contract price offered by 1 Set
the Contractor
Total 16,824.04 6056.65 10767.39
29/32
SCHEDULE 3D - LIST OF FACILITY & SERVICES FOR THE EMPLOYER
( In 1,000USD)
1.5 Vehicle Operation & maintenance Land Cruiser 276000 Km 77.92 28.05 49.87
1.6 Vehicle Operation & maintenance Hi-Lux Pickup 2760000 Km 779.20 280.51 498.69
1.7 Vehicle Operation & maintenance Sedan type 300000 Km 84.70 30.49 54.21
2 Offices
3.1 Furniture
Managerial Desks With Computer Side Tables
3.1.1 8 No 9.38 3.38 6.00
Separate Drawers
3.1.2 High Back Chair 8 No 1.69 0.61 1.08
Office Desks With Computer Side Tables
3.1.3 50 No 46.89 16.88 30.01
Separate Drawers
3.1.4 Medium Back Chair 50 No 7.03 2.53 4.50
3.2 Equipment
Laptop Computers With Operating System,
3.2.1 4 No 6.38 2.30 4.08
Antivirus And MS Office Software;
Desktop Computers With UPS And With
3.2.2 Operating System, Antivirus And MS Office 26 No 30.48 10.97 19.51
Software;
3.2.3 Printers Laser Jet A4 (Black & White); 10 No 8.21 2.96 5.25
30/32
No Description Qty Unit Total Local Foreign
31/32
Schedule of Prices for 230 kv and 400kv Transmission Line
( In 1,000USD)
8.6.2 Stand by Diesel generator LS 1 218.4 32.76 185.64 1 218.40 14.24 270.56
8.6.2 Switchyard civil work LS 1 2159.94 777.58 1,382.36 1 4,661.12 1,678.00 2,983.12
32/32