Professional Documents
Culture Documents
com
subject area
Construction Geoinformation Health Technology
- Teaching unit construction -
DISADVANTAGE COMPENSATION
for the
Students : Jeffrey Quansah
Degree: Industrial engineer- construction industry
House work
Wings I, II and III have the same dimensions: L = 24.50 m, W = 7.0 m and each
component has a total of 10 full floors, each with a height of 3.0 m.
Wing IV has 3 floors, each 3.0 m high: L = 15.50 m, W = 9.10 m. Wing V
has 2 floors, each 3.0 m high: L = 13.50 m; W = 8.20 m.
The entire property has a basement with the exception of a foundation depth of
-4.50 m below ground level as a parking garage and for rooms for building
technology, which is accessed via a ramp on the eastern edge of the building.
The surrounding foundations of the basement floor protrude on all sides by 30
cm beyond the dimensions of the outer edges of the building shown in the
drawing (= are not shown in the sketch). The thickness of the base foundations
on the blinding layer (d=5cm) is 100 cm, the rising reinforced concrete walls
60cm up to the ground floor base slab (d=25 cm).
The location of the construction site is inner-city: only the eastern part has a
property boundary to another private property, while the southern, western
and northern parts are bordered by a pedestrian walkway and a surrounding
road and thus touch "public" space.
The groundwater level is well below the floor of the parking garage. The
existing building ground consists of densely packed sand/gravel with slightly
loamy parts.
2
4
(1.) Draw the excavation conceptually true to scale in the site planthat
shows how the excavation will be secured and take into account the safety
distances and workspaces. The choice of securing the excavation pit should
primarily correspond to the technical necessities, but secondarily also be
subject to objective economic aspects (= no mathematical proof).
(3.) Draw and measure the access roads to the construction site; consider
economic processes in the construction process for all deliveries - also against
the background of point (5.), which largely exclude hindrances as a result of
sensible development. In this context it should be noted that the turning
radius of a semitrailer is at least 23 m!
(4.) Plan the number of cranes or prove them for the planned
construction period:
Due to turnkey production, the number of cranes can be calculated using the
proportionality factor “m3BRI/crane*month" from the lower limit of a "mixed
construction" for the entire building from OKT 0.00 to over all 10 full floors.
1 crane month must be taken into account for the construction site set-up.
1 crane is required for the underground car park for a period of 6,800 man-
hours: the calculation shows that the underground car park is constructed with a
column of 10 men, each working 8.5 hours/day in 5 days/week.
Locate the locations and dimension the cranes in the site plan and take
into account the accessibility due to overpainting and the sufficient load
moment depending on the necessary operation of places from the
construction site facilities (see point (5.)). In this context, use an example to
demonstrate whether the crane(s) can head for the appropriate places and
also lift and move material. Make realistic (self-chosen) assumptions for your
calculations of the observed load moments.
5
(5.) The construction site requires the following facilities
Crew Quarters:
- 1 polishing container
- 1 magazine container
- 2 crew containers
- 1 sanitary trolley/container
site management
- 1 container GU
- 1 container builder
Locate the facilities in the site plan in such a way that the production process
for the entire construction site runs as smoothly as possible.
6
(6.) Determination of the total costs for the duration of use and one operating hour (€/Bh)
for use on the construction site
For each crane (simplified), the following costs should be assumed from
AVR rates “ex works yard”:
Depending on the construction site, the operating hours (operating hours/month) of the cranes, including
waiting times, account for 80% of the 160 operating hours (operating hours/month), the maintenance costs
10% of the operating costs.
At all times, each crane is fully operated by one crane operator. All tower parts
have to be transported to and from the construction site individually with a
heavy-duty low-loader. A single journey costs €1,100.
A mobile crane with 180 €/hour must be rented for assembly and dismantling
with a total duration of 5 days/crane.
In addition, 5 days/crane are required for assembly and disassembly; a crew
of 4 fitters.
A flat rate of €2,500 must be taken into account for the foundation of a crane.
The calculation average wage MASL for all wage work is €40/h. A month is
based on 20 working days with 8.5 hours/day.
7
exercise 2
The contractor has a as the largest device available in his vehicle fleet
The wheel loader bucket release and loading time is 30 seconds. The
transport route is a construction road of 100 m. The basic speed when fully
loaded is 10 km/h under load, the empty run is 20 km/h. The tipping time on
the provided truck is to be taken into account with 15 seconds.
8th
All illustrations, sketches, solutions and calculations that have been prepared must be
presented in a comprehensible manner.