ACCEPTANCE CERTIFICATE

秘鲁华为有限公司
HUAWEI DEL PERU S.A.C.

Acceptance No.: 0026339921123035517 Submission Date: 2021-12-30

Supplier Code: Z036A3 Supplier Name: TOTAL TEK S.A. SUCURSAL DEL PERU

Project Code: 564571E Engineering No.: 564571E


Project Name: Peru AM FBB IP Swap Photonics 2017 DM Strategy Project

PO No.: 604121433726-10 Millstone : AC1 - PAC,AC2 - FAC

Actual Milestone Milestone Approval


Line ShipmentNO. Site Name Site Code Item Description UOM PO Qty Accepted qty
Competed Date Type Name Information
Network Device,
4500445860 45004458
Board Expansion
_80_M24_Co 60_80_M2 881228981 2021-12- 2022-01-08,
7 1 Installation,Per SITE 1 1 AC1 AC1 - PAC
nococha_RE 4_Conoco 5 30 System
SITE,Include Site
C cha_REC
Visit

Remark:

1.This shows the final value of all work done in accordance with the PO. The whole of the works have now been substantially completed, and have satisfactorily passed all the tests on
completion specified in the contract.
TOTAL TEK S.A. SUCURSAL DEL PERU HUAWEI DEL PERU S.A.C.
Supplier Name: Name:

Signature: Signature:

Date: Date: