DETAILED UNIT PRICE ANALYSIS

Project Name: Two - Storey Residential Building

Location: Brgy. Pulong Niogan, Mabini Batangas


Item No./ Description: Provision of Field Office for the Engineer
Unit of Measurement: mo.
Quantity: 6
Designation No. of Person No. of Days Daily Rate Amount
A Labor

Sub-Total for A -

Name and Capacity No. of Units No. of Days Daily Rate Amount
B. Equipment

Sub-Total for B -
C. Total (A+B) -
D. Output per hour =
E. Direct Unit Cost (C÷D)
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
a. Rental of Office/Storage House mo 12.1 5,000.00 60,500.00

Sub-Total for F 60,500.00


G. Direct Unit Cost (E+F) 60,500.00
H. Overhead, Contingencies & Miscellaneous (OCM) per DO 197, s. 2016 0% of G -
I. Contractor's Profit (CP) 10% of G 6,050.00
J. Value Added Tax (VAT) 5% of (G+H+I) 3,327.50
K. Total Unit Cost (G+H+I+J) 69,877.50
L Total Unit Cost (K÷Quantity) 11,646.25