Overall Daily Progress Update: Earth Work Concrete Work SOG Package of Works
Overall Daily Progress Update: Earth Work Concrete Work SOG Package of Works
Date : 4-Apr-23
Terrace Under
Excavation/Soil Underground Backfilling
PC Footing RC Footings GF Columns GF Slab FF Columns FF Slab Ground
Replacement masonry works Under SOG
Masonry
Total Done 35 27 14 2 0 0 0 0 0 0
A1
Total in Progress 13 2 8 3 1 0 0 0 0 0
Total Done 48 43 24 16 6 1 1 0 0 0
A2
Total in Progress 4 5 11 2 10 0 0 0 0 0
Total Done 47 39 23 5 0 0 0 0 0 0
A3
Total in Progress 0 0 2 0 5 0 0 0 0 0
Total Done 35 30 20 6 2 0 0 0 0 0
A4
Total in Progress 18 0 2 3 4 0 0 0 0 0
Total Done 37 22 11 3 1 0 0 0 0 0
A5
Total in Progress 0 0 6 2 2 0 0 0 0 0
Total Done 47 31 10 0 0 0 0 0 0 0
A6
Total in Progress 0 0 9 0 0 0 0 0 0 0
Total Done 40 35 15 2 0 0 0 0 0 0
A7
Total in Progress 4 5 17 6 2 0 0 0 0 0
Total Done 36 33 12 0 0 0 0 0 0 0
A8
Total in Progress 0 3 19 3 0 0 0 0 0 0
Total In Progress 39 15 74 19 24 0 0 0 0 0