You are on page 1of 2

1

IEEE 519 Update From a Utility Perspective


Reuben F. Burch IV, Senior Member, IEEE

interpreted and/or applied. IEEE 519 is certainly no exception


Abstract—IEEE 519-1992 has been widely accepted and used here. However, work done by the IEEE 519 TF, and its
for many years now. During these years, utility engineers have affiliated IEEE 519A TF, through TF meetings, conference
found the pros and cons of applying it on their systems. This papers, panel sessions, and tutorials has gone a long way to
paper will describe one engineers experience in applying the
educate utility engineers on the intent of the Recommended
document and explain how some of the proposed changes in the
soon to be balloted update of this Recommended Practice will be Practice and therefore its proper usage. By having an
beneficial. application guide, which will soon appear as IEEE 519.1, the
TF has taken real world cases and used them to show how the
Index Terms—Harmonics, distortion, interharmonics. limits should be applied. This is very beneficial to the
engineer charged with insuring compliance to the limits of
I. INTRODUCTION customers connected to the utility grid.
The application of the current and voltage distortion tables
T HIS document will describe the pros and cons of using
IEEE 519-1992 in a utility environment. This will reveal
how the existing version of the Recommended Practice works
has often been cause for confusion to new users. The basic
premise is that the utility, since it controls the method of
in the real world. It will also reveal some areas that are serving the load and therefore the resulting system impedance,
lacking and show how proposed updates to the Recommended should be responsible for meeting the harmonic voltage
Practice will address these issues. IEEE 519 is readily distortion limits. Failure to do so basically implies that the
recognized as providing harmonic distortion limits on the service method being considered lacks sufficient system
utility system. Over time, these limits have been accepted by strength to support the planned harmonic load addition. The
both utilities and their customers as criteria. Though the customer, on the other hand, is responsible for meeting the
Recommended Practice is not uniformly applied, it is never harmonic current distortion limits as he controls both the
the less recognized as an authority on harmonic issues. The amount and type harmonic load being added to the system.
harmonic current and voltage distortion limits are the most These concepts are now fairly well understood after years of
recognized part of IEEE 519 as they are widely quoted in usage.
books and papers. Voltage notching and the telephone One related area that the updated version will improve on
influence factor (TIF) are other areas for which recommended is in the provision of a standard harmonic metering method.
limits are supplied but their usage isn’t as widely known or While the limits themselves seem to be understood, the ability
applied. Furthermore, in the case of interharmonics and to consistently and uniformly monitor a given system is not a
harmonic bursts, previous versions of IEEE 519 had no limits given. There exist a number of instruments with which to
what so ever. In fact, these topics were not previously measure both harmonic voltage and current distortion levels.
covered. Therefore, the changes being considered will be At issue, however, is how to use these many varied
welcomed as they will make this Recommended Practice a instruments to collect harmonic data so that adherence to the
more well rounded and comprehensive document for the limit tables in IEEE 519 can be accurately determined. The
utility engineer’s use. The updates also provide for a standard use of existing meters requires the installer to have some
metering method which will insure that field measurements knowledge of the site to be metered, to know what harmonic
are uniformly collected and hopefully that they will be more frequencies to meter, and to further know how often to take
uniformly interpreted. As with any Recommended Practice or harmonic snapshots. After the data has been collected, the
Standard, as knowledge increases and as technology advances, user must then know how to properly interpret the results such
improvement will follow and if found to be true of the that compliance with the Recommended Practice can be
proposed revisions. determined. When the proper operation of equipment
connected to the utility system is at stake, or the potential for
II. TECHNICAL WORK PREPARATION disturbing other customers is possible, it is critical that field
As with any Standard or Recommended Practice, it should data be collected correctly. The updated version of IEEE 519
not be automatically assumed that it will be universally will employ the harmonic measurement method currently
advocated by IEC 61000-4-7(2nd edition). By adopting this
measurement procedure, all the variations in meter
Reuben Burch is a Principal Engineer with Alabama Power Company,
Birmingham, AL 35291 USA (e-mail: rfburch@southernco.com). configuration that presently exist will be eliminated. The
resulting collected data will then be consistent from meter to
2

meter and from location to location providing more useable One other point of confusion is the customer demand
results. Incorrectly metered data and/or improperly which should be used in determining the total harmonic
interpreted data only tend to frustrate and alienate utilities and current demand distortion, Itdd. This should be the average
their customers. The proposed metering method should be integrated demand level at which the customer consistently
more readily acceptable by both parties. operates their facility. Using this method, demand levels that
The existence of interharmonics, also called non-integer are inconsistent with normal operation would be factored out
harmonics, has long been known but there has always been a and not used. The use of artificially high demand levels will
question as to how to handle them. The existing allow potentially harmful levels of harmonics to appear to
Recommended Practice didn’t address them at all, it only meet the Recommended Practice. Conversely, an artificially
provided a definition. This left their handling up to the low demand level will indicate that a load would violate the
imagination of the utility engineer. They are commonly found criteria when in fact it would be serviceable. This discrepancy
with loads such as cycloconverters, arc furnaces, and certain has been incorrectly used customers as a means of reaching
types of converter technologies. The appropriate limit levels compliance with IEEE 519. The misunderstanding of this
have been a question needing attention for many years now. concept has also caused utility engineers to incorrectly
In many cases, due to lack of guidance for a limit, utilities evaluate compliance of a customer. The proposed revision
would simply say that “no problems due to interharmonics are provides language that will insure the proper demand is used
allowed”. This is a rather nebulous statement; confusing both when determining compliance of harmonic current levels.
to the utility as well as to their customer. However, with
experience gained by the IEC, some limits for the updated III. THINGS STILL TO BE DONE
Recommended Practice will be provided. This will be a A problem arose such that a malfunctioning converter
welcome addition. injected levels of the 75th harmonic onto the utility grid. This
Another specific area of interest to utilities relating to harmonic interacted with components in the tank circuit of
interharmonics is Sub Synchronous Resonance (SSR). Low CCVT’s and caused them to fail. This also caused damage to
interharmonic levels can potentially cause damage to turbine components of the carrier relaying system. At this point, there
generators if any interharmonic frequencies coincide with a are no recommendations in either the current or the proposed
modal frequency of the turbine generator. A modal frequency revision of IEEE 519 as to limits for this harmonic level
is one of the natural resonant frequencies of the turbine which would prevent damage. This is due to two reasons.
generator and they are below the synchronous frequency. This First, IEEE 519 has traditionally only addressed harmonics up
type event is a low probability event but one that can have a to the 25th. Other IEEE documents are charged with
tremendous impacts should it occur. Therefore, the close specifying limits above that frequency. However, these other
electrical proximity of interharmonic producing loads near documents do not normally relate to the type issues covered in
generation plants should trigger a prudent review of this IEEE 519. The second reason is that if IEEE 519 did cover
phenomenon to insure that no damage will occur to a turbine higher frequencies, then the issue would be in how to
generator. In the past, engineers did not know what level of determine a limit such that problems of this type would be
interharmonics could potentially damage turbine generators. eliminated. This is one item for consideration in a future
revision of IEEE 519.
The revised version of IEEE 519 will offer some guidance to
those performing SSR studies.
IV. CONCLUSIONS
An area receiving attention in recent years is that of time
varying harmonics. The current and voltage harmonic The actual application of IEEE 519 has taken many varied
distortion limits provide in the IEEE 519 tables are generally paths. With some understanding of the underlying principals it
thought of as being constant harmonic levels. However, it is can be properly and more uniformly applied to the eventual
often noted that the harmonic levels indeed vary over time. benefit of all concerned. Improvements proposed in the
revised IEEE 519 will aid the end-user in this task.
Because of this time variation, limitations in the stated criteria
may be needed. Following the publication of IEEE 519-1992,
V. BIOGRAPHIES
this phenomenon was observed with the operation of certain
process equipment and the beginnings of limits were
Reuben F. Burch IV (M’70, SM’97) was born in Eastman, Georgia on August
proposed. In the intervening years, the application of 5, 1948. He graduated from Auburn University.
statistical methods has been applied to this area. These His is employed by Alabama Power Company in Birmingham, AL. and
concepts have been recognized by the IEC and included in conducts harmonic and transient studies for industrial loads served from the
their standards for some years. This is a long needed area of transmission system.
He is a member of the IEEE, PES, and IAS and is involved with numerous
inclusion in the Recommended Practice as it has been difficult TF’s and WG’s relating to harmonics and flicker. He is the current Chair of
for utility engineers to determine how to handle these events. IEEE 1453.
The proposed changes to the IEEE 519 will incorporate
methods by which the utility engineer can properly handle
time varying loads of various durations, which are a common
occurrence these days.

You might also like