PM 102 Certification Exam

Prometheus Group University

Name: ____________________________________

SAP ID: ____________________________________

Planner Group: ______________________________

Version 6
Multiple Choice
1. A Work Order has been planned but is awaiting selection by the ranking group. What status
should the order be in?
A. In Planning
B. Planning Complete
C. Ready to Schedule
D. Scheduled

2. A Break-in arises and causes an over-capacity with the current schedule, which of the following
type of order should be bumped out of the schedule first?
A. PM
B. High Priority
C. Targeted Work
D. Fill-in Work

3. Which of the following transactions is used to graphically schedule work orders in SAP?
A. /PGPNL/KPIP
B. /PROGROUP/NAV
C. CM25
D. /PGP/SCHEDULER

4. One of your technicians gets approved for vacation in a couple of months. What should be
done?
A. Create a capacity interval for the planned drop in capacity ahead of time
B. Reduce the standard available capacity on the day he leaves for vacation
C. Do nothing, it won’t affect our schedules
D. Change the display settings to turn yellow and/or red at a lower percentage

5. Which of the following KPIs will track a job that breaks into the schedule?
A. Finish Date Compliance
B. Man Hour Compliance
C. Reactive Work
D. Due Date Compliance

6. Your business wants the Basic Start and Basic Finish dates of the order to reflect the dates the
work is being scheduled for, as well as all materials being required on the operation dates.
Which Adjust Dates setting do you recommend:
A. 2
B. Blank
C. 3
D. 1
7. Subsort Fields are built within which part of Scheduler?
A. Display Settings
B. Layout
C. Variant
D. Print Settings

8. I want to produce a field schedule showing every job taking place throughout the week and
what steps/groups are involved. Which of the following should be used?
A. IW38 List Printed and Sorted by Order Basic Start Date
B. Scheduler Print out sorted by Order Basic Start Date
C. Excel Dump by Earliest Start Date
D. Scheduler Print out with Work Center Page Breaks sorted by Earliest Start Date

9. In the Gantt chart, which function will move all selected work orders to the exact same date and
time?
A. Change by Delta
B. Auto Level
C. Set Basic Date/Time
D. Collective Confirmation

10. When reviewing the current schedule, it is discovered that a key job is going to slip. The job in
question was targeted by the ops leads, but we know for sure it isn’t going to get done this
week. What should we do?
A. Leave the job as it sits and hope we find the time to get it done
B. Set it to Planning Complete and review it again later
C. Confirm it so we don’t lose compliance, and if it comes up again we’ll just break it in
D. Set to Ready to Schedule to make sure it gets onto next week’s schedule

11. A technician calls in sick today. Which of the following should you do for the capacity hit?
A. Create a capacity interval for the drop in manpower
B. Reduce the standard available capacity
C. Do nothing, it was unplanned and is too late to affect our schedules
D. Change the display settings to turn yellow and/or red at a lower percentage.

12. Auto-level is running through its program and encounters a job that will use up 5% of available
capacity, and we have set the auto-level limit to 100% with Daily granularity. Currently you have
the following loads: Monday – 98%, Tuesday – 96%, Wednesday – 94 %, Thursday – 82%. Which
day will auto-level put the job on?
A. Monday
B. Tuesday
C. Wednesday
D. Thursday
13. A lead needs to quickly pull up his up-to-date schedule on a regular basis and isn’t familiar with
SAP. Which method would best suit his/her needs?
A. Navigator with preset variants
B. SAP Favorites list
C. Excel dumps of the schedule
D. A PDF Print-out from Scheduler

14. Which of the following quadrants of the Scheduler planning board resembles the List Edit the
most?
A. Capacity Details
B. Resource List
C. Gantt Chart
D. Item Details

15. Which function can allow for first-pass scheduling based on capacity availability?
A. Auto Level
B. Set Basic Date/Time
C. This function does not exist in Scheduler
D. Mass Change

16. Which of the following KPIs will track how much of all work performed came from the locked
schedule?
A. Reactive Work
B. Finish Date Compliance
C. Scheduled Work
D. Man Hour Compliance

17. In an operation, which of the following affects the capacity section of the planning board?
A. Work
B. Number
C. Duration
D. Control Key

18. A medium priority General Maintenance Work Order is planned and approved. When this work
order is chosen by operations to execute per resource availability, during which section of the
Tiered Scheduling model will this order be scheduled?
A. Tier 1
B. Tier 2
C. Tier 3
D. Tier 4
19. Which of the following people should be involved in work selection for the targeted work?
A. Operations
B. Maintenance leads
C. Scheduler
D. All of the Above

20. One of the operations in your selection has a constraint. Running auto level will:
A. Change the constraint to whenever the job can fit
B. Leave that order alone since it has a constrained step and move onto the next order
C. Remove the constraint and reschedule the order
D. Not run until all constraints have been removed

21. Which of the following is used to capture the weekly baseline of your schedule for KPI purposes?
A. Snapshot Generator
B. Printing the Scheduler Planning board
C. Dump to Excel
D. IW38

22. When tracking KPIs, which field is used to determine Finish Date compliance, in conjunction with
No Remaining Work?
A. Work Start
B. Work End
C. Posting Date
D. Actual Work

23. In Scheduler, I want to set the capacity section to turn yellow once I reach 85% loaded, and then
turn red once I clear 110%. How would you make this setting?
A. Use the Total Capacity option of the selection screen
B. In the Display Settings, set Capacity Utilization fields to Percentage Over: 110 and
Percentage Under: 85
C. Against the Notification
D. In the Display Settings, set Capacity Utilization fields to Percentage Over: 10 and
Percentage Under: 15

24. Which of the following Scheduler-only selection options adds additional days to the beginning
and end of your Gantt chart beyond just the data being pulled in?
A. Planning Days in the Future/Past
B. Scheduling Date Range
C. Capacity Display Date Range
D. Display Settings
25. During this class, we focused on which scheduling method?
A. Work Lists
B. Free Form Scheduling
C. Percentage-based Scheduling
D. Tiered Scheduling

True or False
26. When a break-in occurs, PMs should be the first things to move out of the schedule.
A. True
B. False

27. Confirmed operations can still show up on the planning board for tracking purposes if they are
not explicitly excluded.
A. True
B. False

28. A job is going to slip from the current week’s schedule. Rescheduling or changing the status of
the job will hide it from the KPI Reports to avoid any compliance hit.
A. True
B. False

29. Ready to Schedule status should be used to indicate any backlog jobs, regardless of availability.
A. True
B. False

30. A job must be visible to the user in the planning board in order for the capacity to be recognized.
A. True
B. False

31. Auto level will not reschedule a work order that has a constraint on any one of its operations.
A. True
B. False

32. When checking KPIs from a weekly perspective, an operation that was scheduled to finish on
day 3 of the schedule but is final confirmed on day 6 will be considered Finish Date Compliant.
A. True
B. False

33. Schedulers can easily work off of a single layout for all of their scheduling, tracking, and
reporting needs.
A. True
B. False
34. Operations should be involved in work selection and schedule reviews.
A. True
B. False

35. When updating work center capacity for a short period of time, just update the standard
available capacity when the time comes and then change it after the fact.
A. True
B. False

Practical
Please perform the following in SAP and be sure to use your assigned planner group. There is no need
to write anything down for these, as they will be graded out of SAP directly.

1. Your Instrumentation team is going to be short a man for the next 3 weeks. Address this
situation before accidentally overscheduling the crew.

2. It’s time to produce a schedule for next week. Build out the schedule.

3. Now that the week’s schedule has been built and approved, let’s make sure it is locked and
ready to track.