Professional Documents
Culture Documents
Feasibility Assessment of A Hydropower P
Feasibility Assessment of A Hydropower P
Advisor
Dr.Binaya Kumar Mishra
Er. Shankar Lamichhane
By
Mukti Budathoki (2015-1-04-0240)
Prakash Khanal (2015-1-04-0247)
Sagar KC (2015-1-04-0257)
Samir Lamichhane (2015-1-04-0261)
Sandeep Kshetri (2015-1-04-0262)
Seema KC (2015-1-04-0265)
Sudip Koirala (2015-1-04-0271)
School of Engineering
Faculty of Science and Technology
Pokhara University
Date: 2076/08/04
FEASIBILITY ASSESSMENT OF A
HYDROPOWER PLANT: A CASE STUDY IN
LOWER MARDI RIVER, NEPAL
Advisor
Dr.Binaya Kumar Mishra
Er. Shankar Lamichhane
By
Mukti Budhathoki (2015-1-04-0240)
Prakash Khanal (2015-1-04-0247)
Sagar KC (2015-1-04-0257)
Samir Lamichhane (2015-1-04-0261)
Sandeep Kshetri (2015-1-04-0262)
Seema KC (2015-1-04-0265)
Sudip Koirala (2015-1-04-0271)
School of Engineering
Faculty of Science and Technology
Pokhara University
Date: 2076/08/04
BONAFIDE CERTIFICATE
Dr./Er.______________________ Er.________________
External Examiners Supervisor
Affiliation Designation
Addresses Affiliation
Dr./Er.__________________
Head of Department
Affiliation
ACKNOWLEDGEMENT
We would like to express our deep sense of gratitude to Professor/ Assoc. Professor/ Assistant
Professor Dr.Binaya Kumar Mishra and Er. Shankar Lamichhane of School Engineering,
Faculty of Science and Technology Pokhara University Lekhnath Kaski for their continuous
guidance and encouragement. It would have been impossible to accomplish this project without
his/her valuable suggestion.
We would like to express deepest thanks to Dean Er. Buddhi Raj Joshi, Director Er. Arjun
Gautam and project co-ordinator Er. Rajendra Aryal of School of Engineering for their valuable
suggestions and co-operation at different stages during this project period.
Page | i
ABSTRACT
The report’s main focus is on the study of Lower Mardi River Hydropower project for its
feasibility analysis; the works included in this report are hydrological study, survey, development
of contour maps of the site. The Mardi River is located in the Kaski district with catchment of
97.2 km2 at the point where preliminary location of head works is fixed. Lower Mardi River
hydropower project has installed capacity of 2.61MW.
Additionally, the flood analysis of river has been carried out with different methods so as to
make the proposed weir capable of passing the flood discharge without any structural damage to
the components of the hydropower. The flood discharge of approximately for a return period of
100 years has been calculated from Modified Dicken’s method. This report also includes the
result of the survey works carried out in the project site. The survey data has been represented as
the topographic map of the area of dam, power house and the probable alignment route of canal
and penstock. On the second part of the project, design of components like: weir, headrace canal,
sand trap, connecting channel, forebay, penstock, spillway, anchor blocks, turbine, powerhouse
and tailrace.
Weir was designed as Tyrolean weir with height of weir 5.5 m. The connecting canal of
100mlong supplies water to sand trap. Sand trap was of dimension179*5.7*6.9m .The sand trap
and forebay were connected with canal of width 4m and 800m long. Spillway was designed in
forebay and sand trap to discharge the excess of water. The forebay was 62.5 in length and 8.5m
in depth. Then finally penstock was 200m long with diameter of 2.10m.
The total cost of project was found to be NRs574.78 million, IRR 13.4 , B/C ratio 1.13 and
payback period 8.24 years.
Page | ii
TABLE OF CONTENTS
ACKNOWLEDGEMENT i
ABSTRACT ii
TABLE OF CONTENTS iii
LIST OF FIGURE viii
LIST OF TABLES ix
LIST OF ABBREVATIONS x
LIST OF SYMBOLS xi
SAILENT FEATURES OF THE PROJECT xii
1. Introduction
1.1 General……………………………………………………………. 1
1.2 Study Objectives………………………………………………….. 1
1.3 Scope of works……………………………………………………. 1
1.4 Study Execution………………………………………………....... 2
1.5 The present report………………………………………………… 2
2. Description of the Project Area
2.1 Project location…………………………………………………… 4
2.2 Physical features………………………………………………….. 5
2.3 Accessibility………………………………………………………. 5
3. Literature Review
3.1 Background……………………………………………………….. 6
3.1.1 Power situation in Nepal………………………………………. 6
3.1.2 Domestic power demand and supply………………………….. 6
3.1.3 Load forecast…………………………………………………... 7
3.1.4 Energy Consumption pattern of Nepal………………………… 7
3.1.5 Development of the grid system and power transmission…….. 8
3.1.6 Power Distribution plan……………………………………….. 8
3.1.7 Legal provision to invest in hydropower sector in Nepal……... 8
3.2 Components of hydropower plants……………………………….. 10
3.2.1Weir and under sluice structures……………………………….. 10
3.2.1.1 General…………………………………………………….. 10
3.2.1.2 Design consideration of diversion weir…………………… 11
3.2.1.3 Elevation of weir crest…………………………………….. 11
3.2.1.4 Length of weir and under sluice…………………………… 11
3.2.1.5 Shape of the spillway……………………………………… 12
3.2.1.6 Forces acting on weir……………………………………… 12
3.2.1.7 Modes of failure and criteria for structural stability of weir. 13
3.2.1.8 Protection work for weir structure………………………… 13
3.2.2 Intake Structure………………………………………………… 14
3.2.2.1 General…………………………………………………….. 14
3.2.2.2 Design consideration of intake structures…………………. 14
3.2.2.3 Protection works…………………………………………... 15
3.2.23Gravel trap…………………………………………………….. 15
3.2.3.1General……………………………………………………... 15
iii
3.2.3.2 Design consideration………………………………………. 15
3.2.3.3 Protection works………………………………………….... 15
3.2.4 Settling Basin………………………………………………….. 15
3.2.4.1 General……………………………………………………. 15
3.2.4.2 Design Consideration……………………………………... 16
3.2.4.3 Protection works………………………………………….. 16
3.2.5 Headrace canal…………………………………………………. 16
3.2.5.1 General…………………………………………………….. 16
3.2.5.2 Design Consideration……………………………………… 16
3.2.5.3 Protection works…………………………………………... 17
3.2.6 Forebay………………………………………………………… 17
3.2.6.1 General…………………………………………………….. 17
3.2.6.2 Design consideration………………………………………. 17
3.2.6.3 Optimisation……………………………………………….. 17
3.2.6.4 Protection work……………………………………………. 18
3.2.7 Penstock……………………………………………………….. 18
3.2.7.1 General…………………………………………………….. 18
3.2.7.2 Design consideration………………………………………. 19
3.2.7.3 Protection works…………………………………………... 19
3.2.8 Anchor block…………………………………………………... 19
3.2.9 Powerhouse……………………………………………………. 19
3.2.9.1 General…………………………………………………….. 19
3.2.9.2 Powerhouse size…………………………………………… 19
3.2.9.3 Height of powerhouse……………………………………... 19
3.2.10 Tailrace……………………………………………………….. 20
3.2.10.1 General…………………………………………………… 20
3.2.10.2 Design Criteria…………………………………………… 20
3.2.11 Electromechanical Units……………………………………... 20
3.2.11.1 General…………………………………………………… 20
3.2.11.2 Turbine…………………………………………………… 20
3.2.11.3 Generator…………………………………………………. 21
3.2.11.4 Exciters…………………………………………………… 21
3.2.11.5 Ventilation cooling……………………………………….. 21
3.2.11.6 Transformers……………………………………………... 21
3.2.11.7 Control room equipment…………………………………. 22
3.2.11.8 Switch gear……………………………………………….. 22
3.2.12 Transmission lines……………………………………………. 22
3.2.12.1 General…………………………………………………… 22
3.2.12.2 Design aspect of transmission line……………………….. 23
4. Field Survey and Investigation
4.1 Topographical Survey…………………………………………….. 24
4.1.1 Available information and maps………………………………. 24
4.1.2 Surveying……………………………………………………… 24
4.1.3 Mapping……………………………………………………….. 25
4.1.4 Hydrological Investigations…………………………………… 26
4.1.5 Collection of available hydrological and metrological data…... 26
4.2 Sediment investigation……………………………………………. 26
4.3 Transmission line Survey…………………………………………. 27
5. Hydrology
5.1 Hydrological study………………………………………………... 28
iv
5.1.1 Catchments Characteristics……………………………………. 28
5.1.2 Hydrometric Techniques………………………………………. 31
5.1.3 Long term stream flow analysis……………………………….. 31
5.1.3.1 Medium Irrigation Project method………………………… 31
5.1.3.2 Flow duration curve……………………………………….. 32
5.1.4 Regional flood frequency analysis…………………………….. 33
5.1.4.1 WECS Formula……………………………………………. 33
5.1.4.2 Modified Dickens Formula………………………………... 34
6. Alternative Layouts and Recommended Project Layout
6.1 Study of possible alternative layout………………………………. 36
6.2 Presentation of recommended layout……………………………... 37
7. Plant Optimization Study
7.1 General……………………………………………………………. 38
7.2 Assumptions………………………………………………………. 38
7.3 Approach and methodology………………………………………. 38
7.4 Economic Analysis……………………………………………….. 39
7.5Recommendation of installed capacity for feasibility design……... 41
8. Project Description and Design
8.1 Basis of design……………………………………………………. 42
8.2 General arrangement of project components……………………... 43
8.3 Design criteria…………………………………………………….. 44
8.3.1 Hydraulic and functional criteria……………………………… 44
8.3.2 Stability and structural criteria………………………………… 44
8.4 Description of project components……………………………….. 45
8.4.1 Head works…………………………………………………… 45
8.4.1.1 Tyrolean Weir……………………………………………... 45
8.4.1.2 Connecting Channel……………………………………….. 46
8.4.1.3 Sand trap…………………………………………………... 46
8.4.1.4 Headrace canal…………………………………………….. 46
8.4.1.5 Forebay…………………………………………………….. 47
8.4.1.6 Penstock pipe……………………………………………… 47
8.4.2 Powerhouse complex………………………………………….. 48
8.4.2.1 Powerhouse………………………………………………... 48
8.4.2.2 Tailrace…………………………………………………….. 49
8.4.2.3 Switchyard………………………………………………… 49
8.5 Access Road………………………………………………………. 49
8.6 Generating Equipment……………………………………………. 49
8.6.1 General………………………………………………………… 49
8.6.2 Mechanical Equipment………………………………………... 50
8.6.2.1 Inlet Valves………………………………………………... 50
8.6.2.2 Turbines…………………………………………………… 50
8.6.3 Hydraulic Steel Structures…………………………………….. 55
8.6.3.1 General…………………………………………………….. 55
8.6.3.2 Gates……………………………………………………….. 55
8.6.3.3 Stop logs…………………………………………………… 56
8.6.3.4 Intake Trashrack…………………………………………… 56
8.6.4 Powerhouse electrical equipment……………………………… 56
8.6.4.1.Generators and Ancillaries………………………………... 56
8.6.4.2 Excitation System…………………………………………. 57
8.6.4.3 Protection System…………………………………………. 58
v
9. Power and Energy
9.1 General……………………………………………………………. 59
9.2 Reference Hydrology……………………………………………... 60
9.3 Input parameters and assumptions………………………………... 60
9.4 Rated Efficiencies………………………………………………… 60
9.5 Calculation of power and energy…………………………………. 60
10. Construction Planning
10.1 General………………………………………………………...... 63
10.2 Access Road…………………………………………………….. 63
10.3 Camping facilities………………………………………………. 64
10.3.1 Water Supply………………………………………………… 64
10.3.2 Communication……………………………………………… 64
10.3.3 Camp Electrification………………………………………… 64
10.4 Contract Package……………………………………………….. 64
10.5 Implementation Schedule………………………………………. 65
11. Initial Environment Examination
11.1 Project Description……………………………………………… 69
11.2 Study Methodology……………………………………………... 69
11.3 Existing environmental acts, rules, policies, guidelines and 69
conventions…………………………………………………………….
11.4 Existing Environmental Condition……………………………… 69
11.4.1 Physical Environment……………………………………….. 69
11.4.2 Biological Environment……………………………………... 70
11.4.3 Socio-economic and cultural environment…………………... 70
11.5 Impact Assessment……………………………………………… 70
11.5.1 Physical Impacts……………………………………………... 70
11.5.2 Biological Environment……………………………………... 70
11.5.3 Socio-Economic and cultural environment………………….. 71
11.6 Alternative Analysis……………………………………………... 71
11.7 Mitigation and Enhancement……………………………………. 71
11.7.1 Physical Environment……………………………………….. 71
11.7.2 Biological Environment……………………………………... 71
11.7.3 Socio-economic and cultural environment………………….. 72
11.8 Environment monitoring………………………………………… 72
11.9 Conclusion………………………………………………………. 72
12. Cost Estimate
12.1 General…………………………………………………………... 73
12.2 Criteria and assumptions………………………………………… 73
12.3 Estimating methodology………………………………………… 73
12.3.1 Land acquisition, camp and construction power facilities…... 74
12.3.2 Civil Works………………………………………………….. 74
12.3.2.1 Indirect cost………………………………………………. 75
12.3.2.2 Resource cost……………………………………………... 75
12.3.2.3 Electrical and mechanical equipment…………………….. 76
12.3.2.4 Switch yard and transmission line………………………... 76
12.3.2.5 Physical contingencies…………………………………… 77
12.3.2.6 Environmental mitigation and management cost………… 77
12.3.2.7 Engineering, management and administrative costs……... 77
12.3.2.8 Owner’s cost……………………………………………… 77
12.3.2.9 Insurance of works……………………………………….. 77
vi
12.3.2.10 Capital cost……………………………………………… 77
13. Project Evaluation
13.1 Economic Analysis………………………………………………. 78
13.2 Financial Analysis……………………………………………….. 78
13.3 Sensitivity Analysis……………………………………………… 79
14. Conclusions and Recommendation
14.1 Conclusion……………………………………………………….. 80
14.2 Recommendation………………………………………………… 81
References
vii
LIST OF FIGURES
Figure no. Title Page no.
viii
LIST OF TABLES
Table no. Title Page no.
ix
LIST OF ABBREVIATIONS
Abbreviations Meaning
KW - Kilowatt
MW - Megawatt
GIS - Geographic Information System
IEE - Initial Environment Examination
INPS - Integrated Nepal Power System
SHP - Small Hydro Plant
NEA - Nepal Electricity Authority
Gwh - Giga Watt hour
FY - Fiscal Year
KV - Kilo Volt
Km - Kilometre
VDC - Village Development Committee
WECS - Water and energy commission secretariat
ADB - Asian Development Bank
OPEC - Organisation of Petroleum Exporting
Countries
SAARC - South Asian Association for Regional
Cooperation
CG - Centre of gravity
SSF - Shear Stability Factor
ST - Station
BM - Benchmark
EDM - Electronic Distance Measurement
BC - Benefit cost
MIP - Medium irrigation Project
DHM - Department of Hydrology and Metrology
ROR - Run of river
DEM - Digital Elevated Model
IRR - Internal Rate of Return
TEWAC - Total Enclosed water air cooling
PPA - Power Purchase Agreement
x
LIST OF SYMBOLS
Symbols Meaning
xi
SALIENT FEATURES
LOWER MARDI RIVER HYDROPOWER PROJECT
PROJECT LOCATION:
Development region : Western
Zone : Gandaki
District : Kaski
Headwork site : Machhapuchhre VDC
Powerhouse site : Machhapuchhre VDC
Geographical Co-ordinate
Latitude : 28019'00"N to 280 29'00"N
Longitude : 83050'00"E to 83056'00"E
GENERAL:
Name of River : Mardi River
Nearest town : Pokhara
Type of Scheme : Run-of-River
Gross Head : 30 m
Installed Capacity : 2.61MW
Average Annual Energy : 14.06GWh
WEIR
Type : Tyrolean, Concrete Structure
Length : 21.78 m
Crest Elevation : 1098.6.5 masl
Height : 5.5 m
xii
River Bed level at weir site : 1094.34 m.a.s.l
Length of stilling basin : 8.09m
Width of stilling basin : 4.00m
CONNECTING CHANNEL
Shape : Rectangular
Length : 100m
Bed width : 1.43 m
Total depth : 4.25 m
Channel Invert EL : 1090.19 m.a.s.l
Longitudinal slope : 0.0050
Total headloss : 1.81m
SANDTRAP
Length : 179m
Width : 5.7m
Height : 6.9m
Flushing Channel width : 1.5m
Longitudinal bed slope of flushing channel : 0.0050
Number of trash rack bars : 73
Total Headloss : 0.22m
HEADRACE CHANNEL
Headrace invert elevation : 1090.96 m.a.s.l
Clear width : 4m
Length : 800m
Longitudinal slope : 0.0006
Depth of flow : 1.6 m
Side slope : 1.5
Total headloss : 0.46m
xiii
FOREBAY
Width at start : 38m
Width at end : 30m
Length : 62.5m
Total depth : 8.5m
Total headloss : 0.006m
Longitudinal slope : 2%
Number of trashrack bars : 40
Spill pipe diameter : 2.5m
Flushing pipe diameter : 0.80m
PENSTOCK PIPE
Material : Steel
Length : 200m
Finished Diameter : 2.10 m
Thickness : 6 to 8mm
Number of trash rack bars : 25
Number of Anchor Blocks : 4
POWERHOUSE
Size (Length x Breadth x Height) : 35 m * 16 m * 10 m:
Number of Generating Unit : 2
Turbine Type : Horizontal Shaft, Francis
Generated Capacity : 2.61 MW
Net Head : 27.88 m
Rated Turbine Efficiency : 92%
Rated Generator Efficiency : 96.3%
Rated Runner Efficiency : 98%
xiv
Dry season Energy : 3.008 GWh
Wet season Energy : 11.13GWh
Annual Energy Generation : 14.13GWh
ECONOMY
Total Project Cost : NRs 574.78 million
IRR : 13.30%
Benefit/ Cost Ratio : 1.13
Payback Period : 8.24 years
xv
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 1
INTRODUCTION
1.1 GENERAL
Lower Mardi River Small Hydropower Project was identified as potentially viable project by
student of School of Engineering (Group -9), Pokhara University during the desk study report
conducted in year 2019. After identifying the project we applied proposal for survey and other
works in Department of Civil Engineering, Pokhara University. We obtained the letter of approval
for further process of the project from Department of Civil Engineering for an installed capacity
of 2610 KW.
Under the initiation of our project, there were several visits made for investigation, possible
layouts, development possibilities and power evacuation possibilities.
After receiving the letter of approval, we initiated immediate preparation of the feasibility reports
to move forward for project implementation. The project members were involved in survey,
investigation and environmental study of the project.
This report is prepared according to the outcome of investigations at feasibility level, planning
and design for the Lower Mardi River Hydropower Project.
Our group identified the project components of the scheme. We surveyed the finally selected
scheme from late July 2019 to first August 2019.
The inception report with field survey / investigation programme includes the survey works of the
project area including the head-works, waterways and powerhouse sites. Catchment area
calculation was done with the help of Google earth application and Arc Gis tool. During the field
reconnaissance visit river discharge measurements were also collected.
The plant optimization study to decide the optimum scale of development was undertaken. The
result shows that plant capacity with 2.08 MW under hydrological firm flow of 40% (Q40) gives
the best economic return and is recommended as optimum scale for development.
The feasibility level design of the project components has been carried out and the necessary
drawings prepared. Quantity estimation, cost estimation and economic as well as financial analysis
have also been carried out. The feasibility study report has been prepared by including all the
information mentioned above and based on the “Guidelines for study of Hydropower Projects”
prepared by the Department of Electricity Development.
Chapter – 4 : Field Survey and Investigation: Includes brief outline of the site visits,
survey works and investigation and data collection carried out for
hydrological and geological studies.
Page | 2
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 7 : Project Optimization: Presents the optimization studies together with cost
estimation and economic analysis.
Chapter – 8 : Project Description and Design: Describes the detailed features of the
proposed project setting, design criteria and details of all project
components.
Chapter – 9 : Power and Energy: Summarizes the computation of project outputs and the
assessment of power and energy benefits.
References
Page | 3
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 2
Page | 4
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The proposed canal alignment passes through forest and pasture land. There is no unstable area
found in the alignment.
2.3 ACCESSIBILITY
At present there is earthen road access to the project area. The road distance from Pokhara to the
area is about 30km. From Pokhara at about 15 km long fair weather road suitable leads up to the
proposed powerhouse site. The site is difficult to access in the rainy season due to the high
discharge of river.
So, for the convenient access of goods and materials to the proposed site a bridge need to be
constructed for the effective and efficient run of the hydropower project.
Page | 5
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 3
LITERATURE REVIEW
3.1 BACKGROUND
Besides, during the time of deficit power up to 50MW is imported from India as per the Indo-
Nepal Power Exchange Agreement. Nepal and India have agreed in principle to increase this
level of exchange from the existing 50 MW to 150MW. Nepal is also entitled to receive 70
million units of energy annually from Tanakpur in the far-west under the Mahakali Treaty and
10MW power according to Koshi Contract.
Power is also exported to India through some sections of the INPS according to the exchange
agreement. Although the present integrated grid has a total of about 550MW installed capacity
without considering capacity of thermal plants and that available through Mahakali Treaty and
Koshi Contract, only about 425MW can be generated from hydropower stations during the
winter season when the power demand is at its peak.
In areas of transmission and sub-transmission of electricity, the INPS has grown to a network
of more than 1800 km of 132kV, more than500 km of 66kV, and around 2500 km of 33 power
lines. In order to accelerate the pace of expansion and conduct management of rural distribution
systems in a sustainable manner, NEA has adopted a concept of community participation in
rural electrification schemes.
Page | 6
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Load Forecast
Fiscal Year Total Generation System Peak Load Peak Load Growth (%)
Requirement (GWh)
2005-06 2774 603.28
2006-07 2897.1 642.2 6.5
2008-09 3428.1 759.9 9.3
2009-10 3698.4 819.8 7.9
2010-11 4057.1 890.6 8.6
2011-12 4423.3 971 9
2012-13 4815 1057 8.9
2013-14 5231.2 1148.4 8.6
2014-15 5673.8 1245.6 8.5
2015-16 6144.7 1336.1 7.3
2016-17 6645.9 1445.1 8.2
2017-18 7179.6 1561.1 8
2018-19 7719.4 1678.5 7.5
2019-20 8296.7 1804 7.5
Average Growth 8.14
(Source: NEA, 2003/4)
Page | 7
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
wastes (9.6%). Commercial energy sources share 10.5% having rest to other non-conventional
sources. Electricity contributes about 1.8% of the total energy needs. (Source: WECS, 2006)
Page | 10
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
operation, and structures at the site. Ogee Spillway is an improvement upon the free overfall
spillway and is widely used with concrete, masonry, arch and buttress dams. Ogee spillway
works effectively only on one particular head called designed head.
Page | 11
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The spillway has been designed as modern concrete weir with sloping downstream glacis
(sharp crested weir). Weirs of this type are of recent origin and their design is based on modern
concepts of sub surface flow (i.e. Khosla’s Theory).The hydraulic jump is formed on the
downstream sloping so as to dissipate the energy of the flowing water.
The provisions of the sheet piles, cutoff walls, impermeable concrete floor and protection
works including launching apron have been designed considering various factors as presented
in the detailed design of the weir structure. The parameters under considerations are;
Hydraulic jump characteristics
Length and the height of formation of jump
Seepage pressure
Erosion characteristics
3.2.1.6 Forces acting on weir
The main forces acting on the weir when it will be in operation are: Water pressure, Uplift
pressure, Silt pressure and Weight of the weir.
Water pressure
It is the major external force acting on the weir. This is called hydrostatic pressure force and
acts perpendicular on the surface of the weir and its magnitude is given by;
P= 0.5*ꭚ*H2*b
Uplift pressure
Water seeping through the pores, cracks and fissures of the foundation material, seeping
through the weir body itself and seepage from the bottom joint between the weir and its
foundation exerts an uplift pressure on the base of the weir. The uplift pressure virtually reduces
the downward weight of the weir, hence acts against the dam stability. The analysis of seepage
is done using Khosla’s Theory. Khosla’s Theory is the mathematical solution of the Laplacian
equation and it is easy, accurate method for seepage analysis.
Silt pressure
The silt gets deposited on the upstream of the weir and exerts horizontal and vertical pressure
as exerted by water. So, flushing of the silt should be done regularly to reduce its effect of
destabilizing the weir. It is done by the use of undersluice gate. The silt pressure is given by
the relation:
Psilt =0.5*ꝩsub*H2*Ka
Where,
ꝩsub =Submerged unit weight of silt
H=Depth of silt deposited
Ka =Coefficient of active earth pressure
The silt pressure force also acts at a height of H/3 from the base.
Weight of weir
Page | 12
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The weight of weir and its foundation is the major stabilizing /resisting force. While calculating
the weight, the cross section is splitted into rectangle and triangle. The weight of each along
with their C.G. is determined. The resultant of all these forces will represent the total weight
of dam acting at the C.G. of dam. Simply, when the sectional area of each part is multiplied by
unit weight of concrete, weight of that part is obtained. The weight of individual parts/sections
are summed up and final weight is calculated by knowing its section and multiplying its unit
weight.
Compression or crushing
While designing the weir section it should be so designed that the resultant passes through
middle 3rd part of the section to avoid possible tension on the weir section. The section should
be totally in compression. So, weir should be checked against failure by crushing of its material.
If the actual compressive stress exceeds the allowable stress, the dam material may get crushed.
Sliding
Sliding will occur when the net horizontal force above any plane in the weir or at the base of
the weir exceeds the frictional resistance developed at that level. Factor of safety against the
sliding is measured as shear stability factor (SSF) and is given by
Where, μ=Coefficient of friction
q =Average shear strength of the joint
For safety against sliding, SSF should be between 3 and 5. To increase the value of SSF,
attempts are always made to increase the magnitude of q, which is achieved by providing a
stepped foundation, ensuring better bond between the dam base and the rock foundation.
Page | 13
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
head loss. Suitable factor of safety should be employed to design height of intake sill so as to
ensure sufficient withdrawal capacity in the future.
3.2.4.1. General
Suspended particle that is not settled in the gravel trap is trapped in the settling basin. The
basic principle behind settling is that the greater the basin surface area and the lower the
velocity, the smaller the particles that can settle. The geometry of settling basin must be such
as to cause minimum turbulence, which might impair efficiency. To ensure uniform flow,
transitions are provided at inlet and outlet. Selection of width and length also depends upon
land available. For more reliable operation, more than one chamber is employed to make whole
system running even if one of the chambers has to be stopped for maintenance.
Page | 15
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Flushing of deposited matters is essential for smooth operation of settling basin. The lateral
and longitudinal slope may be provided for this purpose. For control of flow in and from
settling tank, gates can be used. Generally periodic flushing system is adopted for settling basin
since the sediment load is not as high as in gravel trap.
The slope is limited by non-settling criteria. Tractive shear approach is always used to ensure
sufficient shear stress to cause scouring of particles transported by it.
3.2.6. Forebay
3.2.6.1. General
A forebay is a type of hydraulic structure connecting the non-pressure canal with pressurized
flow system, i.e. flow through penstock. It is a storage basin which is constructed at the end of
the head race canal during peak power demand period. It serves the following functions:
Regulates the flow into the penstock, particularly the excess water into a spillway
Releases the surge pressure as the wave travels out of the penstock pipe
Serves as secondary or final settling basin and traps some particles that enter the
head race downstream of settling basin
3.2.6.2. Design Consideartion
The design of forebay is similar to that of settling basin, in general, except that exit portion is
replaced by a trash rack and penstock entrance area. The entrance to the penstock should fully
submerge in its position. The different parts of inlet chamber are: Entrance bay or basin,
Spillway, Flushing sluice, Screens, Valve chamber, and Conduit or penstock gate.
Forebay is designed such that 15secs to 3 mina of the design can be safely stored in the storage
above the minimum pipe submergence level. The limiting velocity in the inlet chamber should
be adopted in between 0.2m/s to 0.8m/sec and the submergence depth (S) should be greater
than 0.7D .where D= Diameter of penstock. Then,
total depth of tank=free board + S + D +Settling zone.
Where, S= Submergence head and settling zone>0.3D
The volume of the inlet chamber is calculated by quantifying the volume of water stored within
the plant startup time such that the depth of the inlet chamber should be enough to dissipate the
overflow during upsurge and drawdown. And effective volume of the inlet chamber, V=Q*t ,
where t=Retention time (15 sec to 3 minutes)
And, the length of the tank can be calculated as:
Qspillway= Cw*Lspillway*Hovertop1.5
Where,
Lspillway= length of the spillway,
Hovertop= Head over the spillway,
Cw= Coefficient of discharge
3.2.6.3. Protection works
The forebay is located at a flat area nearby riverside. Fencing is done around the inlet chamber
so that no one can enter the area. The excess eater from the inlet chamber is allowed to spill
from the spillway structure constructed on it. This water is safely discharged to the river using
open channel constructed for the purpose. Gates are used at inlet and outlet for its safe
operation.
Page | 17
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
3.2.7. Penstock
3.2.7.1. General
The potential energy of the flow at the inlet chamber is converted into the kinetic energy at the
turbine of a hydropower plant via penstock.
I t has to bear a very high pressure caused due to water hammer effect at the sudden closure of
the gate by governing mechanism of the turbine. Penstock should be smooth enough so as to
result minimum head loss while flowing water and it should be corrosion resistance from
durability aspect. The thickness should be sufficient enough to resist hop stress developed by
water hammer pressure and normal pressure should not exceed the allowable stress. Penstock
alignment must be straight to avoid head loss at the bents and the extra cost of the anchor block
unless it is mandatory by site condition.
The penstock may be either embedded or exposed as per topography, location of inlet
chamber/Surge tank, Power house and construction easiness etc. The penstock alignment
should start where the ground profile gets steeper. An ideal ground slope would be between
1:1 and 1:2 (V: H).
So, a smaller size penstock saves cost of construction material, but in doing so, the loss of
energy due to loss of head takes place and vice versa. Due to this fact, we need to deduce
optimum diameter which has minimum cost and minimum loss of energy. Water hammer
pressure in excess of normal water pressure can be expressed in equivalent water column height
as,
1
C=√ 1 𝐷
𝜌( + )
𝐾 𝐸𝑒
If the penstock has to feed more than one turbine, various factors govern whether use
independent pipes in number equal to the no. of the turbine or use one pipe and bifurcate it at
turbine inlet. Length from inlet chamber to powerhouse, construction feasibility, reliability,
transportation and fabrication are some important factors to be considered for this.
3.2.7.3. Optimization
Penstock is one of the costly and important structures in hydropower plant. The larger size
incurs more cost of the structure and a smaller size saves the cost of structure but is associated
with increased head loss) which ultimately leads to power loss). So, there is always an optimum
size of penstock for which the total cost of loss and the material is minimum. To seek this size,
optimization technique is used. Increase in size tends to increase the thickness, as thickness is
directly proportional to diameter but this relation is no more valid as the water hammer pressure
decreases with increase in size. The optimization is carried out considering these aspects.
Page | 18
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
3. 2.9. Powerhouse
3.2.9.1. General
Power house accommodates electro-mechanical equipments such as the turbine, generator,
switch gear, control room, engineer’s room, reception room and operator’s accommodation.
The main function of this is to protect the electro-mechanical equipments form the adverse
weather as well as possible mishandling by unauthorized persons. The powerhouse should have
adequate space such that all equipment can fit in and be accessed without difficulty.
Basically, there are two types of powerhouse: surface and underground powerhouse. Surface
powerhouse is cost effective and is best suited when the power house is far away from flood
plain. On the other hand, underground powerhouse is located inside the rock mass which makes
it more stable against flood effects and other external forces. Due to underground construction
and high technological methods, underground powerhouse is slightly costlier than surface ones.
Some powerhouse are located as semi-underground structures being partly on surface and
partly underground.
3.2.10. Tailrace
3.2.10.1. General
Tailrace is the channel into which water is discharged after passing through turbine. If the
powerhouse is close to river, the outflow may be discharged into the river. But, when the river
Page | 19
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
is far from the powerhouse, one may have to construct a channel or pipe according to
topography of the site between the powerhouse and the river. The tailrace should be designed
and maintained properly so that excessive aggravation is avoided.
3.2.11.2. Turbine
General
Hydraulic turbines are machines which convert hydraulic energy into mechanical energy. The
mechanical energy developed by turbine is used in running an electric generator which is
directly coupled to the shaft of the turbine which in turn converts mechanical energy into
electrical energy. Based on the energy conversion, turbines are classified as impulsive or Active
and Reactive turbines.
Impulsive Turbines
The turbine in which pressure head or potential energy of water is converted into the
kinetic energy of water in the form of jet of water issuing from one or more nozzles and
hitting a series of buckets mounted on the periphery of the wheel, at atmospheric
pressure is called impulsive turbine. It is used for high head and low discharge .Pelton
and Turbo are the examples of the impulsive turbine.
Reactive Turbines
The turbine, in which both kinetic energy and potential energy of water is utilized to
rotate the runner or the turbine is called the reactive turbine. The water flows through
the runner under kinetic and potential energy. The turbine runner is submerged and
water enters all around periphery of the runner. Water is taken up to the tail race by
means of a closed draft tube and thus whole passage of water is totally enclosed.
Francis, Kaplan, Propeller, Deriaz turbines are the examples.
Design philosophy
Selection of suitable type of turbine for the project depends upon several factors like head,
discharge, power production, load condition and corresponding efficiency, quality of water,
tail water level, size, construction feasibility etc. Selection of turbine is essential for the layout
of powerhouse, approaching and discharging pipes, conditions of construction and exploitation
and techno-economic parameters.
Turbine is selected from the following basic criteria:
Page | 20
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Specific Speed:
10 to 50-Pelton Turbine
80 to 400- Francis Turbine
300 to 500- Kaplan Turbine (Diagonal)
450 to 1200-Kaplan (Axial)
For Lower Mardi Hydropower project, Francis turbine is selected.
3.2.11.3. Generator
Generator is a 3-phase synchronous machine having the speed range of 70 to 1000 rpm. It may
have either vertical shaft alignment or horizontal shaft alignment. The vertical shaft alignment
is usually preferred for medium and large installation. The stator of generator is manufactured
in a number of segments which are then joined at the site. The entire stator assembly i.e.
embedded firmly in concrete foundation. The generator voltage depends upon the electrical
design (which is bounded by the scope) but the normal range is between 6 to 18 KV.
3.2.11.4. Exciters
The poles of the rotor have to be fed with field current, which is achieved through excitation
system. This is known as static excitation scheme. The generator burs bars feed current to a
step-down transformers to bring down its voltage 230V which is converted into dc with the
help of thyristors converters. The main requirement of the exciters is the reliability with a
steady and stable excitation current. The whole excitation system is made automatic to achieve
quick and accurate control.
3.2.11.6. Transformer
The generator voltage (6.6 to 11KV) has to be step up to the transmission voltage level (33KV)
to minimize loss. This is achieved by the use of step up transformer. The transformer are oil
filled for insulation purpose as well as for cooling purposes. Transformer problems need a close
scrutiny. It is also a great fire susceptible in view of the substantial quantity of oil in such a
close proximity to power cables. An especially designed firefighting equipment is always
included at the transformer site.
The location of the transformer can be either indoors or outdoors. For surface power stations,
outdoor locations are common. The outdoor location may prove to be more economical and
less hazardous; hence the outdoor location is preferred. The numbers of transformer may be as
Page | 21
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
many as the generating units. Each transformer is sufficiently isolated from other so as to
contain the fire in case of accidents. Besides the main transformer, there should be auxiliary
transformer (step down) for power house lighting and other use
Most of the parameters mentioned above are beyond the scope of this project work. The cost
and performance of the line depend to a great extent on the line voltage.
Page | 23
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 4
There were different site visits and exploration works with involvement of all group members for
the purpose of planning different components, scheme optimization including the identification
of alternatives for power evacuation and inter-connection possibilities.
4.1.2 Surveying
Reconnaissance Survey
After finalizing the desk study, our group was mobilized for field visit. After finalizing the project
site and before the detailed survey work, a brief reconnaissance survey was carried out with
flagging at necessary points around the entire project area to be mapped. The next step of the
survey was to fix the control points around the project area to establish control traverse. The
reference of the control points was taken using hand GPS in order to integrate with global
coordinates.
The elevations and the coordinates of each bench mark were tied up by the direct leveling with
the existing two permanent station points located near the headwork site were established. These
Page | 24
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
points referred as ST1 and BM1 are both situated at the proposed head-works site The elevation
and the coordinates of these stations are as follows:
The traverse survey was carried out using EDM. The coordinates of each control/traverse point
was worked out based on the surveyed distance, and angles and the coordinates of triangulation
stations and the azimuth measured by the total station. The elevation of each control point was
worked out by direct leveling.
4.1.3 Mapping
Data Processing
All the survey data were downloaded and computed after the completion of survey works.
Similarly, some field data were evaluated and horizontal distances and elevations were calculated.
All the coordinates and elevation of each station and survey point were computed with respect to
the given DTM coordinates and elevation of control points. After complete checking of the data’s,
mapping software was used for map preparation.
Page | 25
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
All the hydrological and meteorological variables studied are presented separately in the following
chapter.
The following hydrological and meteorological information has been collected so far for the
hydrological investigations required for the project.
Meteorological Data
There was no meteorological station found within the Mardi River catchment. In this case, the
meteorological analysis has been based on the data from neighboring meteorological station.
Hydrological Data
The DHM has not established any gauging station in the Mardi River basin. Hence there is no
information on the flow in the DHM database. Therefore, the regional approach for estimating
hydrological variables is used in the analysis. However, the variables derived from this approach
have been verified by field measurements and the necessary adjustments made accordingly.
Page | 26
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The transmission line survey was not carried out due to the availability of another transmission
line of Mardi River hydropower. So the produced electricity from our hydropower will be supplied
to Mardi River hydropower from which the electricity will be connected to national grid.
Page | 27
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 5
HYDROLOGY
The studies and investigations, presented in this chapter, provide hydrological information
required for the design and optimization of the major components of the project. The main
information required includes the firm flows and the extreme flows. Based on the Guidelines for
Study of Hydropower Projects (Run-of-River Type), the scope of hydrological and sediment
studies related to the Lower Mardi River Hydropower Project covers the following.
The following sections describe the nature of collected data, field activities, catchments
characteristics and the estimates of design values.
The basin lies in the upper part of the Kaski district (Figure 5.1). Elevation of the catchment ranges
from 1062 m to more than 5000 m. (Figure 5.2).
With pinnate pattern of drainage, the catchment area at the intake site covers 97.2 km2. The basin
characteristics of Lower Mardi River catchment at intake site are peresented in Table 5.1. The
characteristics were derived from 100 m resolition Digital Elevation Model (DEM).
The areas of the basin from 2400 m to 5000 m are covered by fairly dense mixed forest. The area
of basin lying above 3000m is 19.97 km2.
Page | 28
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Figure 5.1. Location of the basin and meteorological stations in the vicinity.
Page | 29
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Page | 30
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Table 5.1. Basin characteristics of Lower Mardi River catchment at intake site derived
from 100 m resolition DEM based on the topo map.
Total area (km2) 97.2
Length (km) 47.4
Area below 5000 m (km2) 97.2
Area below 3000 m (km2) 19.97
Jan. 4.799
Feb. 3.329
Mar. 2.444
Apr. 1.771
Page | 32
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
50
45
40
35
30
Discharge
25
20
15
10
0
0 20 40 60 80 100 120
% Exceedance of Discharge
From graph, flow duration curve, the 40% dependable flow is estimated to be 11 m3/s derived
from MIP method which will be adopted as the design discharge.
= 1.8767(77.23 + 1)0.8783
= 86.36 m3/s
Similarly, the prediction regression equation for a 100 year instantaneous flood peak is given by;
= 14.63(77.23 + 1)0.7342
= 359.21 m3/s
Flood of any other return period can be calculated using the following formula
Page | 33
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Qf = exp(lnQ2 + S*𝜎)
𝑄100
𝜎 = ln ( ) /2.3626
𝑄2
359.21
= ln ( ) /2.3626
86.36
= 0.6128
Q2 and Q100 are the 2 year and 100 year return period is instantaneous flood (m3/s). The result of
flood estimate for the headwork site from the regional frequency analysis are presented in table
5.5.
Using Dicken's method, the T year flood discharge Qt, in m3/s, shall be determined as
Qt = CT * A0.75
Where,
CT is modified Dicken's constant proposed by the Irrigation Research Institute, Roorkee, India,
based on frequency studies on Himalayan Rivers. This constant shall be computed as
CT = 2.342 log(0.6T)log(1185/p) + 4
𝑎+6
P = 100 *
𝐴+𝑎
Where,
19.97+ 6
P = 100 * = 22.164
97.2+19.97
The result of flood estimate for the headwork site Modified Dicken's formula are presented in
table 5.6.
In Nepalese context, Water and Energy Commission Secreteriat developed the emperical
relationships for analyzing flood of different frequencies (Dulal & Baral, 2012). So design flood
of 100 years return period is taken as 346.5996 m3/s estimated by Modified Dicken's method.
Page | 35
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 6
The Lower Mardi River Hydropower Project is a small sized water resources development scheme
located about 15 km northwest of Pokhara. The project lies on the Lower Mardi River, one of the
tributaries of the Seti River in the Seti-Gandaki River basin. Although it is a snow fed river it has
a moderate gradient, which makes it attractive for developing a hydropower project. The project
layout has been done in consideration of optimum utilization of nature in the form of head and
discharge.
Various potential layout alternatives for key components of the hydropower project with power
output of 1 to 7 MW were proposed, studied and analyzed based on desk study and field visit
assessment. Feasibility level planning, design and drawings were produced for the best option
having following key components.
Field visits for the verification of the above mentioned alternatives were carried out. Instrument
surveys were carried out to find out level differences (available gross head) between the intake
and the proposed locations of the powerhouse.
The outcomes of the studies were verified during the field visits carried out by the group members
in various fields and the most suitable was selected for the study. The outcomes of the desk
studies, verification from the site visit and short descriptions of each scheme are briefed below.
This scheme consists of a Tyrolean weir located 200 m downstream of the existing old suspension
bridge over the Lower Mardi River. All the waterway structures including the intake gallery, sand
trap, and forebay are located on the right bank of the Lower Mardi River. The scheme requires
approximately 200 m of penstock pipes including bifurcation pipes. The powerhouse in this
scheme is located at an elevation of 1066.15m on the right bank of Mardi River. The powerhouse
is safe from the high floods in the Mardi River. The switch yard is located on the left bank of
Mardi River on the opposite site of powerhouse building. A tailrace conduit of approximately 70
m length is proposed to discharge the water into the Mardi River after power generation.
Page | 37
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 7
Project costs and benefits have been estimated for the various plant capacities of the project. The
objective is to determine the element size which maximizes the discounted net benefits.
7.2 ASSUMPTIONS
Plant optimization study has been carried out for various plant capacities ranging from 2 MW to
6 MW with an interval of 1 MW based on recommended Project Layout. The optimization study
is conducted with the monthly and annual energy and their respective tariff for dry period and wet
period energy as the project evaluation criteria. Based on the rated discharge for each plant
capacity, sizing of various hydraulic structures and electromechanical units were determined.
The optimization of the plant-installed capacity is based on following assumptions:
Economic Parameters
Page | 38
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
determined and cost estimate prepared. Power benefits were determined for each plant capacity
and compared with the costs. The objective was to determine the plant size, which maximizes the
benefits of power supply and the discounted benefit / cost ratios and IRR.
The optimization procedure in this study follows the general approach outlined below:
Determine rated discharge for each designated plant capacities with assumed available head
of 27.9m.
Estimate the size of free flow spill way to pass the design flood of 1 in 100 years.
Determine the optimum sizing of the hydraulic Structures and electromechanical units.
Prepare preliminary design of intake, intake connecting channel, sand trap, flushing structures,
water conveyance component, forebay, penstock, powerhouse and the tail race for each
installed capacity. The following structures are envisaged in the project as main Civil
Components.
- Tyrolean Intake Weir and sand Trap
- Headrace Channel
- Forebay
- Surface Steel Penstock
- Surface Powerhouse
- Tailrace
Estimate the costs of the individual variable as well as fix structures and determine the total
project cost for each plant capacity.
Estimate the yearly operation and maintenance cost to be envisaged in 30 years of operation.
Conduct economic analysis for each plant capacity.
Layout of the individual structure conceived in the optimization study may vary and modified in
the feasibility design. However, the general layout and the main concept of the project will remain
the same.
The various economic indicators like the net present value, benefit cost ratio and the internal rate
of return were calculated for all of the installed capacities. The summary of the results of the
economic analysis for all different installed capacities are shown below.
US $ /
Power Revenues 0.060 Cost Fact : 1
kWh
O&M Cost 1.5 % Net Head : 27.9 m
Forced
Interest Rate 10 % 1
Outage :
Page | 39
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Increm.
Life Time 30 Years 0.5 m3/s
Discharge
Construc. Period 3 Years CRF 0.1061 -
Design Discharge m3/s 5.00 5.50 6.00 6.50 7.00 7.50 8.00 8.50
Mill US
Original Cost 4.05 4.21 4.30 4.41 4.52 4.61 4.79 4.87
$
Orig. Ann.
GWh 9.30 9.94 10.53 11.06 11.60 12.00 12.36 12.75
Energy
Installed Capacity MW 1.24 1.36 1.48 1.60 1.72 1.84 1.96 2.08
Energy Reduction GWh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.1
Ann. En.
GWh 9.3 9.9 10.5 11.0 11.6 12.0 12.3 12.7
(incl.Red.)
Accum. Factor - 1.10 1.10 1.10 1.10 1.10 1.10 1.10 1.10
Present Value Mill US
4.5 4.6 4.7 4.9 5.0 5.1 5.3 5.4
Cost $
Mill US
Annual Benefits 0.6 0.6 0.6 0.7 0.7 0.7 0.7 0.8
$
Annual O&M Mill US
0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Cost $
Mill US
Annual (B-O&M) 0.5 0.5 0.6 0.6 0.6 0.7 0.7 0.7
$
Present Value Mill US
4.7 5.0 5.4 5.6 5.9 6.1 6.3 6.5
Bene $
Mill US
NPV (B-C) 0.2 0.4 0.6 0.8 0.9 1.1 1.0 1.1
$
US $ /
Tarrif / kWh 0.057 0.056 0.054 0.053 0.051 0.051 0.051 0.050
kWh
US $ /
Cost / kW 3593 3406 3196 3030 2892 2761 2696 2590
kW
Page | 40
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
13.50
12.50
12.00
11.50
11.00
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
1
NPV ( B - C ) Mill US $
0
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
Page | 41
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 8
- The weir is designed for a flood discharge of 346.599 m3/s equivalent to 100 years flood
event. The intake structure and the waterway structures up to the sandtrap are designed
for a discharge of 11 m3/s including 30% of design discharge for flushing purpose.
- The waterway section between intake gate and side spillway is designed for a design
discharge of 11 m3/s. The hydraulic slope of this section is proposed at 0.005 to obtain the
velocity of water in the structure sufficient to transport sediment entered the intake.
- The sand trap is designed to settle particle size larger than 0.15 mm. It is a continuous
flushing type twin chambered sand trap with two flushing pipes having suitable gates for
the control of flushing discharge in each chamber.
- The water way structures after the sand trap is free flow headrace tunnel is designed with
a hydraulic slope of 0.0006
- The forebay is designed for a storage volume of 8192 m3, which is sufficient for the
operation of one unit for two minutes at the beginning of plant operation.
- The penstock pipes are designed for discharge of 11 m3/s, which is required to generate
2.61 MW of power.
- The tailrace conduit is designed to discharge 11 m3/s of water after power generation. It
will have a hydraulic slope of 0.0015
- The power house is designed in such a way that it will be safe from the flood in the Mardi
River even for magnitude of flood equivalent to 100 years flood.
- Horizontal shaft type turbines are proposed based on the diagram “Turbine Selection
Diagram: 10 MW Less”.
Page | 42
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
After the generation of 2.61 MW of power, the water from the powerhouse is discharged into the
Mardi River through a 70 m long tailrace conduit.
The components of the project are designed considering the functional requirement for safe,
economy and easiness on construction and operation of the plant.
The design discharge of the project is 11 m3/s. The following guidelines are used including the
contents on “Feasibility Study guidelines for Small Hydropower Project – 2003”.
- The structure should be able to withdraw, convey, and safely discharge the required flow
from the structure.
- Structures should not be vulnerable to floods hazards, i.e. free passage of flow should be
possible.
- Floating debris must not cause blockage at the intake and there should be spillway
arrangement when the power house is closed.
- All components must be hydraulically, geo-technically, and structurally stable and
economically viable.
- The plant should be able to run in isolated mode of operation for different sizes of load.
- The power from the project should be evacuated from line so that the outage is minimum
and cost is economic in long run.
The head loss is a major concern thus the hydraulic parameters were checked in for design of
water conveyance system to ensure a safe passage of design flow with minimum head loss.
The grade of concrete and quality for characteristics compressive strength are decided with the
following criteria based on general practice.
Although reinforcement design is not carried out for structures, but the quantity required per unit
volume of concrete is considered different for different type of structures based on past
experiences in similar nature of the project.
Page | 44
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The structural part of powerhouse and machine foundation is considered similar to plant having
same capacity.
Design Criteria
Following are the main criterion used in the design of tyrolean weir:
Description of Structures:
Tyrolean Weir:
The headworks of the project are a floating type structure founded on alluvium. It is designed for
100 years return period flood of magnitude 346.59 m3/s.
The weir is a tyrolean weir of 5.55 m height and 21.78 m clear crest length. A discharge of 346.599
m3/s overflows over it during 100years return period flood flow. The crest level of the structure is
at El. 1098.6 masl to maintain minimum operating level in front of intake. The crest level of weir
is 4.26 m above the upstream concrete apron. To reduce the uplift below the structures and keep
the exit gradient within the limit, a 1.50 m thick 8.0 m long upstream stone apron is provided.
Upstream and downstream concrete cut-offs of 3m depth are provided to increase the creep length
and protect the structure from undermining.
The stability analysis of the weir shows that the structure is safe against overturning, sliding,
bearing, uplift and undermining.
Page | 45
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Design Criteria:
The connecting channel is designed for discharge of 13.2 m3/s during normal flow. It is designed
for a velocity of 1.8 m/s at a channel slope of 1 in 1200. Rugosity coefficient of 0.015 is taken in
the design. The channel is provided with average freeboard of 0.5 m.
Description of Structure:
The discharge passing through the connecting channel and then through 179 m long sand trap
will be carried to forebay through 800m long trapezoidal concrete headrace channel. The
connecting channel from weir to sandtrap is a rectangular concrete open channel 1.86 m wide and
3.01m deep. It is designed for 0.0050 slope.
To ensure the equal distribution of design discharge into both chambers of the Sand trap, the canal
is divided into two equal sections. Transition length of 10 m is provided from the end of the intake
channel to the Sand trap to ensure tranquil flow conditions before the flow enters the Sand trap.
A vertical lift gate is provided on each channel of the Sand trap at the inlet and outlet of the canal.
These gates are to be used during the Sand trap flushing. The inlet gate can also be used to
maintain the design flows in the chambers.
The Sand trap shall remain in operation during the sediment removal process, i.e.
- The normal operation of the basins shall not be interrupted in order to facilitate flushing.
- The water supply to the head race tunnel shall be maintained fully during flushing as long
as the river flow can provide the additional 20% flow required for the flushing operation.
No significant amount of sediments deposited in the basins shall be mixed into and carried away
with the general basin flow during flushing.
The flushing process could be both either continuous or intermittent depending upon the loading
condition and availability of flow in the stream. In case intermittent supply the Sand trap flushing
system could be operated simultaneously as per their requirement.
Page | 46
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The headrace channel starts from the end of curved head race tunnel having invert level of 1090.96
m. The curve is designed as transition section of the headrace channel. The total length of
channel from inlet portal to forebay is 800 m. The clear width of the channel is 4.0 m and total
height.
The support shall be shotcrete and some concrete lining. The present level of study recommends
for 15% of the tunnel length to be concrete lined and remaining 85% to be shotcreted at required
sections.
The bedrock setting and type of formation is favourable for tunnel and is viable for small size
project.
Since the length of channel is only 800m in length, and the construction of tunnel is proposed to
start from both ends. Hence provision of audit tunnel is not considered in the design.
- The geology should be good, predictable and the loss variation in the underground
structure.
- The velocity and head loss should be in limit.
8.4.1.5 Forebay
The forebay acts as a sort of regulating pond to cushion the impact of sudden load rejection or
load acceptance. Forebay is provided between the free flow tunnel and the pressure flow penstock
where water hammering is expected because of the sudden interruption of the flow. Further it is
provided to function as the balancing reservoir in case of the sudden demand in the pressure
conduit.
The upsurge in the forebay is estimated for sudden closure. Total capacity of the forebay is fixed
as 2125m3 capacity so that the total live storage volume in it is equivalent to the total volume
required for three minutes of operation. Following are the basic data used for the design of the
forebay:
The inlet of penstock is placed at sufficient depth so that no air could enter into the penstock pipe.
RCC structures consisting of walls and columns are proposed for the underground portion of the
powerhouse. These structures are designed to with stand the load of the backfill materials and the
load to the overhead travelling crane including the vibration loads during the operation of the
power plant.
The superstructure of the powerhouse is to be constructed from RCC columns, walls, and block
masonry walls. A series of windows are provided for proper lighting and ventilation in the
powerhouse. One small access door and one large shutter door access are arranged in the
powerhouse.
The power station area is separated from other areas by a fence constructed around the power
station. The main entrance gate is provided on the access road. The level of access road in the
river side area which separates power station area from the river is higher than the river water
level.
(a) Inlet Valve Floor: In this floor, mainly the penstock pipe, inlet valves and draft tubes are
located. This floor accommodates the rooms for the powerhouse auxiliary systems such
as generator coaling system turbine cooling system, etc. The level of this floor is at EL
1066.15.
(b) Turbine – Generator Floor: The level of this floor is at EL 1066.27. In this floor, mainly
turbines, generators, governors and their accessories will be located.
(c) Erection Bay Floor: The erection bay is used for the maintenance of powerhouse
equipment. An overhead travelling crane and a large shutter opening is proposed in this
floor for easy transportation and loading / unloading.
All floors are accessible by a staircase for people and through hatch openings for the crane.
(d) Control Building: The control building is constructed above the penstock pipe level after
the installation of the penstock pipes. This building houses different accessories of the
powerhouse equipment, such as switchgear & diesel generator and battery charger.
(e) Drainage System: Peripheral drains around the powerhouse are provided to trap all
rainwater. Drains are arranged around the powerhouse and at the toe of excavation slope
drainage is constructed of stone masonry in 1:4 cement sand mortar. The drain discharges
water to the Mardi River.
Page | 48
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
(f) Water Supply: It is proposed to use the water tapped from the penstock pipes after proper
treatment. Hence a treatment has to be located in the power house. The treatment plant is
to have pumps installed to pump up water to the necessary areas and taps.
(g) Sewage System: A septic tank will be provided with the provision of a soak pit in the
powerhouse area to manage the sewage.
8.4.2.2 Tailrace
The tailrace is designed with a hydraulic slope of 0.0015. It has a trapezoidal box culvert section
3.60 m. wide and 1.50 m high. The free board adopted is 0.30 m. The outlet portion of the tailrace
is sloped towards the river. The length of conduit is 70 m.
bar and one line bay for outgoing transmission line. The features of major electromechanical
equipment in the plant will be as below.
In case of sudden full load rejection, the spherical valve is capable of emergency closure of the
turbine against full discharge.
8.6.2.2 Turbines
With the available head, design discharge, reliability and considering the cost, two units are
appropriate for the project.
P = g.n.Q.H
H = Net head
Adopt rating of turbine 2000 kW to cater small overload capacity during the availability of water.
The selection of turbine type primarily depends on net head and the discharge available at the site.
The type of turbine determines also the layout of powerhouse. The normal power generation
against time is considered as criteria in unit selection. The design flow is 11 m3/s, where as
minimum flow identified is only 11 m3/sec, so a turbine unit size operable even during the dry
season is reckoned. Specially the site condition dictates installation of only 2 units of turbine each
requiring 5.50 m3/s discharge. For the head of 27.88 m and the discharge of 5.50 m3/s Francis
turbines with horizontal shaft and associated enclosure are found most appropriate. The turbine
shall be capable to run in an additional 10% continuous overload capacity during the availability
of the water. The turbine shall be able to operate safely and satisfactorily under any conditions of
load and water quantity without appreciable vibration, excessive noise or under wear and tear.
The horizontal shaft layout is preferred for this project from the ease of shaft alignment task. The
shaft of turbine will be coupled through fly wheel supported by pedestal bearings to the alternator
shaft. The pelton turbine will be of two nozzles type and these nozzles will be actuated by oil
pressure and closed by high quality stainless steel spring. The water jet in the turbine will be
deflected by a cut in type defector, which will act very fast. The turbine will be equipped with
turbine housing which will guide the pressure released water from the runner to the tailrace safety.
The turbine will be stopped with the help of brake nozzle provided at the turbine housing.
All turbine instrumentation, such as unit control boards, and governor control cabinets will be
located close to the relevant units on the turbine floor. This is advantages for commissioning,
service and maintenance.
Runner
The turbine will be a single runner attached directly to the flange at the end of the turbine shaft.
The runner will be of integrally solid casting steel of minimum 13% Cr or and 6% NC. The runner
will be designed to safely with stand the stresses due to operation at runway speed and under the
most severe conditions.
The hydraulic surfaces of buckets will be carefully grounded and finished smoothly.
Page | 51
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Bolted connection will be provided for attaching the runner to the turbine shaft. The bolts will be
locked in position to prevent loosening during operation.
Shaft
The turbine shaft will be made of forged steel with properly heat treated. It will be designed to
operate safely in combination with the generator shaft.
The shaft will have an integrally forged flanged half coupling on its Generator side for connection
with a coupling flange on the generator shaft. The runner side shaft flange will be provided with
necessary arrangement for attachment of the runner removal device.
Guide Bearing
The turbine will be equipped with a self lubricating oil type guide bearing. The bearing will
consist of housing and a removable bearing shell. The guide bearing will be of self lubricated and
water coaled and complete with oil reservoir and water coaling coil.
Jet Deflector
In order to prevent excessive pressure rise in the penstock and to ensure quick response and power
speed regulation of the unit, each nozzle will be equipped with a jet deflector. This will be actuated
by an oil servometer. The deflector will be of the cut in type and will be made of steel with
stainless steel overlay cutting edge including the hydraulic passage. It will be designed to safely
will stand the maximum discharge from the nozzle.
Brake Nozzle
Each runner will be equipped with a brake nozzle arranged to direct a stream of water against the
backs of the buckets to restrain the rotating part of the turbine and generator after the unit will be
taken off the end.
Turbine Housing
The suitable steel plate turbine housing will be provided for each turbine. The top cover will be
flange connected to the housing to facilitate inspection and dismantling of the runner.
Distributor
The distributor including nozzle body extension will be provided with stiffness and anchorages
sufficient to ensure that no deformation will take place during erection. The distributor will be
rigidly connected to the inlet valve by means of flange.
Governors
Governors are provided for the control of the turbines in case of load variations. The electronic
governors in combination with the hydraulic system acts on the turbine guide vanes for regulating
the turbine flow. The governor should have the following features:
Page | 52
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Each electronic governor has its own hydraulic system. The hydraulic system consists of a sump
tank, accumulator pressure tank and dual lead pump for storage. For maintaining oil pressure in
the system, a jockey pump is supplied. Major parts of the oil pressure system are: essential
controls and piping connections to the governor relay valve and servometers of the turbine guide
vane. The governor regulation data will be as follows:
The oil pressure unit for the governor system with sufficient capacity to drive the governor and
actuate the oil pressure system will be suitably selected. The governor will be located on the
turbine floor near to the turbine.
Flywheel
The alternator rotor shall be designed with a flywheel to obtain satisfactory speed regulation for
coupling with the hydraulic turbine. The selection of flywheel depends however on the design
and manufacturer, to obtain desired objective.
Cooling water shall be used for cooling the alternator and the bearings. The supplied water shall
be taken from penstock and passed through a pressure reducing valve for collection in the cooling
head tank that shall be installed at a suitable location upstream of the powerhouse. The cooling
water through a common header pipe will branch out to individual generating units, which shall
be discharged to the tailrace after circulation in the system. The cooling water system will have
two sets of strainers, one on duty and the other as standby. The cooling system provide necessary
amount of cooling water mainly for the following equipment:
When dewatering of unit is required the gate valve will be opened and water will be collected in
the drainage sump tank. The drainage sump pump will be used for discharging the water in the
tailrace.
Two compressors will feed the both systems. Under normal operating conditions, one compressor
will act as duty and the other as standby.
The system described above hold good in many plants. However, the recent development for
replacing compressed air system is by using nitrogen fettled bladder type accumulator. The
advantage of N2 type accumulator over the compressed air system area: it takes less space silent
in operation and more reliable.
Storage tanks, oil purifier and transfer pumps shall be installed in a special room arranged at the
turbine floor. Separate piping set ups, tanks and transfer pumps shall be provided for supply and
return lines in order to avoid mixing of non-purified oil. Sufficient storage capacity will be
provided for the supply of oil volume equal to the entire hydraulic oil volume of one power unit.
Mechanical Workshop
A mechanical workshop will be equipped with machine tools and devices appropriate for the
maintenance and repair of all mechanical components and machining of the smaller components
of the mechanical electrical equipment and hydraulic steel structures. A diesel generating set
installed as a backup power for construction will be used as a standby for emergency operation.
The surface powerhouse ventilation system consists of a fresh air handling unit and an air
conditioning unit. The fresh air handling unit will be installed inside the ventilation room and will
consists of air filters and three air admission fans, two on duty and one standby. The unit will
such air from outside and distribute it via appropriate ducting to different locations of generator
floor, turbine floor or other places as control room.
The crane travels on two rails, fixed on the two beams along the machine hall of the powerhouse.
The span of the crane is sufficient for moving big machinery parts in various directions along the
machine hall of the power house up to the erection bay. The principal characteristics of the
overhead crane:
8.6.3.2 Gates
The main characteristics of the gates that will be provided at different structural components of
the project will be as follows:
Intake gate
One set of vertical wheel gate with the dimension of 1.3 m height and 1.3 m width will be installed
at the intake for flow regulation in the headrace canal.
Page | 55
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
One set of vertical slide type gate will be provided at the end point of forebay as the intake gate
to penstock.
Tailrace Gate
At the outlet structure of the tailrace a fixed wheel vertical gate will be provided for repair and for
preventing the high flood of Mardi River entering into the powerhouse. The dimension of the gate
is 2.60 m high 1.30 m wide and is designed for a water head of 5 m.
The gates will consist of steel plate, beams, guide frame, seals, hoist, and appurtenant parts
complete with all accessories.
The stop long leaf will consists of skin plate, horizontal girders, vertical stiffeners, their bracing
angles, guide rollers, three way rubber seals, lifting attachments and other necessary components.
The stop logs will be made of structural steel and of all welded construction.
The unit rating of the powerhouse equipment has been selected based on the following
considerations:
The generator will be totally enclosed, air cooled (TEWAC) with air to water heat exchangers
located in the generator hall generator fire protection will be provided by a CO2 deluge system.
The generator will be equipped with a set of combined pneumatic hydraulic operated brakes and
jacks.
The overall inertia constant of the turbine / generator units will be checked in final stage. Due to
transport limitations, both the generator status and rotor will need to be delivered to site in sections
and assembled within the powerhouse. For assembly during construction and to enable
Page | 56
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
disassembly for maintenance, the station crane capacity will have to be suitable for lifting the
complete rotor. It is estimated that the generator rotor will weigh approximately 20 tons. The
main hoist will haul 25 ton capacity and auxiliary hoist will have 5 ton capacity.
The preliminary parameters of the generators are summarized in the following table:
Parameters Value
Number of units : 2
Rating : 1.5 MW horizontal shaft
Power factor : 0.87
Cooling : TEWAC (Totally Enclosed Water Air Cooling)
Synchronous speed : 300 rpm
Number of poles : 20
Frequency : 50 Hz
Rated voltage : 11 kV
Neutral grounding : Resistive grounding via grounding transformer
a. The voltage control under steady state condition shall +/-5% of rated terminal voltage.
b. The automatic voltage regulator shall suppress to residual voltage through the field
discharge.
Power Transformers
The generators shall be directly connected to the step up transformer through circuit breaker and
power cables one set of transformer is proposed. The transformer should be manufactured
according to IEC76 and shall be an outdoor type.
The transformer steps up the voltage from 11 kV to 33 kV. The generation voltage of the voltage
of the project is 11 kV which is stepped up to the help of transformer to match with the
interconnection substation. The transformer will be installed in the switch yard. Three phase
transformer will be selected assuming easy transportation system. Surge arrestors are provided in
the line side to protect over voltage caused by lighting and switching surges.
Page | 57
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Generator Protection
Generator shall be protected with the following schemes:
Differential protection
Field protection
Reverse power protection
Over voltage and over current protection
Ground and current protection and earth fault protection
Out of synchronization protection
Transformer Protection
The power transformer will be protected with the following schemes:
Differential protection
Over current and earth fault protection
Other protection requirements regarding gas operated relays and oil and winding
temperature protection will be implemented as per Best Industry Practice.
For the power transformer, Buchhalz protection and temperature trip circuits are provided.
To protect 33 kV transmission line and transformer from high voltage surges, lightning arrestor
shall be provided.
Control Systems
A control room for the powerhouse, the HV switchgear and to associated works will be located
within the powerhouse. The remote indication of the intake and Sand trap gates at the headworks
will also be in the powerhouse control room. It will be possible to control the units and the
auxiliary system form this control room. The control system will provide the following control
modes:
Page | 58
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 9
This section summarizes the power and energy production from the project. It is assumed that all
the energy generated from the power plant is evacuated and marketed to the integrated Nepal
Power System (INPS).
9.1 GENERAL
Power and energy production capabilities of the project have been calculated using the formulas:
P = 9.81*Q*H*Eff (KW)
E = P*h (KWh)
Francis turbine has been proposed to be used in the project. Since the turbine is set clear above
tail water, the gross head is the difference between headwater and the turbine axis. There is a loss
in conveyance system while conveying the design discharge to the powerhouse. This loss has to
be deducted from the gross head in order to obtain the net head, which is the effective head in
calculating the power and energy from a plant. The loss in the conveying system is dependent in
the velocity of flow, which in turn is related with the discharge available. The mean monthly flow
is different in different months, so the loss will also be different each month. The combined
efficiency is the product of efficiency of generator, transformer and the turbine. The efficiency of
turbine is a function of discharge available at the turbine. The efficiency of the Francis turbine has
been adopted in the range of 87%. As the discharge decreases, the efficiency decreases gradually.
The water from fore-bay to powerhouse is taken through steel penstock where the total losses
calculated are 2.12 m. Gross head is 30 m. There are two horizontal axis in Francis turbines in the
powerhouse. The discharge in each of the turbines is distributed in such a manner that both the
turbines tend to run at their maximum efficiency thus generating maximum possible energy.
The energy computation is carried out on the basis that the river has a discharge of 11.0 m 3/s
equivalent to the 40% excedance event. The net head available for power generation is 27.88 m.
As to option of two units of generating machines is observed to be optimum, the energy
computation is based on the two units of generation machines having an installed capacity of 1.4
MW each. The turbine efficiency is adopted equivalent to 92%. The generator efficiency is
assumed to be 96.3%, and the transformer efficiency is taken is 98% making the overall coefficient
of efficiency equivalent to 87% which is very practical for small capacity power plants. A
compensation discharge equivalent to 10% of the minimum flow in the river is released as
downstream requirement for the conservation of the downstream ecosystem.
Page | 59
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Jan. Feb. Mar. April May June July Aug. Sept. Oct. Nov. Dec.
1.37 1.22 1.19 0.98 1.12 4.45 8.72 12.95 8.21 4.40 2.38 1.68
Hydraulic efficiency: This is calculated from the headless in project components like loss at
entrance, friction loss in conveyances, bend loss, exit loss and loss at reduces etc.
Turbine efficiency: Rated turbine efficiency has been taken as 92% for francis turbine.
Generator efficiency: Generator has iron and copper losses which makes power output lower than
available from mechanical input. The rated efficiency of generator of 96.3% is recommended for
the project.
Transformer efficiency: The rated efficiency of transformer of 98% is recommended for the
project.
The following table gives the results of Power and Energy computations.
Page | 60
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Dry season
Average Design Generation Wet season
Months Days Net head energy
flow Flow capacity energy kwhr
kwhr
May 3.33 31 3.33 27.88 792.364 589518.816
June 5.86 30 5.86 27.88 1394.372 1003947.84
July 23.98 31 11 27.88 2617.422 1947361.968
Aug 44.25 31 11 27.88 2617.422 1947361.968
Sep 35.41 30 11 27.88 2617.422 1884543.84
Oct 18.44 31 11 27.88 2617.422 1947361.968
Nov 8.85 30 8.85 27.88 2105.835 1516201.20
Dec 6.64 31 6.64 27.88 1579.971 1175498.424
Jan 4.80 31 4.80 27.88 1142.147 849757.368
Feb 3.33 29 3.33 27.88 792.364 551485.344
Mar 2.44 31 2.44 27.88 580.592 431960.448
Apr 1.77 30 1.77 27.88 421.167 303240.24
Maximum power generation(kw) 19278.5
Total seasonal energy(kwh) 3008701 11139537.84
Annual Generation(Gwh) 3.008 11.13
Total Generation(Gwh) 14.13
Revenue from dry season energy Rs.8.4/kwh 25273093.31
Revenue from wet season energy Rs.4.8/kwh 53469781.63
Total Revenue in NRs 78742874.94
Data:
Project cost: Rs 574780000
Operation and maintenance cost (1.5% of total): Rs 8621700
Economic Life: 30 years
Interest rate: 10%
Revenue: Rs 78742874.94
B/C Ratio:
CR =I(A/P,I=10%,N=30)
=Rs 60972230.31
𝐵𝑒𝑛𝑒𝑓𝑖𝑡
B/C =
𝐶𝑅+𝑂&𝑀 𝑐𝑜𝑠𝑡
=1.13>1
NPV=-574780000+78772874.94(P/A,i%,30)
For IRR:
Taking, i=13%
NPV = Rs 15674170.97
Taking i=14%
NPV = -Rs 23160015.64
Thus,IRR =13.4% >10% (OK)
Page | 61
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Payback Period:
Table 9.2: Calculation of Payback Period:
Years Net Cash Flow Cumulative Cash Flow
0 -574780000 -574780000
1 70151175 -504628825
2 70151175 -434477650
3 70151175 -364326475
4 70151175 -294175300
5 70151175 -224024125
6 70151175 -153872950
7 70151175 -83721775
8 70151175 -13570600
9 70151175 56580575
𝐴𝑚𝑜𝑢𝑛𝑡 𝑡𝑜 𝑟𝑒𝑡𝑢𝑟𝑛
Payback Period=𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑦𝑒𝑎𝑟 +
𝑁𝑒𝑥𝑡 𝑦𝑒𝑎𝑟 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤
= 8.24 years
Page | 62
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 10
CONSTRUCTION PLANNING
10.1 GENERAL
The Lower Mardi river Hydropower Project is a major constructed project in Kaski District of
Gandaki zone. One of the most important activities related to project construction apart from the
main construction work is the construction of the access road to the powerhouse site.
The construction of the project consists of different activities such as the construction of the access
road including bridge, river diversion works for the construction of the diversion weir and intake,
headrace channel, forebay and penstock pipes. The construction of the powerhouse, tailrace and
switchyard are of so some other important activities of the project. The construction also consists
of the installation of electromechanical equipment comprising of turbines, generators and
accessories like governors, exciters, auxiliary equipment and 33 kV transmission line. In addition,
hydro-mechanical components such as gates, valves, hoisting devices, penstock pipes etc, with
also are installed.
A comprehensive study has been carried out to analyze the project tasks. On the basis of the study
results, a feasibility level construction schedule and the cost estimate of the project has been
prepared. The construction schedule has identified the time period and interrelationship of all the
pre-construction activities and the construction activities.
The project area is connected by Hemja-Lhachok rural road. The project headworks site is located
about 15 km away from Pokhara. The access road and bridge required for access to the different
sites are proposed to be constructed before the award of the contract for the main civil works to
curtail the construction period of the project. About 6 months will be required to construct this
road.
Page | 63
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Areas required for the construction facilities consist of spaces required for permanent camps for
construction management staff, temporary camps for contractor’s staff and labour, construction
materials processing and stock piling, workshop, equipment storage, medical facilities etc.
10.3.2 Communication
Communication to and from the project site may be carried out through VHF sets. Currently a
telephone network exists at very nearby the site. Ribhan has a telephone communication system
connected to Nepal Telecommunication Corporation (NTC). Once the project is commissioned,
Power Line Cable Communication (PLCC) will be used for information exchange between the
powerhouse and the load dispatch center.
While deciding on contract packaging it is essential to use local resources and expertise to the
maximum so that the cost of the project is minimized. Currently there is no manufactures in Nepal
which can manufacture turbines and generating equipment of the size required by the project.
Hence the supply, delivery, installation, testing and commissioning of electromechanical
equipment contract shall be made with foreign manufacturer through International Competitive
Bidding (ICB) procedures. The other works involved in the project could be undertaken by local
contractors. Hence, civil works, transmission lines and metal works bidding can be carried out
through local competitive bidding (LCB) procedure. As this is a small size hydropower project,
the following contract packaging can be recommended.
Page | 64
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Alternatively, the project can also be built through the engineering, procurement and construction
(EPC) contract packaging which could reduce the cost and shorten construction period.
The following list of activities is mentioned as reference to be concluded for the project
implementation from the initial planning days.
Page | 65
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
All construction activities will be mainly concentrated in the dam site and the powerhouse site.
Following are the main activities during construction:
Diversion weir
The intake structure, connecting channel, sandtrap
Headrace channel
Forebay
Penstock
Powerhouse and switchyard
Tailrace structures
Based on the comprehensive study and construction planning, a detailed master construction
schedule has been prepared. The work involved at each of these areas is outlined below.
Preparatory Works
The preparatory works of the project for the main construction work will consists of land
acquisition followed by the construction of access road, camp facilities, construction power upto
pipe erection site, and workshop and camp site. The preparatory works like contractors camp
facilities, connection of construction power to the actual works area, drinking water supply, fixing
of quarry sites, fixing of sites for construction equipment, batching plant etc. will be managed by
respective contractors. The following preparatory works has to be carried out in the beginning of
the construction works.
Access Road
Camps, Water Supply and Sanitation facilities
Construction power
Communication System
In order to provide the necessary access to the work areas, camp site, borrow areas and disposal
areas, an access road to the disposal areas and proposed camp site will be constructed. The basic
assumptions, principal project components and their sequence of activities and construction works
to be executed in the project area are presented in the following sections.
Page | 66
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Basic Assumptions
Following are the basic assumptions used for the construction planning.
Financial arrangement will be carried out in parallel to the detail engineering study before the
construction works starts. Hence only the construction activities is listed in the bar chart.
Diversion Weir
The headworks comprises of a weir, intake . Construction of tyrolean weir and intake will be
completed in two dry seasons.
Firstly the right bank will be dewatered by diverting the river to left bank. Based on the available
river width after the first stage diversion, water depth flowing through the channel is calculated
and height of cofferdam with 1.0 m free board is adopted.
The river diversion will be followed by excavation for the foundation of the intake and a part of
free flow spillway. Once concerting for intake and a part of the weir have been completed,
installation of hydraulic structures will be made. After the rainy season, the river will be diverted
to the right bank so as to construct the remaining weir portion. The construction of intake and
weir will thus be carried out in two phases each of 4 months.
Headrace Channel
Of the water conveyance system, the headrace tunnel is the critical component of project
construction requiring an estimate time of 15 month. Hence, the special emphasis has to be made
for this component of work to ensure timely allocation of resources like equipment, material and
man power.
The total length up to forebay is 800 m.
Forebay
The forebay has a length of 62.5 m. Major works include surface excavation of invert and
concreting work. The total construction of forebay will be completed in about 4 months.
Penstock
The penstock has a diameter of 2.1 m and length of 200m upto the bifurcation point. The diameter
after the bifurcation is 1.40 m. The inclined penstock portion will be excavated form the top to
the bottom as open surface excavation as per the design shape and size. Anchor blocks will be
concerted upto the penstock base level. The saddle piers concrete works and slope protection
works will be carried out. After installation of the penstock pipe in line and alignment, it will be
concerted around in the anchor blocks and designed by providing reinforcement bars.
The total construction period of the penstock supports including installation works will be about
10 months.
Powerhouse
Page | 67
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The powerhouse construction works comprises surface excavation, slope stabilization, concreting,
erection of electromechanical equipment and ancillary structures. Once excavation has been made
for the foundation, compaction of subsurface will be made. Concreting of the subsurface & super
structure will be carried out followed up by erection of gantry crane. Installation of equipment
will be carried out once the civil works has been completed. It is anticipated that powerhouse
excavation will require 2 months while erection of standard will need another 10 months.
Electro-mechanical Equipment
After the civil works contract has been awarded, the tendering for electromechanical works will
be started. The electromechanical works consists of design, manufacturing, transportation,
installation, testing and commissioning of equipment such as turbines, generators, transformers,
Overhead Crane, hydro-mechanical works and their ancillary accessories.
Design manufacture, shop testing and delivery at the site will require 9 months. Erection will
require 4 months while testing will require another 1 month.
Switch Yard
The activity includes earthwork, preparation of base, erection of equipment etc. It will be built
over a period of 3 months.
Project Scheduling
The project construction planning has been carried out using `Microsoft Project‘ which is a
standard software used for such purpose.
As tunnel is the critical component of project construction special attention has to be made for it.
These include timely procurement of construction materials, sufficient number of shifts to achieve
an advance rate. Total duration of the project completion after the contract award is estimated to
be 36 months.
Page | 68
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 11
The IEE process follows the Environment Protection Rules, 1997, and amendment made on
2009 (2065/11/26) and National EIA Guidelines, 1993. This IEE is prepared based on field
studies and consultation with local people and officials. For the physical environment, data on
climate, geology and land were taken. Likewise, in socio-economic and cultural environment
data on population, ethnicity, religion and religious sites, infrastructure, etc are used for the
study. An interaction meeting was held at the project site.
Water Resources Act (1992), Electricity Act (1992), Water Resource Regulations (1993),
Electricity Regulation (1993), Hydropower Development Policy (1992), etc were studied while
preparing the report. In addition, important Acts and Regulations like EPA (1996) and EPR
(1997) and its amendments, Land Acquisition Act 1977, Forest Act (1993), and Forest Rules
(1995), Local Self Governance Act (1999) and Regulation (2000), National Environmental
Impact Assessment Guidelines (1993), Forest Produce, Collection and Sales Distribution
Guidelines (2000), etc were also extensively reviewed while preparing the report.
Page | 69
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Mammals such as Barking deer (Muntiacus munjak), Jackal (Canis aureus), Porcupine (Hystrix
Indica), Rhesus Monkey (Macaca mulata), Malsapro (Martes flavigula), squirrel (Fuinambulas
palmaurum) etc. are reported in the project affected area.
Common Myna (Acridotheres tristis), House Crow (Corvus splendens) and House Sparrow
(Passer domesticus). Koilee (Eudyanamus sp) etc are reported bird species in the project area.
Listed plant species in the project area are Sal (Shorea robusta), and Simal (Bombax ceiba).
Similarly, Rhesus monkey (Macca mullatta), common langur (Maccac assamensis) and leopard
(Panthera parades) are the listed wild animals found in the area.
Agriculture is the major occupation of the people in the project area. The rest of the people are
engaged in business, government service, labour, agro-based industries, livestock and poultry
farming, etc. Health service in the project area is delivered through the existing sub-health post
and health post in VDC.
Land take and land use change are main physical impacts. The project will not require land for
temporary use during the construction phase.
The construction activities like site clearance, excavation of the building foundation, vehicular
movement will generate dust and emission at the project site. However, the construction
activities are limited to small area and not in massive scale. Similarly, there may be noise due
to excavator machine and vehicle as well even workforce.
the forest. Consequently, other impacts on the biological environment of the project are
expected to be low.
The possible adverse impacts on wildlife and avifauna population during the project
construction phase are possibility of hunting and poaching by labour force and disturbance in
the migratory movement of mammals and birds.
One of the major beneficial impacts of the project during the construction phase is the creation
of employment opportunity. Altogether, 50 people will be deployed during the construction of
the project. In this regard, the employment opportunities contribute to poverty alleviation to
some extent.
Some of the major alternatives considered during the feasibility and IEE studies were: which
have minimal environmental impact, avoid build up swampy and unstable areas, provide easy
access for construction and maintenance works and avoid settlements as far as possible
The construction and operation of the hydropower will not have significant impact on the air
quality of the project impact area. Vehicle utilized for construction will be complied with GoN
mass emissions standards.
The project workers will strictly be prevented from hunting and poaching and any other kind of
illegal activities related to hunting and poaching. Informative and warning sign will be placed
at relevant construction sites.
The project group will implement awareness program to aware local people and member of
forest users group of the project area about the importance of forest conservation and wildlife
and economic importance of forest and its role in rural society.
Page | 71
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
11.9 CONCLUSION
The total cultivated land requirement will be approximately 3.6 ha (72 ropani). There will be
no direct impact on biological environment. In terms of the loss of land and assets, 48
households will be affected due to the implementation of the project. Various mitigation and
enhancement measures have been proposed during the construction and operation phase of the
project. The total environmental cost (mitigation, enhancement, CSR, and monitoring costs) of
the proposed project is estimated to be NRs. 6,643,959; which is 1.21% of the total project cost.
The IEE study concludes that construction of the proposed Lower Mardi River Hydropower
Project is environmentally and socially feasible if the proposed mitigation measures and
monitoring plans are implemented.
Page | 72
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 12
COST ESTIMATE
12.1 GENERAL
This Section of the report describes the methodology used for the derivation of the project cost.
This final estimate is based on the detailed layouts and study of the optimum project
configuration selected from the optimization studies and hence shall be considered different
from the cost estimates presented in the Chapter Project Optimization.
Quantities take off and carried out based on the final drawing and quantity calculation as
required.
Costs are derived from Kaski district rate 076/77 in Nepalese Rupees.
An exchange rate of US$ 1 = NRs. 110.00 is used.
Transportation from the nearest Terai Market (Bhairahawa) has been considered.
Most of the rates are analyzed based on the GoN Norms for estimation purpose.
Some specific rates which are not available in the norms are analyzed based on the past
reports of similar projects in Nepal.
It is anticipated that open competitive bidding will be sought for awarding the major contracts.
The costs are based on international competitive bidding under the assumption that the project
proves generally attraction to contractors and suppliers.
(1) Land Acquisition, Access Road, Camp and Construction Power facilities.
(2) Main Civil Works consisting of construction of the following structures:
Tyrolean Weir
Connecting Channel
Sand trap
Headrace Channel
Forebay
Penstock supports
Powerhouse and Central Building
Tailrace
Page | 73
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Penstock pipes
Turbines
Generators
Transformers
Auxiliary equipment
Gates, valves and heisting devices
- In order to account for the cost incurred for the construction of camp facilities, a sum of
1% of the base cost has been considered.
- An allowance of 2% of the base cost has been added to cover to costs for construction
power required for the implementation of the project.
(a) Division of the project into a number of distinct structure like Tyrolean weir, connecting
channel, sandtrap, headrace channel, forebay, penstock pipe supports, powerhouse and
control building, tailrace conduit .
(c) Calculation of the appropriate quantity of each item from maps and drawings.
(d) Development of unit rate of construction works based on district approved rates and
prevailing market rates.
(e) Calculation of cost for each activity by multiplying the quantity obtained in (c) by rates
derived in (d).
(f) Calculation of the cost of each structure by summing up the cost calculated in (e) of
different works required for the structure.
In application of this approach, a contractor’s overhead of 30% was used to reflect contractor’s
profit and overhead expenses.
Page | 74
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Considering the overall construction requirements of the project, a 6 days x 8 hours' work per
week, is selected as the basis for planning and estimating the major construction activities.
Page | 75
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The unit price of labour wages has also taken the reference of wage rate from similar project in
Nepal at present situation.
Wherever applicable norms published by the Ministry of Works and Physical Planning were used.
The price of labour and materials were obtained from District Approved Rates and also collected
from project under construction in Nepal.
- Partly on budget prices supplied by potential suppliers and information form the
experiences of other similar projects.
- Partly on in-house estimate using established international prices.
Physical Contingencies
The estimated costs include physical contingencies, which allow for unforeseen cost increases that
may become necessary as more information is obtained and evaluated.
In view of the extent of investigations carried out to date, the present stage of preliminary designs
and the cost analysis performed the following physical contingencies have been allowed.
Page | 76
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
An amount of 5% of direct base cost has been included to implement environmental mitigation
measures.
Page | 77
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 13
PROJECT EVALUATION
The relevant specific economic parameters that have been applied for the economic analysis in
this study are as follows:
Analysis Period: The construction of the project is assumed to be completed in 3 years. The
economic life of the plant’s civil structures has been assumed to be 50 years and electromechanical
component 30 years from the beginning. Commercial operation period of 30 years has been
assumed.
Interest Rate: A 10 per cent interest rate in real terms has been used, based on the assumed
economic opportunity cost of capital. This is in line with the rate generally used for the power
sector for the evaluation of public sector projects in the country
Economic Investment Cost: As per the existing laws, custom duties at the rate of 1 per cent is
levied on the imported goods that are not manufactured in Nepal. Value added tax at the rate of
13 per cent has not been added to the local cost component for the economic analysis. Based on
these facts, the total economic investment cost of the project is NRs. 574.78 million.
Operation and Maintenance Costs: Annual operation and maintenance costs of the plant in the
first year of commercial operation following completion of the project have been assumed to be
1.5 per cent of the total project cost. Thereafter it is assumed to increase at the annual escalation
rate of 5 per cent.
Financial evaluation uses the real monitory values of the cost and benefits and is inclusive of taxes
transfers, duties and escalation. The financial evaluations concern with the private developers of
the project and its impact on their account. Hence, from the perspective of a private developer,
financial evaluation is the most important aspect of the project to determine whether to finance it
or not.
Page | 78
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The conventional approach was followed for conducting the financial analysis. In this approach,
costs and benefits were first estimated on a common basis. For a project to be feasible and viable,
the benefits should be more than the costs. The methodology involves a number of assumptions
based on prevailing values.
Payback Period
Payback period is the time it takes the cash inflows from a capital investment project equal
to the cash outflows, usually expressed in years. Payback period alone cannot be the basis
to evaluate the project. It ignores some aspects of the overall project. It ignores some
aspects of the overall project. The Simple payback period of the project is found to be 8.24
years.
Page | 79
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Chapter – 14
14.1 CONCLUSIONS
The proposed Lower Mardi River Hydropower Project is a small scale run of river hydropower
scheme. It is located in Machhapurchre Rural Municipality,Kaski district, Gandaki Zone in
Western development region of Nepal. The following main conclusions have been drawn from
the feasibility study of Lower Mardi River Hydropower Project
(1) The project is technically feasible. The total installed capacity of the Lower Mardi River
Hydropower Project is 2160kW. The scheme has a simple tyrolean weir with sandtrap,
headrace channel of 0.80 km in length, forebay, surface type penstock, surface type
powerhouse and tail race. Two horizontal shafts francis turbines are envisaged, which can
be operated at a rated net head of 27.9 m and total rated turbine flow of 5.50 m3/sec.
Generating units have the capacity of 2 x 1080 kW = 2160 kW. The units are installed in
a surface type powerhouse. The total energy generation of the plant will be 14.1 GWh.
(2) The project is also economically feasible and financially viable. The cost of the project at
2019 price level, including contingencies and engineering is estimated to be NRs. 574.78
million. The financial internal rate of return is 13.30% and benefit cost ratio is 1.13.
(3) The construction period of the project from the date of contract award of the civil works
till the completion of the project work is 36 months including mobilization, testing and
commissioning.
(4) In addition to suitable topography, hydrology and geology for the development of
hydropower project, the location of project site is close and accessible from the district
headquarter. This is a very attractive project for private sector investment.
(5) The project will have low environmental impacts, typical for a run of river hydropower
project. No household dislocation and rehabilitation problems exist in this project.
(6) There are no upstream or downstream irrigation facilities of community water supply
systems to be affected by the project.
Job opportunities for the local people, local market development, rural electrification,
access road and contribution to regional development are some of the direct positive
impacts.
Page | 80
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
14.2 RECOMMENDATIONS
The project is recommended for implementation from technical, economical, financial and
environmental points of view.
Following measures have been recommended for the proposed Lower Mardi River Hydropower
Project :
(2) The mitigation measures recommended should be implemented during the construction
phase of the project.
(3) The field layout of the structures and review works has to be done before contractor is
mobilized and field accommodation have to be made on drawings before issuing the
working drawings with coordinates of major structures to the contractors.
(4) The competent construction supervision team has to be formed for getting maximum
efficiency and quality for benefit of the project.
(5) PPA have to be done, so that the construction activities shall be started.
(6) In order to optimize the cost of transmission line, efforts should be made for cost sharing
with co-developers in this basin.
Page | 81
Pokhara University, School of Engineering
APPENDIX A-
HYDRAULIC
DESIGN
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
- BASIC DATA
Design discharge for power
QA = 8.50 m3/s
generation
Design flood discharge (100
QF = 346.60 m3/s
years)
Crest length (total) LS = 27.14 m
River bed level at weir site = 1094.34 m a.s.l.
Minimum headwater depth ho = 0.5 m
Contraction coefficient for
µ = 0.85 (round bars)
trashrack
Clear distance between bars a = 1.48 cm
C/c spacing of bars d = 3.0 cm
Inclination of trashrack β = 15 degree
k value against β k = 0.872
-
H|1
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
FLOOD DISCHARGE
TRASHRACK
Coefficient
Coefficient c = 0.28
Discharge to be diverted
H|2
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
GEOMETRY OF WEIR
m.a.s.l
Required bed El: of stilling basin ELBS = 1092.00
.
H|3
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
DESIGN LEVELS
Top EL: of u/s side wall TLUW = 1099.10 m a.s.l. F.B. = 0.50m
Top EL: of d/s side wall TLDW = 1097.00 m a.s.l.
The length of stilling basin may be reduced due to economic considerations, keeping in
view the fact that the boulders carried by the river/nullah during flood season will deposit in
the stilling basin providing an armouring layer. A cut-off wall to bed rock of suitable depth
should also be provided for added protection against undermining by scour.
H|4
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1096.0
Longitudinal Section
1095.1
1095.0
Elevation (m asl)
1094.0
1093.0 1093.0
1092.0
1091.0
1090.0 1089.6
1089.0
0.0 5.0 10.0 15.0 20.0 25.0
Distance (m)
X-Section
1100.0
1098.0
Elevation (m asl)
1096.0
1094.0
1092.0
1090.0
1088.0
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0
Distance (m)
= 14.05
Water depth in embedded channel t = 3.01 m
Freeboard (25% of water depth) f = 0.75 m
Total depth of embedded
Dt = 3.76 m (recommended)
channel
Total depth of embedded (provided
Dt = 3.95 m
channel )
3.0
2.5 0.8 2.59
2.0 1.1 4.38
1.5 1.5 6.25
1.0 1.9 8.17
0.5 2.3 10.11
0.0 2.6 12.07
0.00 5.00 10.00 15.00 20.00 25.00 30.00 3.0 14.05
Flow (cumecs) 3.4 16.04
3.8 18.03
FRICTION LOSS
Friction headloss (Manning)
H|6
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Where
1090.0
Bed EL: of embedded channel (end) = m a.s.l.
8
Water EL: in embedded channel 1093.0
= m a.s.l.
(end) 9
H|7
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
STILLING BASIN
H|8
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1,101 W.L. Q
1,100
(m a.s.l.) (m3/s)
1093.5 0.0
1,099
1094.0 10.6
1,098
Elevation (m)
1094.5 32.7
1,097
1095.0 62.9
1,096
1095.5 99.4
1,095 1096.5 187.5
1,094 1097.0 237.7
1,093 1098.0 347.9
0.0 200.0 400.0 600.0 800.0
1099.0 468.9
Discharge (m3/s) 1101.0 735.7
Froude Number
(Where V & D are velocity and depth of flow entering the jump)
Manning's Equation
H|9
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Alternatively
Alternatively
Length of stilling basin
Alternatively
Length of stilling basin
Stilling basin with a sloping end sill and one or two rows of baffle blocks 2
CREEP LENGTH
Overflow case
H | 11
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
UPLIFT FORCE
Where:
Uplift pressure head = ux m
The u/s water depth = h m
El. at point 'x' relative to river bed = Hx m
Creep length upto point 'x' = Lx m
H | 12
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
FLOOR THICKNESS
Δh = 1.67 m
Head across the weir
H | 13
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Δh = 0.83 m
Head across the weir
VERTICAL FORCES
Weight of structure G = W1 + W2 +W3
Weight of structure G = 1905.8 kN
Water surcharge WV
Water surcharge WV = 632.5 kN
HORIZONTAL FORCES
Force due to headwater WH1e =
Force due to headwater WH1e = 202.7 kN
Noncohesive
tan ϕ
soils
sand 0.56
gravel 0.60
rubble/stones 0.70
Cohesive soils
clay 0.20
sandy clay 0.30
vG = 10.24
CONCRETE VOLUME
Concrete quantity in u/s & d/s
cutoffs
Flow area
Wetted perimeter
Flow velocity
H | 18
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Approach velocity
H | 19
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Parameters of the crest geometry are determined from the above figure.
K = 0.502 n = 1.830
H | 20
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The origin of X - Y axis is at the crest of spillway and Xc is distance from the u/s face to
crest.
Y^0.54
X = -2.559
6
Y = -0.179 X^1.83
H | 21
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Hydraulic Profile X Y
0.10
H | 22
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
- BASIC DATA
m
Channel Invert elevation B.L.1 = 1090.19
a.s.l.
Channel bed width b = 1.43 m
Depth of flow in connecting channel y = 3.01 m
Total depth of connecting channel hc = 4.25 m
Free board F.B. = 1.24 m
1095
1094.5
1094
0 1094.4
1093.5
0 1090.2
1093
1.4 1090.2
1092.5
1.4 1094.4
1092
1091.5
0 1093.2
1091
1.43 1093.2
1090.5
1090
1089.5
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6
SCOURING SLOPE
To avoid accumulation of particles in the connencting channel a suitable scouring slope
should be estimated as follows.
Scouring Slope
H | 23
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Where:
Sediment size d = 0.015 m
Unit discharge of connecting
qo = 7.13 m3/s/m
channel
Manning's equation
Flow area
A = 4.30 m2
Wetted perimeter P
Wetted perimeter P = 7.44 m
Top width T
Top width T = 1.43 m
Hydraulic depth D
Hydraulic depth D = 3.01 m
Hydraulic radius R
Hydraulic radius R = 0.58 m
Flow velocity V
Flow velocity V = 3.27 m/s 2.37
H | 24
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Discharge capacity Q
Discharge capacity Q = 14.06 m3/s
Unit discharge q
Unit discharge q = 9.83 m3/s/m
Critical depth yc
Critical depth yc = 2.14 m
Froude number,
Froude number Fr
Froude number Fr = 0.60
HEADLOSSES
FRICTION LOSS
BEND LOSS
The channel bends should have a centerline radius of 3T to 5T or more, where ‘T’ is the
water surface width of the design flow. If the radius must be reduced, the head loss at
channel bends can be estimated as;
Headloss at bends
Where:
K = 2 x (B / Rc),
Rc = center-line radius,
B = channel width
RATING CURVE
Rating curve at given distance x = 0.0 m (from start)
1094.0
1093.5
1090.6 1.19
1093.0 1091.0 3.05
1092.5 1091.5 5.11
1092.0 1091.9 7.25
1091.5
1092.3 9.44
1091.0
1090.5
1092.7 11.66
1090.0 1093.2 13.89
1089.5 1093.6 16.14
0.00 5.00 10.00 15.00 20.00 25.00
1094.0 18.39
Flow (cumecs) 1094.4 20.66
H | 26
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Longitudinal Profile
1095.0
1093.0 1093.2
1092.7
1092.0
1091.0
1090.0
1089.0
0 20 40 60 80 100 120
Distance (m)
SURGE CALCULATIONS
H | 27
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Where:
Hydraulic depth D = 3.01 m D = A/T
As only one gate has been provided at the inlet of connecting channel, therefore
Check Δymax < F.B. = O.K.
SUPER-ELEVATION
Rise in water surface above flow
depth
Where:
Radius of bend / curve r = 7.2 m
CONCRETE VOLUME
1095
1094
0.0 1089.9 2.0 1090.2
1093 0.0 1090.2 2.0 1094.4
1092
0.3 1090.2 2.2 1094.4
0.4 1094.4 2.3 1090.2
1091 0.6 1094.4 2.6 1090.2
1090
0.6 1090.2 2.6 1089.9
2.0 1090.2 0.0 1089.9
1089
0.0 0.5 1.0 1.5 2.0 2.5 3.0
H | 29
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
DESIGN OF SANDTRAP
- BASIC DATA
FLOW VELOCITY
Flow velocity (required)
cm/s
√
Coefficient a = 44
Maximum flow velocity in sandtrap vd = 17.04 cm/s
Maximum flow velocity in sandtrap vd = 0.17 m/s
SETTLING VELOCITY
mm/s
Alternatively:
(for T 20o & grain to water density ratio of
2.65)
Reduction factor
Reduction factor α = 0.050
Settling velocity in flowing
water
vs = 0.0090 m/s
Length of chamber
H | 31
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Alternatively:
Transit time
Length of chamber
H | 32
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
CRITICAL VELOCITY
Critical velocity
√ m/s
H | 33
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
TRAP EFFICIENCY
Percentage of sediments retained ( )
Constant e = 2.718
80% 68%
60%
40% 26%
20%
0%
0.5 mm 0.25 mm 0.2 mm 0.1 mm 0.05 mm
Particle Size (mm)
H | 34
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
FINAL DIMENSIONS
179.0
Total length of sandtrap LT = m
0
H | 35
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
TRASHRACK
Width of Trashrack
Width of Trashrack
H | 36
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
HEADLOSSES
FRICTION LOSS
ENTRANCE LOSS
K= 0.10
Entrance headloss
hLE = 0.03 m
H | 37
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Where
hLut = 0.085 m
hLdt = 0.100 m
TRASHRACK LOSS
H | 38
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
LONGITUDINAL SECTION
H | 39
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Longitudinal Section
1094.0
1093.1
1092.0 1091.6
1091.6
1090.0 1089.6
Elevation (m asl)
1088.0
1086.0
1084.0
1082.0
1080.0
1078.0
0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0 180.0 200.0
Distance (m)
X - Section
1094.0
1093.1
1092.0
1090.0
Elevation (m asl)
1088.0
1086.0
1085.7
1084.0
1082.6
1082.0
1080.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0
Distance (m)
H | 40
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
TRANSITION LENGTH
chamber(s)
Flushing discharge
H | 42
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
CB = 0.37 m3
CS = 0.39 m3
H | 44
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1081.4
1081.2
1081
1080.8
1080.6
1080.4
1080.2
1080
1079.8
1079.6
0.0 0.5 1.0 1.5 2.0 2.5
SPILLING ARRANGEMENT
A side channel spillway arrangement is recommended for spilling the excess flows diverted
from the Tyrolean weir during high flow (Summer) season. In the absence of such spilling
arrangement the excess flows will be carried by the Power Channel all the way to the Forebay
causing some spillage along the Power Channel which is least desirable.
Provide Spilling Arrangement YES
Crest level of spill section ELC = 1092.59 m asl
Width of spill section (crest
LS = 25.0 m
length)
Allowable surcharge over crest H = 0.35 m
Check Qs ≥ QD = O.K.
SPILL CHANNEL
Length of spill channel (Δx) LSP = 70.0 m
H | 45
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1096.5
1096
1095.5
1095
1094.5
1094
0 1095.1
1093.5
1093
0 1091.1
1092.5 2.1 1091.1
1092 2.1 1095.1
1091.5 0 1094.1
1091
0 0.5 1
2.11.5 1094.1 2 2.5
Manning's Equation
H | 46
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1094.5
1091.09 0.00
1094.0
1091.49 1.70
1093.5
1091.89 4.57
1093.0
1092.29 7.88
1092.5
1092.69 11.40
1092.0
1091.5
1093.09 15.05
1091.0
1093.49 18.77
1090.5
1093.89 22.55
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 1094.29 26.36
Flow (cumecs) 1094.70 30.20
1095.10 34.07
1095.5
1095
1094.5
1094
1093.5
1093
1092.5
1092
1091.5
1091
1090.5
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5
H | 48
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1093.5
1093.0
1092.5
1092.0
1091.5
1091.0
1090.5
0 2 4 6 8 10 12
Mannings equation
Flow area
10.2
Flow area A = m2
4
Wetted perimeter
H | 49
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Top width
Top width T = 8.80 m
Hydraulic depth D
Hydraulic depth D = 1.16 m
Hrdraulic radius R
Hrdraulic radius R = 1.05 m
Flow velocity V
Flow velocity V = 1.10 m/s 1.72
Discharge capacity Q
11.3
Discharge capacity Q = m3/s
1
Check Q ≥ Qd = O.K.
Unit discharge q
Unit discharge q = 2.83 m3/s/m
Critical depth yc
Critical depth yc = 0.93 m
Froude number Fr
Froude number Fr = 0.33
H | 50
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
B/
Flow Total Hyd.
Velocit Discharg D
Bed Width Dept Dept Radiu
y e rati
h h s
o
B (m) y (m) D (m) R (m) V (m/s) Q (m3/s)
3.00 2.66 3.16 0.96 1.04 8.32 0.95
3.25 2.40 2.90 0.97 1.05 8.18 1.12
3.50 2.19 2.69 0.97 1.05 8.06 1.30
3.75 2.02 2.52 0.97 1.05 7.96 1.49
4.00 1.88 2.38 0.97 1.05 7.88 1.68
4.25 1.76 2.26 0.96 1.04 7.81 1.88
4.50 1.66 2.16 0.95 1.04 7.75 2.08
HEADLOSSES
ENTRANCE LOSS
K= 0.10
FRICTION LOSS
BEND LOSS
The channel bends should have a centerline radius of 3T to 5T or more, where ‘T’ is the
water surface width of the design flow. If the radius must be reduced, the head loss at
channel bends can be estimated as;
Where:
K = 2 x (B / Rc),
Rc = center-line radius,
H | 51
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
B = channel width
RATING CURVE
Rating Curve
1093.5
Elevation Flow
Water Elevation (m asl)
H | 52
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Longitudinal Profile
1093.5
Distance (m)
SURGE CALCULATIONS
Where:
Hydraulic depth D = 1.16 m
H | 53
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
SUPER-ELEVATION
Rise in water surface above flow depth
Where:
Radius of bend / curve r = 44.0 m
The channel bends should have a centerline radius of 3T to 5T or more, where ‘T’ is the
water surface width of the design flow.
Super-elevation at bends Δy = 0.012 m
Super-elevation at bends Δy = 1.24 cm
CONCRETE VOLUME
(Not applicable to stone masonry
channels)
H | 54
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1093.5
1093
1092.5
1092
1091.5
1091
1090.5
1090
0.0 1.0 2.0 3.0 4.0 5.0 6.0
H | 55
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
DESIGN OF FOREBAY
- BASIC DATA
- INFLOWS
- OUTFLOWS
- PEAKING TIME
H | 56
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Transition length
HEADLOSSES
FRICTION LOSS
Friction headloss (Manning)
ENTRANCE LOSS
LONGITUDINAL SECTION
(Wall top level will be constant throughout the entire length of forebay including u/s transition)
Allowable fluctuation in
σallow = 1.4 m
water level
Longitudinal Section
1096.0
1094.0
Elevation (m asl)
1092.0
1090.0
1088.0
1086.0
1084.0
1082.0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0
Distance (m)
(live storage
Useful capacity (required) VF-R = 3323 m3
required)
H | 59
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Normally a volume of QP x 120 m3 (or two minutes at maximum plant flow) will be satisfactory
for mechanical governors. For digital governors the control volume can be further reduced.
Water level in fore bay masl = 1085 1091 1091 1092 1092
Useful volume in fore bay m3 = 0 2089 3212 4335 5459
Total volume in fore bay m3 = 0 13244 14367 15491 16614
Initial Final
Fore bay Fore bay
Time forebay forebay Spill
inflow outflow
volume volume
(hrs) (m3/s) (m3) (m3/s) (m3) (m3/s)
0 0 3323 0 3323 0
1 6:PM 1.77 3323 11 0 0.00
2 7:PM 1.77 3323 11 0 0.00
3 8:PM 1.77 3323 11 0 0.00
4 9:PM 1.77 3323 11 0 0.00
5 10:PM 1.77 3323 1.77 3323 0.00
6 11:PM 1.77 3323 1.77 3323 0.00
7 12:PM 1.77 3323 1.77 3323 0.00
8 1:AM 1.77 3323 1.77 3323 0.00
9 2:AM 1.77 3323 1.77 3323 0.00
10 3:AM 1.77 3323 1.77 3323 0.00
11 4:AM 1.77 3323 1.77 3323 0.00
12 5:AM 1.77 3323 1.77 3323 0.00
13 6:AM 1.77 3323 1.77 3323 0.00
14 7:AM 1.77 3323 1.77 3323 0.00
15 8:AM 1.77 3323 1.77 3323 0.00
16 9:AM 1.77 3323 1.77 3323 0.00
17 10:AM 1.77 3323 1.77 3323 0.00
18 11:AM 1.77 3323 1.77 3323 0.00
19 12:AM 1.77 3323 1.77 3323 0.00
20 1:PM 1.77 3323 1.77 3323 0.00
21 2:PM 1.77 3323 1.77 3323 0.00
22 3:PM 1.77 3323 1.77 3323 0.00
23 4:PM 1.77 3323 1.77 3323 0.00
24 5:PM 1.77 3323 1.77 3323 0.00
H | 60
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
TRASHRACK
Width of trashrack
Number of rack bars
H | 61
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
H | 62
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
SPILL SECTION
Provide Spilling Arrangement YES
Crest level of spill section ELC = 1092.09 m asl
Width of spill section (crest
LS = 17.0 m
length)
Allowable surcharge over crest H = 0.75 m
1096.5
1096
1095.5
1095
1094.5
1094
1093.5
0 1095.9
1093 0 1091.6
1092.5 2.1 1091.6
1092 2.1 1095.9
1091.5 0 1094.8
1091 2.1 1094.8
0 0.5 1 1.5 2 2.5
H | 63
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Manning's Equation
CB = 44.23 m3
Concrete quantity in bottom slab
1097
1096
1095
H | 65
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Ref: C. Nalluri
2.50
fz = 1.12
a = 5.066
h = -0.550
θ y
2θ = 232.21
Mannings equation
Flow velocity V
V = 4.48 m/s
H | 66
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Elevation Flow
Rating Curve (Spill Pipe Option)
1094.5 1091.6 0.00
1091.8 0.41
Water Elevation (m asl)
1094.0
1093.5
1092.1 1.71
1092.3 3.82
1093.0
1092.6 6.58
1092.5 1092.8 9.76
1092.0 1093.1 13.11
1091.5 1093.3 16.34
1091.0
1093.6 19.08
0.00 5.00 10.00 15.00 20.00 25.00 1093.8 20.80
Flow (cumecs) 1093.9 21.00
Froude Number
(Where V & D are velocity and depth of flow entering the jump)
α (D2 -
Length of stilling basin LB =
D1)
LB = -6.0 m
Alternatively
Length of stilling basin
LB = 10.48 m
H | 68
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
FLUSHING PIPE
H | 69
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
As = 0.015 m2
The use of the impact-type stilling basin is limited to installation where the velocity at the entrance
to the stilling basin does not greatly exceed 30 ft/s (9.1 m/s). For discharges exceeding 10 m 3/s, it
may be more economical to consider multiple units side by side.
H | 70
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Alternatively:
Inside width of stilling basin (from
W = 6.00 ft = 1.83 m
graph)
Loss in energy (from graph) EL/E1 = 53 %
The dimensions of various components as shown in the above figure, are given
below;
ft
Total depth of basin at start (H = 3/4 W) H = 8.20 2.50 m
=
ft
Total length of basin (L = 4/3 W) L = 14.58 4.44 m
=
ft
Distance of baffle from inlet (a = 1/2 W) a = 5.47 1.67 m
=
ft
Height of baffle (b = 3/8 W) b = 4.10 1.25 m
=
ft
Depth of basin at end (c = 1/2 W) c = 5.47 1.67 m
=
ft
Length of baffle top (d = 1/8 W) d = 1.37 0.42 m
=
ft
e = 1/12 W e = 0.91 0.28 m
=
ft
Thickness of baffle (t = 1/12 W) t = 0.91 0.28 m
=
ft
Riprap stone size (drock = 1/20 W) drock = 0.55 0.17 m
=
ft
Length of riprap (Lrr = W) Lrr = 10.93 3.33 m
=
H | 72
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
DESIGN OF PENSTOCK
BASIC DATA
H | 73
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
2.10
For circular pipes D is the diameter while maximum values of 'x' & 'y' are given in plan view
as;
Maximum 'x' = 0.65D from pipe centerline and Maximum 'y' = 0.5D from entrance face
However the existing practice in the region is to adopt the bellmouth diameter as 1.5D,
therefore
Therefore:
x y (low) y (up)
Plan
1088.5 2.100 1085.120 1088.270
1088.0 2.100 1085.120 1088.270
Elevation (m asl)
H | 75
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
GATE SIZE
Gate hight H = 2.10 m
Gate width W = 1.65 m
For a gate having H=D and W=0.785D, the flow velocity at the gate will be equal to the
velocity in penstock so no further flow acceleration is produced in this section.
FRICTION FACTOR
Reynolds number
where:
Kinematic viscosity of water at 20oC ν = 1.0E-06 m2/s
where:
Roughness height (welded steel) e = 0.600 mm
Ratio e/D = 0.00029
1 = 1.06
Friction factor (Moody) f = 0.01678
H | 76
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
SUBMERGENCE REQUIREMENTS
TRASHRACK
Width of Trashrack
Width of Trashrack
H | 77
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Height of trashrack
H | 78
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
HEADLOSSES
FRICTION LOSS
Mannings equation
Headloss (Manning)
Hazen-Williams equation
where & Cu=0.278
Headloss (Hazen-Williams)
Alternatively,
Headloss (Hazen-Williams)
Darcy-Weisbach equation
1 = 0.87
Headloss (Colebrook-White) hf = 0.55 m
H | 79
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
TRASHRACK LOSS
ENTRANCE LOSS
K= 0.20
Entrance headloss hLE = 0.0049 m
Where
H | 80
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
BEND LOSS
K= 0.20
No. of bends = 10 no.
Headloss in bends hLB = 1.03 m
H | 81
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
VALVE LOSS
Kv = 0.20
Valve headloss hLV = 0.10 m
MANIFOLD LOSS
Kb = 0.30
Manifold headloss (bifurcation) hLB = 0.15 m
Where:
Kb = 0.20 for symmetrical bifurcation,
Kb = 0.30 for symmetrical trifurcation,
and
Kb = 0.20 for manifold branch
H | 82
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
(The usual limit of headlosses in penstocks is 4% of gross head from economic point of view)
PENSTOCK SECTIONS
SEC- SEC-
PENSTOCK SECTIONS SEC-01 SEC-03
02 04
Length of section-i Li = 50.0 50.0 50.0 50.0 m
Invert elevation at end of each
di = 1079.1 1073.1 1071.1 1067.2 masl
section
Elevation drop in section-i ΔEi = 6.0 6.0 2.0 3.9 m
Penstock inner diameter di = 2.10 2.10 2.10 2.10 m
Thichness of steel sheet ti = 6.0 7.0 7.0 8.0 mm
Angle of inclination with vertical θi = 83.11 83.11 87.71 85.50 deg.
Longitudinal slope Si = 0.12 0.12 0.04 0.08 m/m
Velocity of flow Vi = 3.18 3.18 3.18 3.18 m/s
Invert level at start I.L.iS = 1085.1 1079.12 1073.12 1071.12 masl
Invert level at end I.L.iE = 1079.1 1073.1 1071.1 1067.2 masl
Longitudinal Profile
1088
1086
1084
1082
Elevation (m asl)
1080
1078
1076
1074
1073
1072
1071
1070
1068 INVERT LEVEL
1067
1066
0 50 100 150 200 250
Distance (m)
H | 83
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
AERATION PIPE
Collapsing
Pc = 0.16 kN/mm2
depression
Diameter of aeration
pipe
for Pc ≤ 0.49
Diameter of aeration
pipe
for Pc > 0.49
ALTERNATIVELY
Air vent area should be greater of these or
two values
Where:
Cross-section area
AP = 3.46 m2
of penstock
Rated turbine flow QT = 11.00 m3/s
Cross-section area
AV = 0.69 m2
of air vent pipe
Diameter of air
dV = 0.94 m
vent pipe
The air vent should exhaust to a safe location unoccupied by the project staff or general public.
CRACK OPENING
The penstock should be filled slowly to avoid excessive and dangerous "blow-back". The
recommended practice is to control filling rate via the head gate. The head gate should not be
opened more than 50 mm until the penstock is completely full. This is sometimes referred to as
"cracking" the gate.
H | 84
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
MANIFOLD / BIFURCATION
Number of turbine
nT = 2 no.
units
Number of branches /
nb = 2 no.
manifolds
Discharge of one
Qb = 5.50 m3/s
branch
Diameter of main
D = 2.10 m
penstock
Average velocity in
V = 3.18 m/s
main penstock
Flow velocity in
vb = 3.18 m/s (vb ≥ V)
branches (required)
Check vb ≥ V = O.K.
Length of first
Lb1 = 7.7 m
bifurcation / branch
Length of second
Lb2 = 11.9 m
bifurcation / branch
Length of third
Lb3 = 13.6 m
bifurcation / branch
Wall thickness of
tsb = 14.00 mm
branches
X-sectional area of
steel
H | 85
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
X-sectional area of
As = 0.062 m2
steel
Volume of steel in
Vs = 2.06 m3
branches
Weight of steel in W
= 16.21 tons
branches s
Weight of steel (5% W
= 17.02 tons
increse for joints) s
SURGE CALCULATIONS
Pressure wave speed
Bulk modulus of
water k = 2.1E+09 N/m2
Modulus of elasticity
of pipe material E = 2.1E+11 N/m2
Maximum wall
ts = 6.0 mm
thickness (provided)
H | 86
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Where:
N = 0.29
Maximum
m of water
overpressure ΔP = 21.13
column
(positive)
Maximum
ΔP =
overpressure -1.24 m of water column
(negative)
If water acceleration constant is less than 3 seconds than surge tank is not
required
Water acceleration constant
th = 2.16 sec
ALTERNATIVELY
or
A surge tank may be required
when
TANK REQUIRED
Check L/H<5 =
ALTERNATIVELY
A surge tank may be required
when
Where:
Maximum length of penstock
H | 87
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
TANK
Check L < Lmax =
REQUIRED
WALL THICKNESS
PENSTOCK MATERIAL
ASTM A516-70 steel having yield stress of 38000 psi (262010 kN/m2) and tensile stress of
80000 psi (55880 kN/m2) has been used for penstock design.
Joint efficiency (E) has been taken as 100% ( i.e. 100% radiographic inspection).
Following conditions have been
considered.
Allowable Design Allowable Design
Condition Stress increase Stress
factor (K) Sa = (SI)(K)(E)
Normal Operating 1 25,333 psi (174671 kN/m2)
Emergency 1.5 38,000 psi (262010 kN/m2)
Exceptional 2.5 63,333 psi (436681 kN/m2)
H | 88
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
(required)
Effective thickness of
te = 10.00 mm
penstock
ALTERNATIVELY
Minimum thickness of steel
(D in mm)
sheet
tmin = 7.29 mm
The larger value of minimum shell thickness governs for design purpose
Hoop stress
H | 90
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
H | 91
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
V = (4*4-0.5*0.5*0.4)*3.5
= 55.65 m3
= 55.65- - 4π*
= 39.21 m3
= π*(2.1+0.012)*0.012*78.50
= 6.25 KN/m
= 33.97 KN/m
H | 92
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Therefore,
Here;
L1u = 4m
L1D = 3m
= 119.58 KN
4. F3 = 15.4*Htotal*d*sin((β-α)/2)
= 5.4*30*2.1*sin ((3-42)/2)
= -323.85 KN
5. F6 = 100*d = 100*2.1 = 210 KN
6. F7 = 31*Htotal*(d+t)*t
= 31*30*(2.1+0.012)*0.012
= 23.56 KN
F7U = 31*(30-L4U*sinα)*(d+t)*t
= 31(30-0*sin (42))*(2.1+0.012)*0.012
= 23.56 KN
F7D = 31*30*(2.1+0.012)*0.012
H | 93
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
= 23.56 KN
√
Ka =
√
√
=
√
= 0.4
F10 = 0.5*γsoil*h12*cosi*ka*w
= 0.5*20*1.162*cos17*0.4*4
= 20.58 KN
Note: This force act at 1/3 of buried depth of upstream of anchor block;
h1 = 1/3*3.5 = 1.16m
H | 94
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
SUM ∑ ∑
∑ ∑
Calculate the centre of gravity of the block from the upstream face by taking moment of
mass about O,
( ) ( )
X=
= 1.98m
i.e. the weight of the block WB acts 1.98m from the point O.
Sum of the horizontal forces that acts at the bend;
(∑ – F10)x
1. Expansion case = 401.416-20.58 = 380.836 KN
2. Contraction case = -24.564-20.58 = -45.144 KN
Sum of vertical forces that acts at the bend;
(∑ – F10 –WB)
∑
d= ∑
= = 2.0
e= –d= = 0.0
eallowable = = = 0.66m
H | 95
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
2. CONTRACTION CASE
∑ @O = -45.144*0.2+862.62*1.98+495.89*2 = 2690.7306 KN-m
∑
d= ∑
= = 1.95m
e= –d= m
eallowable =
e < eallowable, which is safe against overturning.
H | 96
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
α = 42⁰
= 40.22*6*sin42
= 161.47 KN/m
F2 = F1
== 40.36 KN/m
A1 = 2.2*0.8 = 1.76 m2
A2 = 0.8*2.2 = 1.76 m2
X = 1.1
H | 97
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
F2 = F2 * cosα F2 *sinα
W = 232.32
0 232.32 0 232.32
∑ ∑ ∑ ∑
∑
So, d = ∑
e=| | = 0.58
Similarly;
∑
P=( )(1+ )
H | 98
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
At Sliding
∑ ∑
149.98 0.5*367.34
149.98 183.67 OK
For Overturning
0.58
0.58
∑ = 313.36 KN
∑
d= ∑
e=| |
= 0.66
Similarly,
∑
P=( )(1+ )
=
= 249.26 KN/m2 OK
H | 99
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
At Sliding
∑ ∑ (
90
90
For Overturning
0.6
0.6
H | 100
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
For high tailwater levels at flood It may be necesssary to provide separate erection and unloading bays
adding considerably to the repair bay floor area.
L = 35 m
W = 16 m
MAIN DIMENSIONS = 10
H m
Ds = 5 m
Height of powerhouse crance rail= this dimension varies somewhat more than the others, as
other factors influence the height of the crane rail. These include:
The requirement to accommodate a main transformer for unloading in the rapair/unloading bay
or large rise in the tailwater at flood, increasing the length of the unit shaft and thus requireing a
higher crane level.
H | 101
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
The height of the underisdde of the powerhouse crane rail is taken with refernce to the unloading
bay in case the unloading and repair bays are at different elevations.
Thus the crane rail height shall be less with reference to the unloading bay as sufficient height
for equipment erction/assembly shall available on the repair bay. The relationship is derived
Hc (H=Height of theunderside of the powerhouse crane rail above the repair /unoading bay floor
- BASIC DATA
H | 102
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1065.5
1065 0 1065.3
0.7 1063.3
1064.5 4.4 1063.3
5.1 1065.3
1064 0.175 1064.8
4.89 1064.8
1063.5
1063
0 1 2 3 4 5 6
Mannings equation
Flow area A
Flow area A = 6.28 m2
Wetted perimeter P
Wetted perimeter P = 6.84 m
Top width T
H | 103
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
Hydraulic depth D
Hydraulic depth D = 1.33 m
Hydraulic radius R
Hydraulic radius R = 0.92 m
Flow velocity V
Flow velocity V = 1.83 m/s
Discharge capacity Q
Discharge capacity Q = 11.48 m3/s
Check Q ≥ QD = O.K.
Unit discharge q
Unit discharge q = 3.14 m3/s/m
Critical depth yc
Critical depth yc = 1.00 m
Froude number Fr
Froude number Fr = 0.51
H | 104
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
RATING CURVE
Rating Curve
1065.5
Elevation Flow
Water Elevation (m asl)
1065.0
1063.3 0.00
1064.5
1063.5 0.47
1063.7 1.43
1064.0 1063.9 2.72
1064.1 4.29
1063.5 1064.3 6.09
1064.5 8.10
1063.0
0.00 5.00 10.00 15.00 20.00 1064.7 10.31
Flow (cumecs) 1064.9 12.70
1065.1 15.28
1065.3 18.04
Longitudinal Profile
1065.5
1065.0
Elevation (m asl)
1064.8 1064.7
1064.5
1064.0
1063.5
1063.0
0 10 20 30 40 50 60 70 80
Distance (m)
H | 105
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
SURGE CALCULATIONS
CONCRETE VOLUME
H | 106
Pokhara University, School of Engineering
Feasibility Assessment of a Hydropower Plant: A Case Study in Lower Mardi River, Nepal
1065.5
1065
1064.5
1064
1063.5
1063
1062.5
0.0 1.0 2.0 3.0 4.0 5.0 6.0
H | 107
Pokhara University, School of Engineering
APPENDIX B -
DESIGN DRAWINGS
M
ard
iR
ive
r
M
ard
iR
ive
r
M
ar
di
Ri
ve
r
SCHOOL OF ENGINEERING
DSGN.
CHKD.
21.78
Trash Rack
River Flow U/S Stone apron
River Flow
D/S Stone apron
(M30 design ) (M30 design)
Way
to S
and
Trap
SCHOOL OF ENGINEERING
DSGN.
CHKD.
28.24
RL1099.1m
RL1099m
14.00
RL1095m
RL1094.34m
61°
RL 1090.1
RL 1089.59m
DSGN.
CHKD.
0.20
RL 1094.33m
4.25
RL 1090.08m
1.86
0.30
Connecting Channel
1120 1120
1110 1110
1100 1100
1090 1090
1092.269
1097.987
1097.454
1096.566
1096.482
1096.327
1096.139
1096.864
1096.742
1097.770
EXISTING
0.000
LEVEL (m)
0+000.00
0+010.00
0+020.00
0+030.00
0+040.00
0+050.00
0+060.00
0+070.00
0+080.00
0+090.00
0+100.00
CHAINAGE (km)
DSGN.
CHKD.
RL 1094.33m
1090 RL 1090.08m
1090 1100 1100 1100 1100
RL 1094.33m
RL 1094.33m
DATUM 1060
DATUM 1070 DATUM 1070
1060 1070 1070
1096.749
1096.686
1096.199
1092.280
1089.864
1096.862
1094.893
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
5.00
5.00
5.00
0.02
5.00
5.00
5.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
1110 1110
1110 1110
1110 1110
1100 1100
1100 1100
RL 1094.33m
RL 1094.33m
1100 1100
1090 RL 1090.08m
1090 RL 1090.08m
RL 1094.33m
1090 1090
1090 RL 1090.08m
1090
1080 1080
1080 1080
1080 1080
DATUM 1070 DATUM
1070 1070
1070
DATUM
1096.329
1096.139
1095.949
1070
1096.751
1096.742
1096.361
1070
EXISTING LEVEL (m)
1098.065
1097.338
1096.286
EXISTING LEVEL (m)
EXISTING LEVEL (m)
5.00
0.00
5.00
5.00
0.00
5.00
DISTANCE (m) DISTANCE (m)
5.00
1.53
5.00
DISTANCE (m)
0+060.00 0+080.00
0+099.96
SCHOOL OF ENGINEERING
DSGN.
CHKD.
Overflow Part
Slope 2%
609.0430
X X
Slope 2%
Operator Building
SCHOOL OF ENGINEERING
DSGN.
CHKD.
RL 1093.39m
RL 1092.47
0.50
NSL
9.52
14.02
1:1 1:1 1:1 1:1
2.60
RL 1079.97m
60°
0.60 0.50
0.50 0.50
2.60 2.60 2.60 2.60
12.90
SCHOOL OF ENGINEERING
DSGN.
CHKD.
LEVEL (m)
EXISTING
1070
1080
1090
1100
1110
0+000.00 1090.261
0+020.00 1089.026
RL 1090.96m
0+030.00 1088.926
RL 1093.05m
0+040.00 1088.768
0+050.00 1088.116
0+060.00 1087.590
0+070.00 1086.713
0+080.00 1085.841
0+090.00 1085.320
0+100.00 1084.799
0+110.00 1084.277
0+120.00 1083.756
0+130.00 1084.694
0+140.00 1086.221
L-section of Headrace channel
0+150.00 1086.373
0+160.00 1086.525
0+170.00 1086.640
0+180.00 1086.755
0+190.00 1087.339
0+200.00 1087.923
0+210.00 1087.719
0+220.00 1087.515
0+230.00 1087.310
0+240.00 1087.106
0+250.00 1086.901
0.4
0+260.00 1086.528
0+270.00 1086.070
0+280.00
0+290.00
0+300.00
1085.369
1085.525
1084.608
Plan of Headrace Channel
0+310.00 1084.189
0+320.00 1083.770
0+330.00 1082.699
0+340.00 1082.240
0+350.00 1083.015
0+360.00 1083.791
0+370.00 1085.302
0+380.00 1086.667
0+390.00 1087.583
4.00
0+400.00 1088.498
0+410.00 1088.690
0+420.00 1088.883
0+430.00 1089.075
0+440.00 1089.267
0+450.00 1089.460
0+460.00 1089.652
0+470.00 1089.689
0+480.00 1089.726
0+490.00 1089.413
0+500.00 1089.100
0+510.00 1088.787
0+520.00 1088.474
0+530.00 1088.162
0.2
0+540.00 1087.849
0+550.00 1087.536
0+560.00 1087.223
0.6
0+570.00 1086.910
0+580.00 1086.597
0+590.00 1088.849
0+600.00 1089.602
0+610.00 1088.536
0.4 2.90
0+620.00 1086.801
0+630.00 1085.591
0+640.00 1084.382
DRG.NO.
CHKD.
DSGN.
0+650.00 1083.254
0+660.00 1082.086
SCHOOL OF ENGINEERING
0+670.00 1080.746
0+680.00 1079.406
0+690.00 1079.247
0+700.00 1079.169
0+710.00 1078.560
0+720.00 1077.951
DATE:- 2076/
0+730.00 1076.905
0+740.00 1076.136
0+750.00 1075.182
0+760.00 1074.670
0+770.00 1074.652
ALL DIMENSIONS ARE IN M.
0+780.00 1074.635
0+790.00 1078.525
0+800.00 1083.823
0+810.00 0.000
1070
1080
1090
1100
1110
1110 1110
1090.732
1090.461
1089.828
1089.930
1089.026
1088.689
1089.167
1088.768
1088.474
1088.333
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
2.33
8.00
8.00
0.00
8.00
8.00
0.00
5.92
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
1087.590
1086.902
1086.888
1085.841
1085.122
1085.845
1084.799
1083.752
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
0.00
8.00
8.00
0.00
8.00
8.00
0.00
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
DSGN.
CHKD.
1084.803
1083.756
1082.710
1087.235
1086.221
1085.665
1084.891
1088.239
1086.524
1084.810
EXISTING LEVEL (m) 8.00 EXISTING LEVEL (m) EXISTING LEVEL (m)
0.00
8.00
8.00
0.00
4.39
8.00
8.00
0.00
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
1087.176
1086.755
1085.771
1088.700
1087.923
1086.945
1088.292
1087.515
1086.738
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
3.42
0.00
8.00
8.00
0.00
8.00
8.00
0.00
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
DSGN.
CHKD.
1087.883
1087.106
1086.329
1087.326
1086.528
1085.717
1086.398
1085.646
1084.717
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
0.00
8.00
8.00
0.00
8.00
8.00
3.88
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
1084.608
1083.964
1084.777
1083.770
1083.120
1084.492
1082.240
1081.545
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
0.00
8.00
8.00
0.00
8.00
8.00
0.00
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
DSGN.
CHKD.
1084.687
1081.585
1080.721
1088.802
1088.500
1086.667
1084.654
1083.268
1089.187
1088.498
1088.211
1086.305
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
1.84
4.53
8.00
8.00
4.49
0.00
5.16
8.00
8.00
0.00
3.33
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
1088.883
1088.194
1089.956
1089.268
1088.557
1090.341
1089.652
1089.374
1087.931
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
0.00
8.00
8.00
0.00
8.00
8.00
0.00
3.23
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
DSGN.
CHKD.
1090.726
1090.161
1087.305
1091.110
1089.100
1086.680
1090.895
1088.474
1086.054
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
1.44
8.00
8.00
0.00
8.00
8.00
0.00
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
1087.849
1085.428
1089.644
1087.223
1084.803
1089.018
1086.597
1087.082
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
0.00
8.00
8.00
0.00
8.00
8.00
0.00
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
DSGN.
CHKD.
1090.564
1090.717
1089.602
1087.342
1089.199
1086.801
1084.919
1085.983
1085.111
1084.382
1082.773
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
3.80
0.00
8.00
8.00
0.00
8.00
8.00
3.63
0.00
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
1082.086
1080.524
1080.815
1079.723
1078.156
1080.765
1079.217
1077.239
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
0.00
8.00
8.00
2.26
8.00
8.00
0.20
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
SCHOOL OF ENGINEERING
DSGN.
CHKD.
1079.515
1078.430
1076.021
1077.742
1076.136
1074.365
1075.975
1074.670
1073.632
1073.295
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
1.98
8.00
8.00
0.00
8.00
8.00
0.00
6.36
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
1074.635
1072.988
1082.840
1083.823
1081.592
1083.706
1083.903
1084.897
EXISTING LEVEL (m) EXISTING LEVEL (m) EXISTING LEVEL (m)
8.00
4.62
0.00
8.00
8.00
0.00
8.00
8.00
0.00
8.00
DISTANCE (m) DISTANCE (m) DISTANCE (m)
DSGN.
CHKD.
Hand Rail
By pass structure
Headrace Pipe
Slope 1% 38.00
15000.0000
Slope 1%
Trash Rack
A
A
8500.0000
By pass pipe
Spillway
Overflow part
Sediment flushing pipe Spill Channel
Penstock pipe
Spill pipe
SCHOOL OF ENGINEERING
DSGN.
CHKD.
11260.6433
Handrail
Spillway
Trash Rack
9.48 Penstock pipe 10.84
Slope 1%
Sediment flushing pipe
Headrace Canal
62.50
30.00
SCHOOL OF ENGINEERING
DSGN.
CHKD.
Saddle support
SCHOOL OF ENGINEERING
DSGN.
CHKD.
CRANE
CONTROL BLOCK
1066.00
16.00
800
0.5
DOOR
DOOR
300
1.76 Ø
16
2-nos
1200.
1.80
500 0.50
T G T G
ROLLING SHUTTER
150 mm THICK
P.C.C.M-10
3300
2.560
2.50
3.00
350
150 mm THICK
P.C.C.M,-10
2 D/T GATES
SECTION 1-1
3.00
(SCALE 1:200)
SLOPE 0.0015
TAIL RACE
3.5
2
1
PLAN
0.20
2.00
0.30
3.66
SCHOOL OF ENGINEERING
Tailrace
SUBT. BY:- BCE,
DSGN.
CHKD.
AMOUNT
DESCRIPTION UNITS QUANTITY RATE
(Rs.)
WEIR
33837989.15
Bulk excavation m3 1653 140 231408
Structural excavation m3 6746 270 1821324
Fill / backfill m3 4199 150 629892
Total 574782040
Contingencies @ 3% 17243461
Grand Total (Rs.) 592025501
Grand Total (M. Rs.) 592.026
Grand Total (M. US $) 5.382
APPENDIX-D
PHOTOS