Professional Documents
Culture Documents
PMP Test: Download Full PDF Package Translate PDF
PMP Test: Download Full PDF Package Translate PDF
edu/39888335/Pmp_test
99+
Search
Download PDF Download Full PDF
Premium
Package Joao Translate PDF
TOOLS
Pmp test
Rajesh Kumar Dash
1 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
2 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
3 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
Page 4 of 52
Question number: 13
Which of the following would NOT be included in the Communication Management Plan?
You answered: A.
Question number: 14
Which of the following best describes the purpose of integrated change control on a project?
You answered: C.
Question number: 15
In which of the following processes would it be most helpful for you as a project manager to employ information gathering techniques?
You answered: C.
4 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
A Quality audits
B Inspection
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
C Cause and effect diagram
D Pareto chart
Question number: 17
You are a project manager overseeing the construction of a new shopping mall. Your team had compiled and reviewed zoning and building
regulations to help ensure that your project would not be interrupted by any regulatory bodies, however, the information reviewed was out of date.
As it turns out, you have unknowingly exceeded the new maximum height r estrictions for structures in that area. You must now seek a variance
from the local government authorities, and if it is refused, your project could be shut down. Which of the following could have helped avoid this
situation?
You answered: B.
Question number: 18
Two of your team members are arguing over a technical issue on your project. You suggest that they put their differences aside and offer to take
them both to lunch. Which conflict resolution technique did you use?
You answered: D.
A Withdrawal
B Compromise
C Collaborate/Problem Solve
D Smoothing
Question number: 19
You are working as a project manager for an advertising project. Your inputs include deliverables, work performance information, checklists, and
approved change requests. What PMBOK process are you working on?
You answered: A.
5 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
Process Group: Monitoring & Controlling process
Page 6 of 52
Based on the list of inputs provided the only possible answer is choice A, Perform Quality Control process. The checklists should have tipped you off that it involved
quality. Plus we need the deliverables and approved change requests during Perform Quality Control so that we can perform tests on them to make sure they were
completed correctly.
Question number: 20
You just delivered a product to your customer when you receive an email informing you that the end result is unacceptable. The customer says
that a crucial component is missing, but you know that component was not in the original plan. Also, the product passed all quality tests. How
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html
should you respond?
7/21/2019
You answered: C.
A Repair the product to include t he missing component at no charge to the customer, because the customer is always right.
B Perform the work and bill the customer for the added cost.
C Meet with the customer to document the missing component, and then issue a change request to complete the required
work.
D Inform the customer that since the product passed all quality tests and passed scope verification, it is complete.
Question number: 21
You are managing a project and a team member comes across a major risk. Based on the team member's assessment the risk has a fairly high
probability and impact of occurring. What should you do first?
You answered: D.
Question number: 22
You are working on a project for a non-profit organization and are putting together the schedule. You recall that you worked on a similar project
last year and decide to use the same activity list as a starting point and just make slight changes. What scheduling tool and technique are you
using?
You answered: A.
A Analogous estimating
B Decomposition
C Templates
Question number: 23
Which of the following best describes the primary purpose of the project charter?
You answered: B.
6 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
B It authorizes work to begin on the project
Page 7 of 52
C It completely describes the work to be done on the project
D It describes the business case and reason for doing the project
A Go to the accounting director's manager and ask for the senior resources you need.
D Call a meeting with the accounting director, so that you can explain more clearly the need for senior resources on your
project.
Question number: 25
You are working on a fixed price contract and have spent $120,000 so far out of a budget of $120,000. You estimate there is still another $20,000
of work to complete the project. Because you are under contract, your company will have to pay all remaining costs to complete the project.
Which of the following best describes this situation?
You answered: B.
Question number: 26
You are submitting a status report to your external customer. Which form of communication should you use?
You answered: B.
A Formal verbal
B Formal written
C Informal verbal
D Informal written
Question number: 27
You are the project manager overseeing the construction of a new aircraft carrier. The construction involves fitting various components together
at the shipyard, and it must be done in a particular order. Unfortunately, certain components have been assembled at the shipyard, but your
project team cannot install them because other necessary tasks have not yet been completed, and because you currently lack the resources
needed to install them. The components cannot be kept at the shipyard, and thus, you will incur substantial costs for moving and storing them
until they can be installed. You want to ensure that this doesn't occur again on this project, so you should carefully review which of the following?
7 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
until they can be installed. You want to ensure that this doesn't occur again on this project, so you should carefully review which of the following?
You answered: C. Page 8 of 52
A Requirements Documentation
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html
D Procurement Management Plan 7/21/2019
Process Group: Planning process
The problem here is one of sequencing activities. The components should not have been assembled so soon, as they cannot be installed nor can they be stored where
they are. The Project Schedule Network Diagram – an output of Sequence Activities – should be re-visited to verify that future activities are properly sequenced so
this problem does not re-occur.
Question number: 28
You are managing a datacenter infrastructure project. You have spent $250,000 out of a total budget of $600,000. You have completed 30% of
the work thus far, but according to the schedule you should have completed 40% of the work. All work items carry the same value. Which of the
following best describes the situation?
You answered: A.
Question number: 29
You are managing a complex project to overhaul a water treatment plant. You are trying to report key information to the stakeholders, but are
having trouble compiling all of the relevant data. You have multiple budget reports in various formats, some of which are out of date, and they are
housed in various locations. The work performance information is similarly scattered amongst various documents, and is difficult to interpret.
Which of the following would best assist you in communicating the key information to the stakeholders?
You answered: A.
A Performance Reporting
B Communications Technology
D Issue Log
Question number: 30
You are managing a project and one of your vendors submits a deliverable that you feel is incomplete. He disagrees and insists that his work is
done and refuses to do any further work on it. How should you handle this situation?
You answered: D.
C File a lawsuit to force the vendor to complete the work or pay you damages
Question number: 31
8 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
Question number: 31
Your team is reviewing the entire procurement process to look for successes and failures. What are you doing?
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
9 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
10 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
11 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
12 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
13 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
14 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
15 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
16 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
17 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
18 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
19 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
20 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
21 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
22 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
23 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
24 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
25 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
26 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
27 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
28 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
29 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
30 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
31 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
32 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
33 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
34 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
35 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
36 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
37 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
38 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
39 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
40 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
41 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
42 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
43 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
44 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
45 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
46 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
47 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
48 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
49 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
50 of 51 12/23/2022, 1:03 PM
(99+) Pmp test | Rajesh Kumar Dash - Academia.edu https://www.academia.edu/39888335/Pmp_test
About Press Blog People Papers Topics Academia Biology Job Board We're Hiring! Help Center
51 of 51 12/23/2022, 1:03 PM