You are on page 1of 1

INFORMATION OF FINAL BILL

PACKAGE-IV 09.08.2022
Target Date of
Sl. No. Items of FPS Current Status
Completion
RFI no and date to be
1 Final Bill & Bar Chart with Hard & Soft Copy Submitted
update
The Summary of Contractor’s Stage Payment claims for works as
2 Submitted
submitted in accordance with Clause 19.4.

3 The amounts received from the Authority against each claim. Submitted

Any further sums which the Contractor considers due to it from the
4 Submitted
Authority.

An IPC for those parts of the Final Payment Statement which are not in
5 dispute, along with a list of disputed items which shall then be settled in Submitted
accordance with the provisions of Article 26.

A Final Payment Certificate in accordance with Clause 19.15 if there


6 Submitted
are no disputed items.

7 Completion Certificate Submitted

8 Maintenance Manual Submitted

9 Environmental Audit Report Submitted

10 Road Safety Audit Report Submitted

11 Final Status of Applicable Permits Submitted

12 As-Built-Drawings of Highways & Structures complete in all respect. Submitted

13 Reports of Tests conducted for Completion as per Schedule-K

(a). Visual and Physical Test Submitted

(b). Riding quality Test Submitted

(C ). Tests for Bridges. Submitted


(d). Other Tests Submitted
14 Mix Design Reports (Highways & Structures) Submitted
15 Third Party Test Reports (any other tests) Submitted
16 NOC certificates of ROB (from Railway Department) NA NA
17 Statement of Royalty & Paid Challans Submitted
18 GST paid Challans Submitted
19 NCR’s Statement Submitted
20 Fly-Ash consumption details Submitted
21 Extension of Time (EOT) approval letters Submitted
22 Milestone Achievement letters Submitted
23 Statement of Borrow Area Submitted
24 List of Approval Drawings Submitted
25 Methodology of Highways & Structures Submitted
26 Correspondences related to COS Submitted
27 RFI Files with Numbering and proper ID Submitted
28 Copy of MPR and QPR Submitted
Soft scan copy of all
29 All Correspondences in chronological order
correspondance
Checking of Insurances, Performance Security Validity & Bank
30 Submitted
Guarantee for Advance Payment.