Final Bill Checklist - Pkg-4
Final Bill Checklist - Pkg-4
PACKAGE-IV 09.08.2022
Target Date of
Sl. No. Items of FPS Current Status
Completion
RFI no and date to be
1 Final Bill & Bar Chart with Hard & Soft Copy Submitted
update
The Summary of Contractor’s Stage Payment claims for works as
2 Submitted
submitted in accordance with Clause 19.4.
3 The amounts received from the Authority against each claim. Submitted
Any further sums which the Contractor considers due to it from the
4 Submitted
Authority.
An IPC for those parts of the Final Payment Statement which are not in
5 dispute, along with a list of disputed items which shall then be settled in Submitted
accordance with the provisions of Article 26.