PROJECT SITUATION

DATE : Thursday, 20th October 2022

LOCATION
No
SULFINDO - PROJECT WIKA CIKAMPEK - PROJECT WIKA KULONPROGO - PROJECT CREC KM 132 - PROJECT BAYAH - PROJECT JATILUHUR - RENTAL WEDA BAY - RENTAL PALEMBANG - RENTAL SAMARINDA - RENTAL

Until now, already finish 113 titik, our team


Still can not working, because still check the Today, can not working, the water supply is The 1st hole, depth is 14,10m (07-10-2022)
1 Yesterday, 22 titik left not finish will finish 5 titik again, after that we should The machine still broken, not working. D050 working half day only, until 12.00am.
hole with metal detector not enough. and now (20-10-2022) become 12m. Today, borrow the dinamo stater from Mr.
do routine maintenance for all machine
Kang's friend.
Today, 2nd hole depth 10m, stop 'cause have
Water tank already processing, around 2 days Also the water pump from WIKA not strong a religion activity at the school beside the site, Today, service EMB for sensor RPM start
2 Today, continue working D051 working like usual
can be finish enough it was finish at 12.30pm but now is rainy, can from 3pm The machine already start working from
not continue drilling. 13.00 pm

the rebar team, standby waiting the rebar from (Still discuss about this with echa, farghat, 1m-4m depth is landfill. 5m-10m depth is ex-
3 Ariyanto not working, 'cause he was sick.
sulfindo and vicky) paddy soft soil (black soil and sand soil)

The 1st hole, depth is 14,10m (07-10-2022)


4
and now (20-10-2022) become 12m.

DATE : Friday, 21th October 2022

LOCATION
No
SULFINDO - PROJECT WIKA CIKAMPEK - PROJECT WIKA KULONPROGO - PROJECT CREC KM 132 - PROJECT BAYAH - PROJECT JATILUHUR - RENTAL WEDA BAY - RENTAL PALEMBANG - RENTAL SAMARINDA - RENTAL
for the time, follow weda bay area
Move to south area to finish 24 titik, depth Yesterday, can not continue drilling, rainy and
1 Standby, waiting the rebar from Sulfindo. Preparing the water to start boring. Last night, instal the rebar. The machine still broken, not working. Start working 10.20 am D050-D051 Working normally like usual.
12m. the soil is collapse.
Need submersible pump, for now borrow
2 Waiting the checking the hole. Today start working 7am. Today, EMB Machine already can use. The chines people asking D050 do overtime
from WIKA first.
Yesterday, KMT already sent the rebar, but
3 Mr. Miko from Sulfindo refuse because the 10.33 concreting 1st hole Cleaning area for start drilling.
size is wrong.
4 Water tank will be finish on Sunday 13.22 concreting 2nd hole Start drilling titik 114 at 9.40 am
at 13.34 pm titik 114 depth 11 meters, then
15.37 start boring 3rd hole.
rainy.
18.11 drilling 3rd hole until 10 meters,
at 19.41 pm titik 114 depth 13 meters
continue tomorrow.
Need more steel plate because the ground
always sinks if passed by our machine.

DATE : Saturday, 22th October 2022

LOCATION
No
SULFINDO - PROJECT WIKA CIKAMPEK - PROJECT WIKA KULONPROGO - PROJECT CREC KM 132 - PROJECT BAYAH - PROJECT JATILUHUR - RENTAL WEDA BAY - RENTAL PALEMBANG - RENTAL SAMARINDA - RENTAL
for the time, follow weda bay area
Track's hose broken, chinese will help us to
at 09.25 install the rebar on titik 114.
take us to the city to fix it.