MARABA AL IRAQ AL KHADRAA

Incident Summary Report


For

Period: 2021-2023

Date of Reporting Recommendation


# Department Incident Description Responsibility Status Remarks
Incident Person Name Detail
Through the crossing of the road by  The operator needs a Site Supervisor Hussain Close
the telescopic forklift (reg. no: banksman to guide him abdulla
7545) the earth collapse under one through the path.
The operator of the tires. Because of the rain fall  Improving the lighting on the
1 21\11\2021 (Mohammed Operation that cause slipping for one of the location.
loaded pipes. The pipe slipped on a
Abdulhassan)  Safety Meeting with the staff
barrier nearby location and cause
and reminding all the operators
minor damage.
to prevent working on the not
settled locations.
On date: 21-03-2019, one of our  Take the patient to the hospital Site Supervisor Close
operator named Hussain Bunaian was for the treatment.
working in the field of South Rumaila
in front of the station 4, the operator
project manager fell down to the ground because of
2 21-03-2022 Operation
Marwaadel some medical problem, the
treatment given by the medical team
and the ambulance vehicle took him
to the hospital.

On Sep 24th 2020, the flatbed-head  Stopping all the head trucks Site Supervisor Ahmed Close
truck Actros (197199) which driven and conducting inspection for Ghadban project
by Maraba driver, was coming from the equipment's, the result and Manager Nada Khalid
south rumaila and heading the the action was below:
destination of North Rumaila. The o Stop work and get back
vehicle stopped and checked in CP the head trucks (140177,
G67 and there was some defects with 197199) to the Base of
the connection wires and the brake maraba to fix all the issues
supply line between the truck and founded in the inspection
the flatbed, further action done by and cover it with a backup
the team in ROO for reporting the head truck-flatbed.
issues. o Resume work for the
following equipment
3 24-Sep-2022 Checkpoint CP G67 Journey
(145817, 120288).
o After finishing the
maintenance it was
inspected by the HSE team
and resume to the
location.
 Aware the drivers to conduct
the inspection every day using
the daily checklist attached and
in case of finding any issue it's
should be reported to the
supervisor of the project and
it's not allowed to do any

Doc No. MIK-FM-21-01 Issue No. 1.0 Issue Date: 01 June 2018 Revision Date:
MARABA AL IRAQ AL KHADRAA
Incident Summary Report
mission.
 Checking with the supervisor
daily and get the inspection
report from the sites.
 Applying the monthly
inspection according to the HSE
procedure number (10)
(preventive maintenance.
4 On 24 of Feb. 2020 the contractor  Inspecting the saucing Site Coordinator (Nabaa Close
section machine operator (abdul machines for the contractor salman) , HSE
mutallib) faced some problem on the and so for these for MIK to be Department, Journey
valve of the equipment which was sure it's not facing same department.
keeping the black water inside. After a problem.
hard day work he faced the problem  No contractor approved to
27-2-2023 Operation Department. Journey and due to that the liquid dropped on work till he do the inspection
the ground causing pollution on the and success pass, also they
road on line no 84WQ1. most obligate to the periodic
inspection.
 All contractors signing a
commitment to protect and
care for the environment.
5 The flatbed was left in the location in  Escorting the vehicle back to Site Coordinator, HSE Close
Rumaila for a period of time and there the main base at MIK in Manager.
was a plan to transport it to another Burjesia and stop working it.
place in Ru346, the driver connect the  Replacing the flatbed and the
flatbed without doing the peruse head truck with another one
inspection and directly connect the good condition and inspected.
Operation
21 – 03 - 2023 Operation Department.
department
electrical cables and the air supply  Doing inspection immediately
after connecting the truck to the for all the flatbeds working in
flatbed. When he pass the CPG67 the the project and replacing any
crow there inspect the flatbed and equipment not satisfied.
found some defects and they made
the reporting to the operation dept.

6 On 7 of June, the driver of the head  Replacing the 5th wheel Operation department, Close
truck Actros (72336) reach the NPS  Inspecting the trucks of the HSE manager
base in Burjesia on morning, he was project for similar issues
aiming to connect the acid tanker by,  Request new 5th wheel tester
the driver reversed the truck to do the to inspect the 5th wheels In the
connection per the 5th wheel and king periodic inspection.
24/ 04 / 2023 Hussain ali, site supervisor Journey
pin connection procedure, he done the
connection successfully and then tried
to move forward but suddenly the
tanker break up connection with the
5th wheel of the truck.

Doc No. MIK-FM-21-01 Issue No. 1.0 Issue Date: 01 June 2018 Revision Date: