JOB HAZARD ANALYSIS

Date: 12TH JUNE 2019 BRIEF BY REVIEW BY APPROVED BY

Prepared by: OCTAGON HSSE TEAM SIGNATURE

Company: OCTAGON Maju Holdings Sdn. Bhd NAME FARHE ZULHUSNI


Site Address: POSITION PROJECT EXECUTER HSSE SNR. EXEC
DATE 12TH JUNE 2019 12TH JUNE 2019

JHA Reference No.: JSA/OMHSB/MCDONALDS/014 JHA Review No.: 00


Making Predetermined JHA shall be verified and reviewed on site every day before performing the work

Description of work: Repainting McDonalds Pylon.

STEP
JOB STEP JOB STEP HAZARD JOB STEP CONTROL
NO
1.1 Other contractor may carry out their works that 1.1.1 Inform MCDONALDS representative and other contractors
Workers arrived at site &
introduce additional hazard to our works. working at site who may interfere with our works.
Supervisor/PIC notify MCDONALDS
1.1.2 Conduct toolbox meeting before start work.
1. representative about the work
1.2 Unsafe work conditions at site may endanger workers. 1.2.1 Everybody must conduct last minutes risk assessment at all
activity.
times.
1.2.2 No Work at Height allowed during rain.
Barricade the working area c/w safety 2.1.1 Make sure workers are wearing high visibility vest.
2. 2.1 Traffic flow may cause an accident
signage. 2.1.2 Flagman with baton to be available if there is traffic at site
3.1 Overlapping may cause trip, slip and fall 3.1.1 Make sure to isolate the hose properly, if crossing the main
Setup cable management for road required to install cable ramp
3.
compressor sander hose/electrical 3.2 Damaged electrical cable may cause electrocution 3.2.1 Make sure site in charge conduct visual inspection on cable
(if using electrical sander) 3.2.2 Ensure cable not laying on water containment
4.1 Obstructing traffic flow. 4.1.1 Refer the lifting plan regarding position skylift.
4.2 Workers hit by skylift. 4.2.1 Appoint flagman to control the traffic.
4.2.2 Wear high visibility vest all the times.
4.2.3 Workers are visible to the crane operator.
4. Position skylift at work area. 4.2.4 Clear signals are given to the crane operator.
4.2.5 Make sure Lift Plan is available and approved.
4.3 Reverse skylift while working. 4.31 Make sure the work load not exceed the SWL (Standard Work
Load).
4.3.2 Make sure base of skylift parking can support the load.
JOB HAZARD ANALYSIS

5.1 Worker falls from the sky lift bucket 5.1.1 Make sure the sky lift bucket is equipped with proper
guardrails.
5.1.2 Make sure workers are wearing safety harness and hook at
anchorage point.
5.1.3 Check the control devices: -
 Is overload warning device operational and tested?
 Is load indicator operational and tested
 Is boom angle indicator operational and tested
 Is hook’s safety catch in order?
Is the emergency STOP button being functional
5.2 Equipment may fall from bucket sky lift 5.2.1 No worker allowed to work under the sky lift when work at
Using the OCTAGON Skylift checklist
height is in progress.
to inspect the: - 5.2.2 Properly isolate and barricade the working area and do not
anybody is standing or working at the same area
 General Maintenance 5.3 Asset Damage while lifting using crane. 5.3.1
5. Make sure the work load not exceed the SWL (Standard
 Outriggers Work Load).
 Safety Devices 5.3.2 Make sure work area clear from obstruction.
 Hoist Devices 5.3.4 Check the documents before start work: -
 Is load chart fitted in cab
 Is boom in good condition
 Is PMA number marked clearly on skylift.
 Is PMA certificate copy in cab
 Is operating manual available at site office
 Is Maintenance record available and up to date
 Is the hoisting bucket in good condition and
maintain?

5.3.5 Make sure outrigger covered with proper base plate to


avoid the property damages.
6.1 Over reach may cause worker fall from height 6.1.1 Make sure worker wearing full body harness & 100% tie of
6.1.2 Ensure full supervision while work commence
6.2 Expose to chemical dust may cause breathing problem & 6.2.1 Make sure worker wearing safety glass
eyes irritation 6.2.2 Make sure worker wearing dust mask N95
Sanding work & repainting work of 6.3 Exposure in hot weather may cause worker suffer heat 6.3.1 Implement rotation system between work crew
6.
McD pylon using skylift stress 6.3.2 Ensure worker regularly to drink water
Materials bring up on sky lift may fall/drop object 6.3.3 Make sure all materials & tools bring up secure inside
bucket
6.3.4 Ensure grinder & painting spray attached with lanyard hose
6.4 Direct contact with chemicals may cause health problem 6.4.1 Make sure SDS available at site
7. Remove all debris from work area. 7.1 Debris thrown around may cause people to trip. 7.1.1 Make sure workers do housekeeping regularly.
JOB HAZARD ANALYSIS

Personal Protective Equipment (PPE) appropriate to the task at hand shall be worn/used at all times.
Tick box any PPE that applies to this job

ANY ADDITIONAL PPE APPROPRIATE TO THE TASK : Dust mask N95, full body harness

List required equipment / tools (e.g fire extinguisher, barricading / signs , hand tools, mechanical tools, plant etc.):
Hand Tools.
Wear Safety Google
Wear Face Mask.

The work crew acknowledges that they understand and will comply with the precautions listed above
WORKER & SUPERVISOR NAME DATE :

NAME: SIGNATURE :

NAME: SIGNATURE :

NAME: SIGNATURE :

NAME: SIGNATURE :

NAME: SIGNATURE :

NAME: SIGNATURE :