Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
I also reviewed documentation interrelated with accidents and incidents that had occurred over
the last 2 years whether any accidents were recurring or any incident was leading to accidents. I
also inspected the reason behind the absence of workers due to illness.
After communicating with the workers , observation of the site, accident, incident record
assessment and source of information which I had reviewed prior to the study of particular areas
helped me to assess necessary actions that were needed to be done
Hazard category Who might be harmed What are you already What further controls/actions are Timescales for
and hazard and how? doing? required? further actions Responsible
to be person’s job
completed title
(within …)
Hazardous labour, Supervisors, Personal Protective 1. Wet cutting should be practice 7 Days Site
Substance Visitor , and other Equipment is Supervisor
for engineering control of dust to
workers involved in the mandatory in these
Dust generated task dusty areas eliminate from ever becoming air
while concrete First-aid kit available born particle
cutting and Cutting of concrete and with proper trained
Concrete Grinding grinding of concrete for staff 2. Dust collector should be installed 1 Month Finance
electrical installation or Manager
in working areas
for another adjustment is
very dusty job in the 3. Welfare facility such as eye 1 Month Project
construction. Dry cut of Director
washer installed at workplace
these material release
dusts into working zone. 4. Proper Barricading should be 1 Month HSE
There is no specific Manager
installed in the working place
control measure for dust
controlling hence 5. Unauthorized entry should be 3 days
workers is breathing in Safety
banned
dusty air so it will lead Supervisor
lung cancer or short 6. Proper training of the staff 2 Days (5,6)
term irritation or may be
long term illness
condition.
Electricity Any skilled person using The electrical installation is in All risks are well-ordered in N/A N/A
Possible fault disorder equipment or progress meanwhile professional way so no further action
Portable electric installation on periodically inspection of required
equipment the site installed electrical facilities
like grinder after any changing in
machine The most harmful burn execution plan
,Welding ,electric shock ,lost time
plant injury or even death Main circuit breaker is
General while working with installed in the accessible
Electric disorder equipment area in case of emergency
Work Equipment All person involved in Proper training related to 1. Replace manual handled 14 Days Finance
and Machinery handling manually usage of work equipment is equipment with portable Manager
,power tools, and provided to all workers electric tools such as circular
Manual handled machine operators wood cutter etc.
tools ,power tools PPE to handle, manual, 2. To ensure safe condition of 7 Days Electrical
and machinery Close to worker power tool and machinery is the equipment proper Supervisor
facilitation centre provided to workers inspection and maintenance (2,3)
workers were performing is required
different activities with 3. Proper labelled instruction of 3 Days
manual handling tools the equipment should be
which is ot appropriate delivered to the workers
place to perform tasks 4. Proper space and proper 5 Days Safety
place to handle the work Supervisor
Manual operated tools equipment
without proper 5. Only Authorised person 7 Days
inspection and should allow to perform the Site
maintaince can cause task Supervisor
entrapments which may 6. Proper warning signs should 14 days (5,6
lead to ,cuts, abrasion, be available while work in
and organ damage progress
Vibration workers related to the Area barricade while working 1. Machinery related to 14 Days Site
All grinding and mixture ad grinding vibration should be used for Supervisor
concrete mixture activities Anti-vibrations gloves are limited time
machines activities Excessive use of provided
concrete mixture 2. Health surveillance program 1 Month Project
machine and grinding Workers are trained to use should be active Director
machine like disc cutter mixture machine and grinder
lead to hand arm 3. Adequate training to handle 7 Days Site
vibration such as vibrating machineries Supervisor
vibration white finger
4. Proper risk assessment carry 5 Days Safety
Vibration could cause out Supervisor
pain or permanent (4,5)
disability 5. Proper inspection of all 1 month
vibrating equipment’s
Movement of People All workers on site Proper Barricade around the No further action is required N/A N/A
and Vehicles in especially those who parking zone
Workplace load and unload the
material from the Foot path are clearly marked
Parking of the vehicles
vehicles in parking Collision may cause Only licensed holder drivers
zone and losing of serious injuries and are allowed to drive the
vehicle controls fatigue of the victim vehicle
while moving in or
Load Handling Mobile crane Operators, Visual Inspection before 1. Provision of Proper Personal 3 Days Site
Equipment Forklift truck operators operating forklift truck and protective Equipment Supervisor
and other persons mobile crane 2. Check all lifting gears and all
Forklift Truck and involved in these necessary element like 1 Week
Mobile crane is used working Helpers and operators are 3rd shekels, D shekels sling web Safety
to lift and shifting the accomplishments party certified belt etc. before execution of Supervisor
material. Mobile the work (2,3)
crane used for Mobile crane used to Provide safety Induction 3. Provide proper training to all 2 Week
roofing material. shift the roofing material before execution of work skilled labour
at height ,if it fails due to Barricade areas where
Forklift truck was mechanical fault then it operation of forklift truck and 4. Safe operations designed
using to shift the may lead to serious mobile crane occurred before implementing 14 Days Site
material on the site injury ,property loss mechanical operations Supervisor
even fatigue Separate footpath for 5. Competency of forklift truck 5 Days (4,5)
pedestrian and mobile crane operator
Forklift truck is used for must check
rd
shifting the material, Authorized persons are 6. Inspected all machines by 3 7 Days Safety
Load was not secured allowed to enter in these Party Supervisor
and according to safe areas
limit of prescribed MSDS
of forklift truck .This
Moral
Moral, general legal and financial
It is moral duty of Banu Mukhtar Contracting to provide safely environment for their workers. The
arguments
basic focus of Banu Mukhtar is safety of their worker. All workers should have a safe environment
to complete their assigned Job. Our skilled and non-skilled person came to earn their wages not to
face any accident and any incidents. As Banu Mukhtar know the moral importance towards safe
returning of their employees cause ill health may a major impact on employees live and their
families .An illness may affect workers health mentally physically . An illness doesn’t affect only the
victims but it also mentally affect other his colleagues.
Its legally obligated for Banu Mukhtar to Fulfill ILO Legal requirement to protect their worker
under the ILOs safety and Health Convention (C-155)
Legal
Its employer responsibilities to follow all national and international applicable legal frame work.
Adopting legal framework for both (employees and Employer) is compulsory .Clients and National
Legal enforcement agencies main focus on legal framework. If any parties fail to adopt the legal
requirements then they may face penalties or to stop organization from further work. Risk should be
reduced so that’s employee can work in a safe manner. Legal procedure in any case of death
organization owner may have sentenced to death and revoking of organization license .ILO
convention C-155 and it recommendation (R 165) article implies on all organization to provide a
safe working environment. All machinery should be suitable for suitable tasks. Minimize all risk by
Job risk assessment. Environment for all working activities should be in safe manner
Action Purchasing and fixing dust collector system to remain safe from excessive inhalation of dust
particles which may have chronic effect on the workers.(Hazard Category. Hazardous substance
Dust)
Specific legal arguments OSHA standard (1926.57 C - Ventilation) narrated Design and operations for exhaust fans ,jets
,ducts ,hood and Separators .A dust Collector should be designed to maintain health safety
program active for the workers who are working in dusty areas .By installation of Dust collector
sufficient purified air will be available for the workers who are exposures to the dust. Dust collector
is used for safe disposal of dust and purifies the atmosphere area of working place. Its legal
responsibilities of employer to provide safe working environment
Consideration of likelihood AND severity The likelihood of illness in working place is high because workers are working in the exposure of
dust particles .Workers are at risks without proper safety measurement The likelihood of risks
range from acute to high risks .The severity of this risk is totally dependent upon inhalation in dusty
polluted . It may be short term risk like skin irritation and visual disruption. It may be long term risk
like Asthma, lung cancer etc.
From prescription of risk the severity may be described in four stages due to dust as following :
When measuring the severity risk are categorized in 4 different phase
Action Safe working platform for working at height and third party inspection certificate by scaffolding
inspector ( Hazard Category work at Height)
Specific legal arguments The international labour organization have a clear recommendation upon occupational safety and
health (R164) part of C-155.Part IV clearly mentioned that undertaking organization must
Provide and maintain workplace ,machinery and equipment ,which should be safe and
practicable for the assigned task
Meanwhile Banu Mukhtar also adopted country legislation where ILO recommendation are part of
national law enforcement agencies .At the moment Banu Mukhtar is following ILO recommendation
and country legislation.
Action Fire fight equipment like fire extinguisher ,sand bucket and fire hydrant system installation required
and it should be accessible for any emergency and applying hot work permit system ( Hazard
Category -Fire)
Specific legal arguments OSHA standard for Construction (29 CFR 1926) narrates fire protection and fire managing
regulation in the construction industry. Suitable fire control equipment shall be available in the
working zone and it should be maintained for immediate use. Country Fire department adopted
OSHA slandered as part of its legislation .Banu Mukhtar has legal responsibility to fulfil the
requirement of country fire department as well as OSHA slandered to continue their working
Planned review date/period with It is company policy to review all risks every year .Therefore I set risk assessment review data not
reasoning later than 6 Feburary 2023. However risk assessments have no legal time scale when you can
review your risk assessment. It is totally dependent upon organization demand and hence it can be
reviewed on following bases:
1. Risk assessment review required If there is any new working Procedure adopted by the
organization
2. Risk assessment review needed If there is any new legal procedure implemented by the
national enforcement agencies
3. Risk assessment is compulsory if there is any catastrophic event occurred organizations.
How the risk assessment findings will be I will arrange a meeting with Project Director, HSE Manager, and Site Engineer to brief about risks
communicated AND who you need to tell occurring on the sites and suggest actions about correction or minimizing the risk. I provided the
summary of all risks related to the construction sites to the Project Director .Meanwhile Agenda of
meetings, recommendations of meeting and conclusion points of the meeting will email to all
concerned person for record .Major risks should be conveyed to the all employees via tool box talk
or by posters. A summary of risk assessment and safe procedure of work place will be delivered
via social media page to all employees of firms
How you will follow up on the risk I will set a reminder of 15 days to remind the concerned department for implementation of
assessment to check that the actions suggested recommendations for corrections. I will talk to the responsible authorities about the
have been carried out status of procedure either they implemented or still the action is required .Meanwhile I will also
inquire if the actions is still pending, if the actions are still pending then I will try to know the reason
behind it .If there will be any problems to handle the situation ,I will discuss with project director
either there is any alternative solution of the actions .If these will be remain overdue for more than 3
month then an information will be conveyed to the Managing Director via Project director for
actions.