Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that the work is
my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while completing
all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant resources section for
this qualification on the NEBOSH website.
Part 1: Background
Plant operates 24 hours in 03 shifts. First shift starts from 8 am and ends at 4 pm. Second
shift starts from 4 pm and goes up to 12 am. Third shifts starts at 12 am and ends at 8 am.
During my visit to the plant site, I assessed raw material mixing tanks, Quality assurance
Description of the area to be included in the laboratory, Gallon filling machines, storage warehouses, admin offices, mess hall, Storage silos,
risk assessment paint batching section, and production floor.
HSE Officer is a responsible person for health and safety measures in the company. He takes
Any other relevant information care of the safety of the workers during day today working of the plant.
* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be factual.
After internet search, I went to the plant site of Wallcare Paint Industries Limited. I went into the
office of HSE Officer of the plant. Firstly I interviewed him, in which I asked about potential hazards
Then I went to HSE department of the company. There I started checking safety documents of
the company including HSE plan, accident record, audit reports, inspection reports, training
session record, ill health records and complaint book. Internet search, interviews on site
and HSE documents really helped me in identification of hazards of the workplace,
current control measures taken to reduce those hazards and any additional controls needed
to reduce those hazards completely.
I proposed some additional controls after reading ILO codes of practise, conventions
and recommendations. For example, I proposed replacement of damaged electrical supply wire
of the
grinder with the new one, as an additional control measure:
https://www.ilo.org/dyn/normlex/en/f?p=NORMLEXPUB:12100:0::NO: :P12100_ILO_CODE:C167
Hazard category Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
and hazard and how? required? further actions to person’s job
be completed title
(within …)
Health, welfare All the workers using toilets Hand wash soap was available in Proper sanitation, cleaning and 1 week Housekeeping
and working on site. all toilets. housekeeping of the toilets should Head
environment be done on regular basis
Toilet facilities at production Proper lights were installed in toilets.
Housekeeping site were very unhygienic Toilets should be properly sanitised 1 week Housekeeping
condition in toilets and poorly maintained, there with the help of phenyl or antiseptic Head
was very were mud spots in toilets, liquids
poor, which could besides this the toilet seats Hand wash basins should be installed in
cause outbreak were also wet, dirt was the toilets 2 weeks Finance
of disease. present in most of the Manager
toilets, also drainage system Soap and hand sanitizers should be
was poor few toilets were provided in the area 1 week Finance
over flowing, liquid soap Manager
bottles were empty, no toilet Proper supervision of the
roles were available. housekeeping process should be done on 1 week Housekeeping
regular basis Head
These unhygienic toilets
can result in outbreak of Proper training should be given to
disease and cross the workers about proper usage of 2 weeks HSE Officer
contamination in workers. toilet facility
Noise Area operators and Noise hazard signage were posted Acoustic barriers should be 1 month Finance
other workers will be in area. installed around roller mill to reduce Manager
During crushing suffered from loud noise. noise at source
and pulverizing Cabins were provided for operators.
operation, loud Workers were working near Proper maintenance and periodic 2 weeks Maintenance
noise was roller mill where raw inspection should performed Head
being produced by material was grinded into be grinders and cutters on
roller mill, which powder farm to use in
could cause further processing, the roller First aid box should be present in the area 2 weeks HSE Officer
hearing mill was producing high
impairment. noise because poor
maintenance and workers Safety signs should also be present in the 1 week HSE Officer
were not wearing any area
hearing protection.
Excessive breaks should be given to 2 weeks Adin Manager
This high noise can result the workers to reduce their noise
in ringing in eras, temporary exposure
or permanent hearing
Proper information, instructions and
loss, tinnitus or persistent HSE Officer
trainings should be given to the 2 weeks
tinging bells.
workers about noise control
Manual Handling Workers shifting different Cold drinking water was provided Chemical bags should be transported 1 month Finance
materials manually to workers. with the help of forklift truck or hand Manager
Workers were were exposed to the hazards. trolleys
manually shifting Robust Hand gloves were given
phthalic It was noted that in to workers involved in manual Adequate number of workers should 3 days Admin Manager
anhydride, talcum, production area workers handling. be allocated for the manual
aluminium powder were manually shifting transportation of the brine tank
and pigment phthalic anhydride, talcum, HSE Offi cer
bags which could aluminium powder and First aid box should be present in the 1 week
cause back pain pigment bags from area in case of emergency
storage warehouse to Acti vity
different processing Proper supervision of the activity 1 week Supervisor
containers and mixers. The should be provided by the management
task was very repetitive,
sometime very heavy load Proper practise sessions and HSE Officer
is lifted exciding safety limit training should be given about how to 2 weeks
allowed for manual handling perform manual handling safely
and lifting posture of most
of the workers were Necessary personal protective equipment HSE Officer
incorrect. should be given to the workers 2 weeks
Electricity Worker using cutting grinder All power tools were being Replace that damaged supply wire of 3 weeks Electrician
can get harmed. inspected every month and putted the grinder with the new wire
Supply cable prop tags and color cods.
of cutting It was noted that a worker Perform temporary maintenance of 1 week Electrician
grinder was was using cutting grinder to Hand gloves were provided to the wire for the time being
damaged, which cut six inches diameter pipe workers.
on contact, could in utility area for tie in Install a circuit breaker in the circuit 1 week Electrician
cause severe of new connection with
electric shock existing pipe line, electric
cable of cutting grinder was Install emergency stop button to 3 weeks Maintenance
damaged from several pints the grinder Supervisor
and conducting wires were
exposed, wires was also Fix Earth wire of the grinder 1 week Electrician
plugged in socket directly
without proper plug.
First aid box must be placed in the area 2 weeks HSE Officer
This unsafe condition can
lead to fire and
electrocution resulting in Safety signs should be present in the area 1 week HSE Officer
property damage and
Learner number: Page 8 of
Learner
personal injuries like
Electricity may cause Safety signs should be provided at 2 weeks HSE Officer
electrocution, electrical shock, the place
arcing, fire, skin burn,
organ damage and deaths in Proper information and training 3 weeks HSE Officer
severe cases. sessions should be given to the
workers about electrical safety
Vibrations Workers and operators Compressors were installed Base of the compressor should be 2 weeks Finance
working around near by away from operator cabins. rebuilt to reduce vibration intensity Manager
Air compressor the compressors might
was causing get effected. Regular toolbox talk is being given Proper maintenance and regular 2 weeks Maintenance
high magnitude to the workers inspection of the compressor should Supervisor
of vibrations High magnitude of vibrations be done to reduce vibration level
which could were felt near heavy
cause muscle air compressor providing air Job rotation of the workers should 2 weeks Admin Manager
damage for pneumatic operations of be done to reduce worker’s exposure
plant, Bases of the blowers to vibration
were damaged also no Admin Manager
proper maintenance record Excessive breaks should be given to the 2 weeks
was available that’s workers to reduce their exposure to the
why compressor were vibration
producing high vibrations. HSE Officer
Proper instructions and training should 3 weeks
This might result in be given to the workers about vibration
muscle weakening, joint and
nerve damage of workers, also
it can
Slips and Trips All the workers Safety procedure of good All spillage from the floor should 1 week Housekeeping
performing their activities housekeeping was in place in be cleared regularly Head
Paint emulsion in the warehouse and paint storage area.
was spilled on other who might visit the Slip kit should be placed near 2 weeks Area Head
floor from pint storage area. Safety signs were present in the area emulsion spillage in warehouse
damaged paint
gallon in It was noted that in Absorbing mats should be placed 2 weeks Area Head
warehouse could product storage warehouse at spillage area
cause slip and Emulsion paint gallon was
fall and damaged due to poor Supervision of housekeeping should 1 week Housekeeping
respective injuries. stacking on one another be done Head
and due to emulsion paint
spillage on floor there are high
chances of slippage from very Proper trainings to deal with slip and 3 weeks HSE Officer
slippery floor. trip hazards should be given to the
workers
This might lead to Safety shoes and other related
accident resulting in injuries personal protective equipment should be 3 weeks HSE Officer
like bruises, broken bones, provided to the workers
paint inhalation, breathing
problem and
unconsciousness.
Specific legal arguments ILO conventions and recommendations make sure proper installation of technical devices to reduce noise in
workplace. For example:
R156 - Working Environment (Air Pollution, Noise and Vibration) Recommendation, 1977 (No. 156) says that;
“11. The employer should ensure the regular inspection and maintenance of machines and installations, with respect to
the emission of harmful substances, dust, noise and vibration.
12. The competent authority should, when necessary for the protection of the workers' health, establish a procedure for
the approval of personal protective equipment”.
https://www.ilo.org/dyn/normlex/en/f?p=NORMLEXPUB:1 2100:0::NO::P12100_INSTRUMENT_ID:312494
The control of Noise at work Regulations 2005 state that;
These recommendations and regulations are forcing Employer to reduce noise in workplace by installing
proper technical devices. Wallcare Paint Industries Limited fails to comply with these recommendations and
regulations.
Consideration of likelihood AND The likelihood of embracing effects and injuries from high level of sound is high. Because workers did not
severity possess ear muffs and ear plugs. There were no safety measurements for workers. There were no acoustic
barriers around roller mill to reduce noise. So likelihood of injury seemed high.
. types of injury or ill health
. number of workers at risk Severity can be explained after dividing into many stages. Four basic severity stages are given below;
. how often the activity is . Minimal (no injury)
carried out . Minor (first aid requiring injury)
. how widespread the risk is
. Major (long term hospital treatment injury and damage to the plant)
. Catastrophic (death to the workers and huge damage to plant property and equipment
Severity of the impactor injury caused by the noise pollution is major.
. Noise may cause temporary hearing loss, permanent hearing loss, noise induced hearing
loss (NIHL), ear drum damage, ringing in ears and ear pain. Most of these problems require
hospital treatment. So, severity level is major.
. Almost a hundred workers work in raw material mixing section and all are at risk of being
affected by the noise
. Roller mill is working 24/7. So, workers are exposed to the hazard during their shift timing (08
hours)
Specific legal arguments Some ILO conventions force Employer to provide safe electrical equipment to the workers.
Article 26 of ILO Convention 167 states that:
“1. All electrical equipment and installations shall be constructed, installed and maintained by a competent person,
and so used as to guard against danger.
2. Before construction is commenced and during the progress thereof adequate steps shall be taken to ascertain
the presence of and to guard against danger to workers from any live electrical cable or apparatus which is under, over
or on the site.
3. The laying and maintenance of electrical cables and apparatus on construction sites shall be governed by the
technical rules and standards applied at the national level.”
According to this ILO convention, Employer should provide and maintain safe electrical equipment.
Wallcare Paint Industries Limited is in non-compliance with this ILO convention.
Consideration of likelihood AND severity Likelihood of injuries and accidents due to damaged electrical wire is high. Workers are working carelessly
in the area. Workers do not have proper insulated personal protective equipment. Operator of the
. types of injury or ill health
machine is exposed to the hazards throughout his shift time. So, likelihood is quite high.
. number of workers at risk
. how often the activity is carried out Severity can be explained after dividing into many stages. Four basic severity stages are given below;
. how widespread the risk is . Minimal (no injury)
. Minor (first aid requiring injury)
. Major (long term hospital treatment injury and damage to the plant)
. Catastrophic (death to the workers and huge damage to plant property and equipment
Severity of the injuries caused by the electricity is catastrophic.
. Electricity may cause arcing, electric burns, electric shocks, electrocution, skin burns,
internal organ damage and death in certain cases. Most of the injuries need hospital
treatment but death makes severity level catastrophic.
. Total of 04 people were at risk. One fabricator and 03 helpers involved in the activity
. Activity was carried out for around 03 hours. So, workers were exposed to the hazard
for almost 03 hours
. Risk was spread only at the specific activity of maintenance in utility section
Specific legal arguments There are some ILO conventions which try to ensure installation of safety guards and missing parts
in machineries to make their working safer.
ILO convention 119, Article 6 states
“1. The use of machinery any dangerous part of which, including the point of operation, is without appropriate guards
shall be prohibited by national laws or regulations or prevented by other equally effective measures: Provided that
where this prohibition cannot fully apply without preventing the use of the machinery it shall apply to the extent that
the use of the machinery permits.
2. Machinery shall be so guarded as to ensure that national regulations and standards of occupational safety and
hygiene are not infringed”.
https://www.ilo.org/dyn/normlex/en/f?p=NORMLEXPUB:12100:0::NO::P12100_INSTRUMENT _ID:312264
ILO convention 155 (occupational safety and health convention) says that;
This ILO convention demands installations of safety guards on dangerous and exposed parts of the
machinery. Wallcare Paint Industries Limited does not conform to this ILO standards.
Consideration of likelihood AND severity Likelihood of injury and accident due to unguarded mixer is high. Workers are working near the mixer
without proper personal equipment. They are directly exposed to the propeller blades of the mixer. They are
. types of injury or ill health
not well trained to work in that situation. That’s why probability of the accident is high.
. number of workers at risk
. how often the activity is carried out Severity can be explained after dividing into many stages. Four basic severity stages are given below;
. how widespread the risk is . Minimal (no injury)
. Minor (first aid requiring injury)
. Major (long term hospital treatment injury and damage to the plant)
. Catastrophic (death to the workers and huge damage to plant property and equipment
Severity of the injuries is catastrophic.
. Drawing-in may cause cuts, bruises, broken bones, fractured bones, finger cutting, and
loss of body parts, head injury and death in some cases. Some of these injuries can be
cured in hospital but death takes severity level to catastrophic.
. Almost 25 workers were working near unguarded pigment mixer. So, they all were at risk
of injury
. As, pigment mixer is working continuously for 24 hours daily. So, workers are exposed to
the hazard almost 08 hours a day during their shift timing
. Risk of getting injury by unguarded mixer is present around the pigment mixer only
in production area
How the risk assessment findings will I will share my risk assessment findings to the responsible persons, HSE Officer and other officers in the
be communicated AND who you need to tell form of presentation. I will arrange a meeting with all management of the company and will present findings
of my risk assessment to them. I will convince them to complete additional recommended actions in time. I
will also share my risk assessment with them in the form of hard copy documents, emails, letters and
memos.
Findings of my risk assessment will also be communicated with the workers in the form of
announcements, toolbox talk, instructions, training sessions and notice board announcements. Risk
assessment findings will also be shared on the intranet of the company to which every worker has access.
If there are financial problems or some extra effort or money needed to complete the task, I will refer
to Finance Manager for help. If Finance Manager is unable to help in completion of tasks on time, then I
will meet with the Managing Director of the company for sources to complete the task in allocated time.