Unit IG2: Risk assessment

Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).

Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.

Part 1: Background
You should aim to complete this section in 150 - 200 words.
Topic Comments
Name of organisation* PECPL Construction & industrial Co. Ltd
Site location* COIMBATORE, INDIA
Number of workers 500 total Employees
For over 25 years, PECPL has been serving the rather challenging construction and
industrial need in the Coimbatore as one of the most respectful general contracting
companies. Since its inception, PECPL has provided a range of services including.
General Contracting, where it earned its “First Class” classification, Design &Build,
Operations & Maintenance, and Project Management.

PECPL has managed to serve the Aviation, Transport, Defense, Rail, and
General description of the organisation
Telecommunication, Water, and Energy industries and is currently working on one of the
most important projects in the history of GANDHI PURAM, COIMBATORE.
PECPL has two shift of working, day shift from 06:00AM to 17:00PM, night shift
from18:00PM to 05:00AM and general office staff is from 07:00AM to 16:00PM. All
worker sage is mostly between 22 to 50 Years old.
PECPL has Certified QMS ISO9001:2015, EMS ISO14001:2015, HSMS which
Complies with OHSAS ISO18001:2007&SRMS which complies with ISO26000:2010
Description of the area to be included in the The risk assessment will cover complete site inspection and Rail track installation of
risk assessment Gandhi Puram Metro Deep Under Ground Station 1F4/5A1.
The Project Manager is responsible for health and safety (who is directly reported to
Any other relevant information
Project director).

Learner number:00660718 Learner name: Sanjay Kumar S Page 1 of 9


* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be
factual.

You should aim to complete this section in 100 - 200 words.


Note: this section can be completed after you have competed your risk assessment.
I Carry out my risk assessment consulted different sites like also referred
HSG150(https://www.hse.gov.uk/pubns/books/hsg150.htm) for gaining in formation. I also get
some information from ILO

I visit to PECPL company site meet with HSE Manager and he refer me to HSE Officer
for site inspection. The officer gives me site visit, after that he give me some previous
Outline how the risk assessment was record of accident happening onsite from different hazards. I have spoken to HSE
carried out this should include: Officers, Engineers and workers about their workplace condition, health, and safety
 sources of information consulted; management system of the organization. Identified the hazards by observing workers
were working in unsafe condition, Unsafe movement of vehicles, found some water
 who you spoke to; and
accumulation and chemical spillage on site. And some near misses happened on the
 how you identified:
spot.
- the hazards;
- what is already being done; and Some actions were already taken but it was not satisfactory to ensuring health and
- any additional controls/actions safety to the workers. Some of the necessary actions was missing
that may be required.
atsitewhichmayleadtoworkersseverinjuriesanddamagepropertyorequipment.

Following the inspection, I referred back to the notes that I made during inspection and
source of information that I had already reviewed to help me to decide on any additional
control measures of unsafe condition, unsafe movement of vehicles and workers, water
accumulation, and for chemical spillage that were needed.

Learner number:00660718 Learner name: Sanjay Kumar S Page 2 of 9


Part 2: Risk Assessment

Organisation name: PECPL Construction & industrial Co. Ltd


Date of assessment: 08-APRIL-2022
Scope of risk assessment: To find the risk and hazard regarding activity and to take control measure and remedial measures to avoid any
accident

Hazard category Who might be harmed What are you already What further controls/actions are Timescales for
and hazard and how? doing? required? further actions Responsible
to be person’s job
completed title
(within …)
Vibration Correct specific power tools 1 week Execution in
Hazard Workers, supervisor, Safe usage of power tools including Gun, Hilti, and Vibrator charge
electrician, technician, training conducted. Machine used for their relevant
Usage of tools helpers, this is will be operations to be monitored
which causes happen due
Hand-Arm continuous usage of
vibration Gun, Hilti, Vibrator, Inspection of gun, Hilti and Safe operation procedure and
vibrator machine had been method statement required and 2 weeks HSE
Syndrome(HAVS and other electrical
) tools(which produce conducted prior to start the need to be followed. Manager
(i.e. Drilling vibration). work.
machine,
chipping hammer Usage and exposure Strict supervision made
available for identifying the Special training required for the Equipment
machine,etc.) to vibration causing 1 week
risk and hazard and to safe uses of vibrator or such in charge
tools will result in
Tingling nature in the control them in safe power
finger, numbness in manner
finger, losing of Physical fitness and calibration
certificate required for the power Procurement
strength and grimness Risk assessment has been 1 Month
tools. manager
due to reduction in implemented and followed,
dexterity.
Weekly inspection and

Learner number:00660718 Learner name: Sanjay Kumar S Page 3 of 9


Hazard category Who might be harmed What are you already What further controls/actions are Timescales for
and hazard and how? doing? required? further actions Responsible
to be person’s job
completed title
(within …)
maintenance team required for
frequent inspection and Site
Provided the mandatory maintenance. 1 week Engineer
PPE to avoid vibration
hazards. As per Indian Standard only
personal protective equipment
required for the specific task. Procurement
2 weeks manager

Learner number:00660718 Learner name: Sanjay Kumar S Page 4 of 9


Hazard category Who might be harmed What are you already What further controls/actions are Timescales for
and hazard and how? doing? required? further actions Responsible
to be person’s job
completed title
(within …)

Learner number:00660718 Learner name: Sanjay Kumar S Page 5 of 9


Hazard category Who might be harmed What are you already What further controls/actions are Timescales for
and hazard and how? doing? required? further actions Responsible
to be person’s job
completed title
(within …)

Learner number:00660718 Learner name: Sanjay Kumar S Page 6 of 9


Part 3: Prioritise 3 actions with justification for the selection
Suggested word counts
Moral and financial arguments for all actions: 300 to 350 words
For EACH action:
Specific legal arguments: 100 to 150 words
Likelihood AND severity: 75 to 150 words
How effective the action is likely to be in controlling the risk: 100 to 150 words

Moral, general legal and financial arguments for ALL actions

Moral, general legal and financial


arguments

Justification for action 1

Action

Specific legal arguments

Consideration of likelihood AND severity


How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that you
indicated in your risk assessment;
and
 whether you think the action will fully
control the risk.

Learner number:00660718 Learner name: Sanjay Kumar S Page 7 of 9


Justification for action 2

Action

Specific legal arguments

Consideration of likelihood AND severity


How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that you
indicated in your risk assessment;
and
 whether you think the action will fully
control the risk.

Justification for action 3

Action

Specific legal arguments

Consideration of likelihood AND severity


How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that you
indicated in your risk assessment;
and

Learner number:00660718 Learner name: Sanjay Kumar S Page 8 of 9


 whether you think the action will fully
control the risk.

Part 4: Review, communicate and check


Suggested word counts for each section:
 Planned review date or period and reasoning for this: 50 - 100 words
 How the risk assessment findings will be communicated and who needs to know the information: 100 - 150 words
 Follow up on the risk assessment: 100 - 150 words.

Planned review date/period with


reasoning
How the risk assessment findings will be
communicated AND who you need to tell
How you will follow up on the risk
assessment to check that the actions
have been carried out

Learner number:00660718 Learner name: Sanjay Kumar S Page 9 of 9