Professional Documents
Culture Documents
Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You mustrefer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment.Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
Load Handling Workers who are working PPEs were provided to 1. Workers working under the 1 day Project
Equipment under the suspended load all the workers working suspended load must be Manager
and trespassers, visitors under the suspended evacuated from under the (1-5)
Crane operation was can be harmed. load. suspended load and area must
going on for be barricaded. Safety
installation of 14” and As Workers were working Work permit was issued Manager
12ft length poles but under the suspended load for lifting activity. 2. Crane operator must be trained 2 weeks (3,5)
load was not carried it can be fall and slip and skilled and he should be 3rd
by crane operator through the slings as party certified so can operate the
Manual Handling Workers who are carrying PPEs (coverall, safety 1. Cement bags must be off-loaded 1 week Project
the cement bags from shoes, safety helmet) by using fork lifter truck by manager
Cement bags were trailer can be harmed. were provided to all the putting pilots under the bags. (1-5)
Electricity Excavator operator and Excavation work permit 1. Underground cables and lines 2 weeks Project
other work related workers was issued. must be identified by using area manager
Excavator was and water users can be drawing before the commence of (1-5)
Health welfare and Workers who are working PPEs were provided to 1. There must be elimination of 2 days Project
Work environment in hot weather conditions all the workers working work in hot weather conditions if manager
can be harmed. in work site. reasonably possible or there (1-5)
Construction work must be stop of work during
was going on in As workers were working Temporary rest shelters peak temperature. Site
adverse and hot in hot weather there can were provided to take 2. There must be monitor Engineer
Hazardous Workers who are doing MSDS (material safety 1. Mixing must be done in mixing 1 month Project
substance the job by hand can be data sheet) was tank and agitator must be manager
harmed. provided of paints. installed inside the tank for ( 1-5)
Workers were mixing agitation it will eliminate the
the oil based paints As workers were mixing human involvement to some
with kerosene oil by the paint manually without extent thus will minimize the risk. Site Engineer
hand without wearing wearing Proper PPEs it (1,3)
PPEs (gloves, mask, can cause eyes irritation, 2. There must be proper PPEs 1 day
and goggles) and hand and face infection. (gloves, mask, and goggles) Material in
there was no provided to all the workers who charge (2)
Movement of People Workers who were Complaint against this 1. There must be trained banks 3 weeks Safety
and Vehicle passing and working in the matter was registered. man hired to control vehicles Manager
There was fork lifter way of the fork lifter might when there are present inside (2,4,5)
which was being used be get harmed seriously. the working area.
for placing the
cement bags from As there was no body 2. The storage area for cement
storage area to the present there to control bags and other building
working area and no and instructions for materials must be present near 1 month
banks man was controlling the vehicle it the working site to lower the Project
present there to can hit to someone and distance and hence the risk of Manager
3 months
Vibration Jack hammer operator Jack hammer operation 1. There must be elimination of air 1 Month Project
who was operating the permit was issued. operated jack hammer instead of manager
Workers were doing jack hammer might be this electrically operated jack (1-4)
digging work by using harmed. hammer must be used so can
jack hammer which reduce the vibration.
was doing abnormal As jack hammer was 2. If elimination is not possible then 1 weeks Safety
vibration due to high doing abnormal vibration it there must be regulator installed Manager
pressure of air. can cause ergonomics on pipe line such as valve (3,4)
hazards and can cause to through which can adjust the air
dislocate the arm and pressure and will minimize the
shoulder if jerk is more risk.
Action
Action
Action
Planned review date/periodwith I have planned the schedule to visit the organization after one year as per the policy of
reasoning organization. I will visit the organization on 8 th June,2022 for review of risk assessment or in case of
any accident/near miss. Reason for my visit will by to review the safety condition of the organization
which is according to the policy of organization.
How the risk assessment findings will be I have planned that I will arrange a meeting with supervisors and safety manager. I will talk them
communicatedAND who you need to tell about the condition of safety measures in organization. I will make them aware about the further
safety measure for improvement of safety condition. I will talk them to give them suggestion about
safety condition of organization. I will use all type of analysis for better understanding of the
authorities. I will upload my risk assessment findings on intranet system of organization. After this
discussion I will make workers aware about the hazards and risk assessment findings.
How you will follow up on the risk I will visit the organization personally and make observation about the safety conditions of
assessment to check that the actions organization. I will make keenly observations to get relevant information. I will notice either the
have been carried out safety measures are being followed and implemented in organization or not. If these control
measures are not implemented inside the organization then I will talk to the supervisors and
organization managmnet authorities to take serious step in this regard. I will talk to GM if these
persons will not follow my recommendations. I will make him aware about organization safety
condition and hazards which can cause accidents inside the organization.