Unit IG2: Risk assessment

Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).

Important note: You mustrefer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment.Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.

Part 1: Background

You should aim to complete this section in 150 - 200 words.


Topic Comments
Name of organisation* Alambani construction Company.
Site location* Jeddah, Suadi Arabia.
Number of workers 851
Alambani construction company is the one of leading construction companies of Saudi
Arabia. It was established in 1972 in Jeddah. It is serving Saudi Arabia with high quality
construction services in Saudi Arabia. It is famous for its designs , craftsmanship and
inspired life styles. Company is providing services in different companies with their
General description of the organisation
construction services at different places in Saudi Arabia. Services provided by the
company are infrastructures, aviation, housing projects, industrial projects and building
creator. There were three shifts for workers, Morning shift(6am-2pm), Evening shift(2pm-
10pm) and night shift (10pm-6am).
The area which is to be included in the risk assessment included the construction site of
Description of the area to be included in the
Project development which is Six flags World largest regional theme park company Near
risk assessment
Riyadh City.
Responsible persons for safety at site were safety manager, project manager and
Any other relevant information
supervisors.
* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be
factual.

You should aim to complete this section in 100 - 200 words.

Learner number: Learner name: Page 1 of 16


Note: this section can be completed after you have competed your risk assessment.
For completion of my risk assessment I visited the site but before visiting the site I studied
the HSE policy documentation and ILO health and safety documentation about
construction companies and then went to the site where construction work was carry out.
https://www.ilo.org/wcmsp5/groups/public/---ed_dialogue/---sector/documents/
Outline how the risk assessment was instructionalmaterial/wcms_161768.pdf
carried out this should include: https://www.hse.gov.uk/construction/
 sources of information consulted;
 who you spoke to; and
 how you identified: I visited the site at day shift. There were workers who were working for completion of that
- the hazards; construction project. I talked to the manager, project supervisor, safety manager, workers
- what is already being done; and and shift in charge these persons helped me for getting in and making my information
- any additional controls/actions clear about the health and safety and hazards. I also asked for health and safety policy of
that may be required. the company and saw either all the rules were being followed by the workers and
company. I observed there were many hazards which were unnoticed by the workers that
can cause serious incident. Safety condition of the organization is valuable but hazards
were present during my visit.
For control measures of the hazards I visited the following links:

Learner number: Learner name: Page 2 of 16


Part 2: Risk Assessment

Organisation name: Alambani construction Company


Date of assessment:
Scope of risk assessment: Construction site of Project development which is Six flags World largest regional theme park company Near
Riyadh City.
Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
Slip and trip Workers who were Safety signs and first 1. All walkways must be clean and 2 days Safety
working and walking near aid box is provided to safe for the passage of workers Manager(1,3,5
. Cement bags and walkways, visitors which workers. to avoid any kind of incident.
other construction came here to visit the site 2. There must be a separate place 1 month
material was placed and managers who were for the cement bags and waste Project
on site randomly and there for management should be removed from site on Manager(2,4)
workers were moving work might be get harmed. instance bases to eliminate the
through that area risk of tripping hazard.
As different hurdles are 3. There must be proper 4 days
present on the walkways housekeeping at site to lessen
which can cause workers the chances of tripping.
to trip and fall that can 4. Workers must be trained to
make the workers to get overcome such hurdles while
seriously or minor injured. working inside the organization 1 week
to lower the risk of hazard.
5. Proper lighting system should be
provided at walkways for
controlling the tripping accidents.
2 weeks
Fire Workers who were First Aid kit is given to 1. There should be a separate 3 weeks Safety
There was flame standing near the flame workers. place for flame cutting and manager(1,2,3
cutting process cutting machine might be workers exposure to that area

Learner number: Learner name: Page 3 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
continued for cutting get harmed. Fire extinguishers were must be stopped before the start
the big steel Poles available of activity to lower risk. Plant
and flammable As there are sparks Manager(4,5)
material was present emitting from the flame Fire Hydrants were also 2. There must be fire blankets
there like cement cutting machine which can installed. present there to control the 3 days
bags flammable harm the workers by sparks of fire for getting workers
concrete chemicals initiating the fire through harmed.
like glass wool and combustible materials
ordinary gypsum. them and make them
injured seriously like 3. Workers must be provided 4 weeks
burning and may also complete training for dealing
leads to fatality . with flame cutting machine.

4. There must be fire resistance


coveralls and glasses provided 2 days
to workers to save workers from
sparks of flame cutting process.

5. Alternative process like use of


circular saws should be used by 2 months
the organization for elimination
of this hazard.
Work at height Workers who are picking Permit to work at height 1. Workers must avoid going on 1 day Project
the material from edge of is given to the workers. unsafe places such as edge of Manager
Workers are roofs can be harmed . roof so can avoid from falling ( 1-5)
removing scaffolding Workers are provided thus will minimize the risk.
material from Top Workers can fall down as complete PPE for safety.
portion after there are no guardrails 2. There must be installation of Safety In
completing the around the roof which can . guardrails around roof so it can 1 week charge

Learner number: Learner name: Page 4 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
scaffolding work but leads to head ,back bone avoid from falling from roof it will (3,5)
there was no proper and leg broken minimize the risk.
system for offloading injuries ,falling from roof
material. also leads to fatality in
most cases. 3. Certified Safety harness of must 1 week Site
be provided to workers with life engineer
line so can avoid from falling and (1,4)
thus reduce the level of
probability.

4. Air bags must be provided it will 1 week


reduce the severity thus will
minimize the risk.

5. A safety net should be placed on 2 weeks


sides of roof to lower risk of
falling.

Load Handling Workers who are working PPEs were provided to 1. Workers working under the 1 day Project
Equipment under the suspended load all the workers working suspended load must be Manager
and trespassers, visitors under the suspended evacuated from under the (1-5)
Crane operation was can be harmed. load. suspended load and area must
going on for be barricaded. Safety
installation of 14” and As Workers were working Work permit was issued Manager
12ft length poles but under the suspended load for lifting activity. 2. Crane operator must be trained 2 weeks (3,5)
load was not carried it can be fall and slip and skilled and he should be 3rd
by crane operator through the slings as party certified so can operate the

Learner number: Learner name: Page 5 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
according to lifting down from one side i.e. crane and carry the load safely Rigging
plan and pipe was Load was not carried and efficiently. In-charge
shaking and down on according to lifting plan, (3,4)
one side and workers which can leads to head,
were working under back bone and leg 3. Lifting plan must be followed by
suspended load. injuries. rigging in charge so can do the 1 week
task safely.

4. Tag line should be attached to


the pipeline so can balance the
2 days
suspended load if required.

5. Health and safety plan must be


devised for lifting activity so can
do the job safely and according
to the lifting and safety plan. 1 month

Learner number: Learner name: Page 6 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
Mental illness Ill- Workers who are working Overtime was provided 1. Organization must plan 3 weeks
Health at site might be harmed. for more than 08 hours. complete safety analysis and Project
audits for inspection of health Manager
As there are only two shifts Workers were provided condition of workers. (1-4)
which make workers to be medical facility at site.
stressed due to load of 2. Shift pattern should be changed Safety
There was load of
work & mentally ill that will from two shifts to three shifts so 1 week Manager(1)
work on workers due
lead workers towards the load of work can be reduced
to only two shift
serious nervous system and man power must be
patterns and less
diseases and depression. increase according to the
man power. There activities.
was inflexible .
working hours for 3. Rest breaks should be provided 2 days
workers. to workers to lower the risk of
stress.

4. Workers should be provided


complete training about their 4 weeks
task to minimize the difficulties
during work.

5. There must be a plan for making 3 months


flexible hours for worker’s duties.

Manual Handling Workers who are carrying PPEs (coverall, safety 1. Cement bags must be off-loaded 1 week Project
the cement bags from shoes, safety helmet) by using fork lifter truck by manager
Cement bags were trailer can be harmed. were provided to all the putting pilots under the bags. (1-5)

Learner number: Learner name: Page 7 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
offloading manually workers.
from trailer and As workers are carrying 2. Cement bags must be transport Project
carrying to 10m away the bags manually it can First aid kit was by using trolleys instead of 2 weeks engineer
which is of 50 kg, leads to ergonomics provided. carrying manually. Trolleys must (1,2,4)
more than allowable hazards i.e.it can cause to be provided.
limit (25kg). back bone pain, hand and
leg ergonomics problems. Safety
3. If reasonably possible move the manager (5).
trailer near to the place where 1 day
cement bags are required.

4. Load must be divided by


carrying the cement bag by two
or more persons so it will 2 days
minimize the load on one person
and thus it will reduce the level
of risk.

5. Job hazards analysis must be


done for manual handling so can
estimate the maximum possible 1 month
hazards and control measures.

Electricity Excavator operator and Excavation work permit 1. Underground cables and lines 2 weeks Project
other work related workers was issued. must be identified by using area manager
Excavator was and water users can be drawing before the commence of (1-5)

Learner number: Learner name: Page 8 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
working at site for harmed. PPEs (Safety shoes. excavation work.
excavation work for Safety helmet, Goggles) Site
basement of building As electricity cables are were provided to 2. Excavation work must be stop Engine
but there was utility underneath there can be workers involved in on cabling and utility lines place 1 month (1,2,3)
lines(Electricity short circuit if excavator excavation work. if reasonably possible and
cables, water lines) cuts the cables and also alternate plan must be devised Safety
available in 6 ft. depth water lines are also Safety signs were and lines must be far away from Manger (4,5)
available there and water placed on work place. excavation work.
is good conductor of
electricity which can cause 3. If alternate place is not possible
electric shock to water than cable and water lines route 1 month
user and leads to fatality. must be change for avoiding the
hazards thus minimize the risk.

4. Excavator inspection must be


done and inspection certificate 1 week
should be available on site.

5. Health and safety plan must be 2 months


devised and executed so can
minimize the risk.

Health welfare and Workers who are working PPEs were provided to 1. There must be elimination of 2 days Project
Work environment in hot weather conditions all the workers working work in hot weather conditions if manager
can be harmed. in work site. reasonably possible or there (1-5)
Construction work must be stop of work during
was going on in As workers were working Temporary rest shelters peak temperature. Site
adverse and hot in hot weather there can were provided to take 2. There must be monitor Engineer

Learner number: Learner name: Page 9 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
weather conditions. be dehydration which can rest. continuous and sufficient supply 1 week (2,3)
leads to headache, of water should be available on
dizziness and site so workers can avoid from Site In
weakness .Also hot work dehydration. Charge (2,4)
environment can cause 3. There must be rest containers
physical discomfort due to available for workers with air 2 months Safety
heat stress. conditioners so workers can take Manger (5)
rest in comfortable environment
4. There must be frequent rest
breaks during work and tea or
other items should be served to 2 weeks
workers so can maintain the
energy to work.
5. There must be health and safety
plan devised for health and
welfare of workers working in hot 2 months
working environment.

Hazardous Workers who are doing MSDS (material safety 1. Mixing must be done in mixing 1 month Project
substance the job by hand can be data sheet) was tank and agitator must be manager
harmed. provided of paints. installed inside the tank for ( 1-5)
Workers were mixing agitation it will eliminate the
the oil based paints As workers were mixing human involvement to some
with kerosene oil by the paint manually without extent thus will minimize the risk. Site Engineer
hand without wearing wearing Proper PPEs it (1,3)
PPEs (gloves, mask, can cause eyes irritation, 2. There must be proper PPEs 1 day
and goggles) and hand and face infection. (gloves, mask, and goggles) Material in
there was no provided to all the workers who charge (2)

Learner number: Learner name: Page 10 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
emergency shower are mixing the paint manually by
installed. hand. Safety In
charge
3. Emergency shower must be ( 4,5)
installed on site if any infection 2 weeks
occur can wash immediately.

4. Training must be provided to all 2 weeks


the workers working on site so
can reduce the level of risk.

5. Job hazards analysis must be 2 months


done for hazards substance
before the activity start.

Movement of People Workers who were Complaint against this 1. There must be trained banks 3 weeks Safety
and Vehicle passing and working in the matter was registered. man hired to control vehicles Manager
There was fork lifter way of the fork lifter might when there are present inside (2,4,5)
which was being used be get harmed seriously. the working area.
for placing the
cement bags from As there was no body 2. The storage area for cement
storage area to the present there to control bags and other building
working area and no and instructions for materials must be present near 1 month
banks man was controlling the vehicle it the working site to lower the Project
present there to can hit to someone and distance and hence the risk of Manager

Learner number: Learner name: Page 11 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
control the vehicle. somewhere that can make hitting the vehicles with workers. 1,3)
the workers to get harmed
seriously by injuries on 3. Drivers for vehicles must be
head . hired on experience and training
bases to lower the chances of
accidents. 1 month

4. There must be separate ways


present for movement of such
vehicles to eliminate such risks.
3 weeks
5. Automatic upper lifting cranes
must be present for elimination
the risk of accident,.

3 months

Vibration Jack hammer operator Jack hammer operation 1. There must be elimination of air 1 Month Project
who was operating the permit was issued. operated jack hammer instead of manager
Workers were doing jack hammer might be this electrically operated jack (1-4)
digging work by using harmed. hammer must be used so can
jack hammer which reduce the vibration.
was doing abnormal As jack hammer was 2. If elimination is not possible then 1 weeks Safety
vibration due to high doing abnormal vibration it there must be regulator installed Manager
pressure of air. can cause ergonomics on pipe line such as valve (3,4)
hazards and can cause to through which can adjust the air
dislocate the arm and pressure and will minimize the
shoulder if jerk is more risk.

Learner number: Learner name: Page 12 of 16


Hazard category and Who might be harmed and What are you already What further controls/actions are Timescalesfor
hazard how? doing? required? further Responsible
actions to be person’s job
completed title
(within …)
than normal. 3. There must be proper periodic 2 Weeks
inspection of jack hammer so
can check the abnormalities of
jack hammer and fix it.
4. Job hazards analysis must be 3 Weeks
done for jack hammer operation.

Learner number: Learner name: Page 13 of 16


Part 3: Prioritise 3 actions with justification for the selection
Suggested word counts
Moral and financial arguments for all actions: 300 to 350 words
For EACH action:
Specific legal arguments: 100 to 150 words
Likelihood AND severity: 75 to 150 words
How effective the action is likely to be in controlling the risk: 100 to 150 words

Moral and financial arguments for ALL actions

Moral, general legal and financial Moral arguments:


arguments

Justification for action 1

Action

Specific legal arguments

Consideration of likelihood AND severity


How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that you
indicated in your risk assessment;
and
 whether you think the action will fully
control the risk.

Learner number: Learner name: Page 14 of 16


Justification for action 2

Action

Specific legal arguments

Consideration of likelihood AND severity


How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that you
indicated in your risk assessment;
and
 whether you think the action will fully
control the risk.

Justification for action 3

Action

Specific legal arguments

Consideration of likelihood AND severity


How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that you
indicated in your risk assessment;
and

Learner number: Learner name: Page 15 of 16


 whether you think the action will fully
control the risk.

Part 4: Review, communicate and check


Suggested word counts for each section:
 Planned review date or period and reasoning for this: 50 - 100 words
 How the risk assessment findings will be communicated and who needs to know the information: 100 - 150 words
 Follow up on the risk assessment: 100 - 150 words.

Planned review date/periodwith I have planned the schedule to visit the organization after one year as per the policy of
reasoning organization. I will visit the organization on 8 th June,2022 for review of risk assessment or in case of
any accident/near miss. Reason for my visit will by to review the safety condition of the organization
which is according to the policy of organization.
How the risk assessment findings will be I have planned that I will arrange a meeting with supervisors and safety manager. I will talk them
communicatedAND who you need to tell about the condition of safety measures in organization. I will make them aware about the further
safety measure for improvement of safety condition. I will talk them to give them suggestion about
safety condition of organization. I will use all type of analysis for better understanding of the
authorities. I will upload my risk assessment findings on intranet system of organization. After this
discussion I will make workers aware about the hazards and risk assessment findings.
How you will follow up on the risk I will visit the organization personally and make observation about the safety conditions of
assessment to check that the actions organization. I will make keenly observations to get relevant information. I will notice either the
have been carried out safety measures are being followed and implemented in organization or not. If these control
measures are not implemented inside the organization then I will talk to the supervisors and
organization managmnet authorities to take serious step in this regard. I will talk to GM if these
persons will not follow my recommendations. I will make him aware about organization safety
condition and hazards which can cause accidents inside the organization.

Learner number: Learner name: Page 16 of 16