Professional Documents
Culture Documents
Project Time Management
Project Time Management
IC
CHAPTER 6
T
PROJECT TIME MANAGEMENT
A
IM
Overview of Project Time Management
Plan Schedule Management
Define Activities
T
Sequence Activities
Estimate Activity Resources
L
Develop Schedule
Control Schedule
M
S
Learning Objectives
IC
After completing this chapter, you will be able to :
List the seven processes involved in Describe the Estimate Activity
Project Time Management Resources process, its inputs, tools
T
Describe the Plan Schedule and techniques, and outputs
Management process, its inputs, tools Describe the Estimate Activity
A
and techniques, and outputs Durations process, its inputs, tools
Describe the Define Activities process, and techniques, and outputs, with
IM
its inputs, tools and techniques, and special emphasis on three-point
outputs, with special emphasis on estimates
time decomposition Describe the Develop Schedule
T
Describe the Sequence Activities process, its inputs, tools and
process, its inputs, tools and techniques, and outputs
L
IC
Project Time Management includes the processes required to
manage the timely completion of the project.
T
A
IM
T
L
U
M
S
Overview of Project Time Management
Triple Constraint Model
IC
T
A
IM Quality
T
Scope
L
U
M
S
Overview of Project Time Management
Project Constraints
IC
T
Quality
A
IM
Quality
Scope
T
L
Scope
U
M
S
Process
IC
6.1 Plan Schedule Management
6.2 Define Activities
T
6.3 Sequence Activities
6.4 Estimate Activity Resources
A
6.5 Estimate Activity Durations
IM
6.6 Develop Schedule
6.7 Control Schedule
T
L
U
M
S
6.1 Plan Schedule Management
IC
Plan Schedule Management is the process of establishing the
policies, procedures, and documentation for planning,
T
developing, managing, executing, and controlling the project
schedule.
A
IM
T
L
U
M
ITTO
S
Plan Schedule Management
IC
INPUT TOOLS AND TECHNIQUE OUTPUT
T
1. Project management plan 1. Schedule management plan
2. Project charter
A
3. Enterprise environmental factors 1. Expert judgment
4. Organizational process assets 2. Analytical techniques
3. Meetings
IM
T
L
U
M
4.1 Project Time Management
Develop Project
S
Charter
• Project charter
IC
6.1 11.2
Plan Identify
Schedule Risks
Management
T
• Project management
plan
• Enterprise • Schedule
4.2 environmental factors
A
management plan
• Organizational
Develop Project process assets
Management 11.4
Plan
IM
Perform
Quantitative
6.4
Risk
Estimate
Analysis
6.2 Activity
Define Activities Resources
T
6.5
Estimate
L
Enterprise / Activity
Organization 6.3 Durations
Sequence
U
Activities
6.6
Develop
M
Schedule
S
Inputs
IC
1. Project Management Plan
The project management plan contains information used to
T
develop the schedule management plan which includes, but
is not limited to :
A
Scope baseline. The scope baseline includes the project
IM
scope statement and the work breakdown
structure (WBS) details used for defining activities,
duration estimation, and schedule management; and
T
Other information. Other scheduling related cost, risk,
L
IC
2. Project Charter
The project charter defines the summary milestone schedule
T
and project approval requirements that will influence the
management of the project schedule.
A
IM
T
L
U
M
Inputs
S
3. Enterprise Environmental Factors
IC
The enterprise environmental factors that influence the Plan
Schedule Management process include, but are not limited to :
T
Organizational culture and structure can all influence
schedule management;
A
Resource availability and skills that may influence schedule
IM
planning;
Project management software provides the scheduling tool
and alternative possibilities for managing the schedule;
T
Published commercial information, such as resource
productivity information, is often available from commercial
L
IC
4. Organizational Process Assets
The organizational process assets that influence the Plan Schedule
Management process include, but are not limited to :
T
Monitoring and reporting tools to be used;
A
Historical information;
Schedule control tools;
IM
Existing formal and informal schedule control related policies,
procedures, and guidelines;
Templates;
T
Project closure guidelines;
L
S
IC
1. Expert Judgment
Expert judgment, guided by historical information, provides
valuable insight about the environment and information from prior
T
similar projects.
A
2. Analytical Techniques
The Plan Schedule Management process may involve choosing
IM
strategic options to estimate and schedule the project such as:
scheduling methodology, scheduling tools and techniques,
estimating approaches, formats, and project management
T
software.
L
3. Meetings
U
IC
1. Schedule Management Plan
A component of the project management plan that
T
establishes the criteria and the activities for developing,
monitoring, and controlling the schedule.
A
IM
T
L
U
M
S
6.2 Define Activities
IC
Define Activities is the process of identifying and documenting
the specific actions to be performed to produce the project
T
deliverables.
A
IM
T
L
U
M
ITTO
S
Define Activities
IC
INPUT TOOLS AND TECHNIQUE OUTPUT
T
1. Schedule management plan 1. Activity list
2. Scope baseline 2. Activity attributes
A
3. Enterprise environmental factors 1. Decomposition 3. Milestone list
4. Organizational process assets 2. Rolling wave planning
3. Expert judgment
IM
T
L
U
M
Project Time Management
S
6.1
Plan Schedule
IC
5.4 Management
Create WBS • Schedule
management plan
• Scope baseline
T
6.2
A
Define
Activities
IM
• Activity list
• Organizational
• Activity attributes
process assets • Milestone list
• Enterprise
T
environmental factors
6.4
Estimate 6.6
Develop
M
Activity
Resources Schedule
S
Inputs
IC
1. Schedule Management Plan
A key input from the schedule management plan is the
T
prescribed level of detail necessary to manage the work.
A
2. Scope Baseline
IM
The project WBS, deliverables, constraints, and assumptions
documented in the scope baseline are considered explicitly
while defining activities.
T
L
U
M
S
Inputs
IC
3. Enterprise Environmental Factors
Enterprise environmental factors that influence the Define
T
Activities process include, but are not limited to :
A
Organizational cultures and structure,
Published commercial information from commercial
IM
databases, and
Project management information system (PMIS).
T
L
U
M
S
Inputs
IC
4. Organizational Process Assets
The organizational process assets that can influence the Define
Activities process include, but are not limited to :
T
Lessons learned knowledge base containing historical
A
information regarding activity lists used by previous similar
projects,
IM
Standardized processes,
Templates that contain a standard activity list or a portion of
an activity list from a previous project, and
T
Existing formal and informal activity planning-related policies,
L
IC
1. Decomposition
Decomposition is a technique used for dividing and
T
subdividing the project scope and project deliverables into
smaller, more manageable parts.
A
IM
T
L
U
M
S
Tools & Techniques
IC
2. Rolling Wave Planning
Rolling wave planning is an iterative planning technique in
T
which the work to be accomplished in the near term is
planned in detail, while the work in the future is planned at a
A
higher level.
3. Expert Judgment
IM
Project team members or other experts, who are
T
experienced and skilled in developing detailed project scope
statements, the WBS, and project schedules, can provide
L
IC
1. Activity List
The activity list is a comprehensive list that includes all
T
schedule activities required on the project.
A
2. Activity Attributes
IM
Activities, distinct from milestones, have durations, during
which the work of that activity is performed, and may have
resources and costs associated with that work.
T
L
3. Milestone List
A milestone is a significant point or event in a project.
U
M
S
6.3 Sequence Activities
IC
Sequence Activities is the process of identifying and
documenting relationships among the project activities.
T
A
IM
T
L
U
M
ITTO
S
Sequence Activities
IC
INPUT TOOLS AND TECHNIQUE OUTPUT
T
1. Schedule management plan 1. Project schedule network diagrams
2. Activity list 2. Project documents updates
A
3. Activity attributes 1. Precedence diagramming method
4. Milestone list (PDM)
5. Project scope statement 2. Dependency determination
IM
6. Enterprise environmental factors 3. Leads and lags
7. Organizational process assets
T
L
U
M
Project Time Management
S
6.1
6.2
Plan Schedule
IC
Define Activities
Management
T
• Milestone list
• Project scope
statement
A
6.3 Project
Sequence Documents
• Project documents
IM
Activities updates
• Organizational
T
process assets • Project schedule
• Enterprise network diagrams
environmental factors
L
6.6
U
Enterprise /
Organization Develop
Schedule
M
S
Inputs
IC
1. Schedule Management Plan
The schedule management plan identifies the scheduling
T
method and tool to be used for the project, which will guide
how the activities may be sequenced.
A
IM
2. Activity List
The activity list contains all schedule activities required on
the project, which are to be sequenced.
T
L
U
M
S
Inputs
IC
3. Activity Attributes
Activity attributes may describe a necessary sequence of events or
defined predecessor or successor relationships.
T
A
4. Milestone List
The milestone list may have scheduled dates for specific
IM
milestones, which may influence the way activities are sequenced.
IC
6. Enterprise Environmental Factors
Enterprise environmental factors that influence the Sequence
T
Activities process include, but are not limited to :
A
Government or industry standards,
Project management information system (PMIS),
IM
Scheduling tool, and
Company work authorization systems.
T
L
U
M
S
Inputs
IC
7. Organizational Process Assets
The organizational process assets that can influence the
T
Sequence Activities process include, but are not limited to:
project files from the corporate knowledge base used for
A
scheduling methodology, existing formal and informal activity
IM
planning-related policies, procedures, and guidelines, such
as the scheduling methodology that are considered in
developing logical relationships, and templates that can be
T
used to expedite the preparation of networks of project
activities.
L
U
M
S
Tools & Techniques
IC
1. Precedence Diagramming Method (PDM)
The precedence diagramming method (PDM) is a technique
T
used for constructing a schedule model in which activities are
represented by nodes and are graphically linked by one or
A
more logical relationships to show the sequence in which the
IM
activities are to be performed.
T
L
U
M
S
Tools & Techniques
IC
2. Dependency Determination
Dependencies may be characterized by the following
T
attributes: mandatory or discretionary, internal or external,
as described below.
A
IM
3. Leads and Lags
A lead is the amount of time whereby a successor activity
can be advanced with respect to a predecessor activity.
T
L
U
M
S
Dependency Determination
Types of Dependencies
IC
T
A
Mandatory
IM Discretionary
T
L
External
U
M
S
Tools and Techniques
Applying Leads and Lags
IC
Finish-to-start Task A Task B
T
+3-day
A
Finish-to-start lag
with a lag Task A Task B
IM Task A
−3-day
T
Finish-to-start
with a lead lead
L
Task B
U
Days 1 19
M
S
Outputs
IC
1. Project Schedule Network Diagrams
A project schedule network diagram is a graphical
representation of the logical relationships, also referred to as
T
dependencies, among the project schedule activities.
A
2. Project Documents Updates
IM
Project documents that may be updated include, but are not
limited to :
Activity lists,
T
Activity attributes,
L
Risk register.
M
S
Outputs
Project Schedule Network Diagrams
IC
A C D
T
A
Start Finish
B E
A
C
IM
T
E F G
H
Start Finish
L
D
U
B
M
S
Project Schedule Network Diagrams
Types of Network Diagrams
IC
A
T
AON (activity-on-node)
A
Start PDM (precedence
B diagramming method)
IM A
T
AOA (activity-on-arrow)
ADM (arrow Start
L
diagramming method)
U
B
M
S
Project Schedule Network Diagrams
Activity-on-Node Diagramming Method
IC
T
A
A C D
IM
Start Finish
B E
T
L
U
M
S
Activity-on-Node Diagramming Method
PDM Relationships
IC
Hardware Install
T
arrives hardware
Finish-to-start
A
Complete Obtain final
regression test sign-off
IM
Document tech. Begin logical Finish-to-finish
requirements design
T
Activate Remove
Start-to-start new router old router
L
Start-to-finish
U
M
S
Project Schedule Network Diagrams
Activity-on-Arrow Diagramming Method
IC
T
C
CD D
A
Start A Dummy
Start A CE Finish
IM B
BE
E
T
L
U
M
S
Project Schedule Network Diagrams
Graphical Evaluation and Review Technique
IC
T
A C D
A
loop
IM
Start Finish
B E
T
L
U
M
S
6.4 Estimate Activity Resources
IC
Estimate Activity Resources is the process of estimating the type and
quantities of material, human
resources, equipment, or supplies required to perform each activity.
T
A
IM
T
L
U
M
ITTO
S
Estimate Activity Resources
IC
INPUT TOOLS AND TECHNIQUE OUTPUT
T
1. Schedule management plan 1. Activity resource requirements
2. Activity list 2. Resource breakdown structure
A
3. Activity attributes 3. Project documents updates
4. Resource calendars 1. Expert judgment
5. Risk register 2. Alternative analysis
IM
6. Activity cost estimates 3. Published estimating data
7. Enterprise environmental factors 4. Bottom-up estimating
8. Organizational process assetsT 5. Project management software
L
U
M
Project Time Management
7.2
S
Estimate Costs
6.1
6.2
Plan Schedule
IC
Define Activities 9.1
Management
Plan Human
• Schedule Resource
11.2 management plan
• Activity cost Management
Identify Risks estimates
T
A
12.1
9.2 Plan
Acquire Project 6.4
Procurement
IM
Team Estimate Management
Activity • Project
Resources documents
updates
T
12.2
• Organizational
Conduct process assets Project
Procurements • Enterprise Documents
L
environmental • Activity resource requirements
factors • Resource breakdown structure
U
Enterprise / 6.5
6.6
Organization Estimate
Develop
Activity
Schedule
M
Durations
S
Inputs
IC
1. Schedule Management Plan
The schedule management plan identifies the level of
accuracy and the units of measure for the resources to be
T
estimated.
A
2. Activity List
IM
The activity list identifies the activities which will need
resources.
T
3. Activity Attributes
L
The activity attributes provide the primary data input for use
in estimating those resources required for each activity in the
U
activity list.
M
S
Inputs
IC
4. Resource Calendars
A resource calendar is a calendar that identifies the working
T
days and shifts on which each specific resource is available.
A
5. Risk Register
IM
Risk events may impact resource selection and availability.
IC
7. Enterprise environmental factors
The enterprise environmental factors that can influence the
Estimate Activity Resources process include, but are not limited to,
T
resource location, availability, and skills.
A
8. Organizational Process Assets
IM
The organizational process assets that can influence the Estimate
Activity Resources process include, but are not limited to :
Policies and procedures regarding staffing,
T
Policies and procedures relating to rental and purchase of
supplies and equipment, and
L
IC
1. Expert Judgment
Expert judgment is often required to assess the resource-
T
related inputs to this process.
A
2. Alternative Analysis
IM
Many schedule activities have alternative methods of
accomplishment.
T
L
U
M
S
Tools & Techniques
IC
3. Published Estimating Data
Several organizations routinely publish updated production
T
rates and unit costs of resources for an extensive array of
labor trades, material, and equipment for different countries
A
and geographical locations within countries.
4. Bottom-Up Estimating
IM
Bottom-up estimating is a method of estimating project
T
duration or cost by aggregating the estimates of the lower-
level components of the WBS.
L
U
M
S
Tools & Techniques
IC
5. Project Management Software
Project management software, such as a scheduling
T
software tool, has the capability to help plan, organize, and
manage resource pools and develop resource estimates.
A
IM
T
L
U
M
S
Outputs
IC
1. Activity Resource Requirements
Activity resource requirements identify the types and
T
quantities of resources required for each activity in a work
package.
A
IM
2. Resource Breakdown Structure
The resource breakdown structure is a hierarchical
representation of resources by category and type.
T
L
U
M
S
Outputs
IC
3. Project Documents Updates
Project documents that may be updated include, but are not
T
limited to :
A
Activity list,
Activity attributes, and
IM
Resource calendars.
T
L
U
M
S
6.5 Estimate Activity Durations
IC
Estimate Activity Durations is the process of estimating the
number of work periods needed to complete individual activities
T
with estimated resources.
A
IM
T
L
U
M
ITTO
S
Estimate Activity Durations
IC
INPUT TOOLS AND TECHNIQUE OUTPUT
T
1. Schedule management plan 1. Activity duration estimates
2. Activity list 2. Project documents updates
A
3. Activity attributes 1. Expert judgment
4. Activity resource requirements 2. Analogous estimating
5. Resource calendars 3. Parametric estimating
IM
6. Project scope management 4. Three-point estimating
7. Risk register 5. Group decision-making
8. Resource breakdown structure techniques
9. Enterprise environmental factors 6. Reserve analysis
10. Organizational process assets
T
L
U
M
Project Time Management
S
11.2
Identify Risks 6.4
6.1 6.2
Estimate
Plan Schedule Define
Activity
IC
Management Activities
Resources
• Activity list
5.3 • Activity attributes
Define Scope
T
• Project scope Project
statement
Documents
A
9.2
IM
Acquire Project
Team
6.5
11.2
Estimate Identify Risks
Activity
T
12.2 Durations
Conduct
• Activity
Procurements
L
duration
estimates
U
environmental
factors
S
Inputs
IC
1. Schedule Management Plan
The schedule management plan defines the method used
T
and the level of accuracy along with other criteria required to
estimate activity durations including the project update cycle.
A
IM
2. Activity List
The activity list identifies the activities that will need duration
estimates.
T
L
U
M
S
Inputs
IC
3. Activity Attributes
The activity attributes provide the primary data input for use
T
in estimating durations required for each activity in the
activity list.
A
IM
4. Activity Resource Requirements
The estimated activity resource requirements will have an
effect on the duration of the activity, since the level to which
T
the resources assigned to the activity meet the requirements
will significantly influence the duration of most activities.
L
U
M
S
Inputs
IC
5. Resource Calendars
The resource calendars influence the duration of schedule
T
activities due to the availability of specific resources, type of
resources, and resources with specific attributes.
A
IM
6. Project Scope Statement
The assumptions and constraints from the project scope
statement are considered when estimating the activity
T
durations.
L
U
M
S
Inputs
IC
7. Risk Register
The risk register provides the list of risks, along with the
T
results of risk analysis and risk response planning.
A
8. Resource Breakdown Structure
IM
The resource breakdown structure provides a hierarchical
structure of the identified resources by resource category
and resource type.
T
L
U
M
S
Inputs
IC
9. Enterprise Environmental Factors
The enterprise environmental factors that can influence the
T
Estimate Activity Durations process include, but are not
limited to :
A
Duration estimating databases and other reference data,
IM
Productivity metrics,
Published commercial information, and
T
Location of team members.
L
U
M
S
Inputs
IC
10. Organizational Process Assets
The organizational process assets that can influence the
T
Estimate Activity Durations process include, but are not
limited to :
A
Historical duration information,
IM
Project calendars,
Scheduling methodology, and
T
Lessons learned.
L
U
M
S
Tools & Techniques
IC
1. Expert Judgment
Expert judgment, guided by historical information, can
T
provide duration estimate information or recommended
maximum activity durations from prior similar projects.
A
IM
2. Analogous Estimating
Analogous estimating is a technique for estimating the
duration or cost of an activity or a project using historical data
T
from a similar activity or project.
L
U
M
S
Tools & Techniques
IC
3. Parametric Estimating
Parametric estimating is an estimating technique in which an
T
algorithm is used to calculate cost or duration
based on historical data and project parameters.
A
IM
4. Three-Point Estimating
The accuracy of single-point activity duration estimates may
be improved by considering estimation uncertainty
T
and risk.
L
U
M
S
Tools & Techniques
IC
5. Group Decision-Making Techniques
Team-based approaches, such as brainstorming, the Delphi
T
or nominal group techniques, are useful for engaging team
members to improve estimate accuracy and commitment to
A
the emerging estimates.
6. Reserve Analysis
IM
Duration estimates may include contingency reserves,
T
sometimes referred to as time reserves or buffers,
into the project schedule to account for schedule uncertainty.
L
U
M
S
Three-Point Estimates
PERT and Triangular Distribution
IC
PERT Triangular distribution
T
Mean = TO + 4TM + TP Mean = TO + TM + TP
6 3
A
Standard deviation = TP - TO Standard deviation = TP - TO
6 3
IM
Variance = σ2 Variance = σ2
Question
T
If you want to estimate the total project duration with a
95 percent confidence level, what is the range of project duration if
the sum of the critical path items equals 30 days and the standard
L
Answer
25 to 35 days
M
S
Three-Point Estimates
PERT and Triangular Distribution
IC
PERT Triangular distribution
T
Mean = TO + 4TM + TP Mean = TO + TM + TP
6 3
A
Standard deviation = TP - TO Standard deviation = TP - TO
6 3
IM
Variance = σ2 Variance = σ2
T
L
U
M
S
Outputs
IC
1. Activity Duration Estimates
Activity duration estimates are quantitative assessments of
the likely number of time periods that are required
T
to complete an activity.
A
2. Project Documents Updates
IM
Project documents that may be updated include, but are not
limited to :
Activity attributes; and
T
Assumptions made in developing the activity duration
estimate, such as skill levels and availability,
L
IC
Develop Schedule is the process of analyzing activity sequences,
durations, resource requirements, and
T
schedule constraints to create the project schedule model.
A
IM
T
L
U
M
ITTO
S
Develop Schedule
IC
INPUT TOOLS AND TECHNIQUE OUTPUT
T
1. Schedule management plan 1. Schedule baseline
2. Activity list 2. Project schedule
A
3. Activity attributes 1. Schedule network analysis 3. Schedule data
4. Project schedule network 2. Critical path method 4. Project calendars
diagrams 3. Critical chain method 5. Project management plan updates
IM
5. Activity resource requirements 4. Resource optimization techniques 6. Project documents updates
6. Resource calendars 5. Modeling techniques
7. Activity duration estimates 6. Leads and lags
8. Project scope statement 7. Schedule compression
9. Risk register 8. Scheduling tool
T
10. Project staff assignments
11. Resource breakdown structure
12. Enterprise environmental factors
L
S
6.1 6.4
11.2 Plan Estimate
Identify Risks Schedule
IC
Activity
Management Resources
• Risk register
• Schedule
management plan • Activity resource Project
requirements
5.3 6.2 • Resource breakdown
Documents
Define scope
T
Define structure
Activities 6.5
• Project scope statement
Estimate
A
Activity
7.2
9.2 Durations
Estimate
6.3
Acquire Project Sequence • Activity Costs
IM
Team Activities duration
estimates
7.3
• Project staff assignments
• Resource calendars Determine
Budget
12.2
T
• Project 12.1
Conduct
6.6 schedule Plan
Procurements Procurement
Develop
L
• Resource calendars Management
• Project
Schedule management plan
updates
U
• Enterprise
environmental Control Management
factors Schedule Plan
S
Inputs
IC
1. Schedule Management Plan
The schedule management plan identifies the scheduling
T
method and tool used to create the schedule, and how the
schedule is to be calculated.
A
IM
2. Activity list
The activity list identifies the activities that will be included in
the schedule model.
T
L
U
M
S
Inputs
IC
3. Activity Attributes
The activity attributes provide the details used to build the
T
schedule model.
A
4. Project Schedule Network Diagrams
IM
The project schedule network diagrams contain the logical
relationships of predecessors and successors that will be
used to calculate the schedule.
T
L
U
M
S
Inputs
IC
5. Activity Resource Requirements
The activity resource requirements identify the types and
T
quantities of resources required for each activity used to
create the schedule model.
A
IM
6. Resource Calendars
The resource calendars contain information on the
availability of resources during the project.
T
L
U
M
S
Inputs
IC
7. Activity Duration Estimates
The activity duration estimates contain the quantitative
T
assessments of the likely number of work periods that will be
required to complete an activity that will be used to calculate
A
the schedule.
IM
8. Project Scope Statement
The project scope statement contains assumptions and
T
constraints that can impact the development of the project
schedule.
L
U
M
S
Inputs
IC
9. Risk Register
The risk register provides the details of all identified risks and
their characteristics that affect the schedule model.
T
A
10. Project Staff Assignments
The project staff assignments specify which resources are
IM
assigned to each activity.
T
11. Resource Breakdown Structure
The resource breakdown structure provides the details by
L
IC
12. Enterprise Environmental Factors
The enterprise environmental factors include, but are not
limited to :
T
Standards,
A
Communication channels, and
Scheduling tool to be used in developing the schedule
IM
model. T
13. Organizational Process Assets
The organizational process assets that can influence the
L
IC
1. Schedule Network Analysis
Schedule network analysis is a technique that generates the
T
project schedule model.
A
2. Critical Path Method
IM
The critical path method, which is a method used to estimate
the minimum project duration and determine the
amount of scheduling flexibility on the logical network paths
T
within the schedule model.
L
U
M
S
Tools & Techniques
IC
3. Critical Chain Method
The critical chain method (CCM) is a schedule method that
allows the project team to place buffers on any project
T
schedule path to account for limited resources and project
A
uncertainties.
IM
4. Resource Optimization Techniques
Examples of resource optimization techniques that can be
used to adjust the schedule model due to demand and
T
supply of resources include, but are not limited to :
L
Resource leveling.
U
Resource Smoothing.
M
S
Tools & Techniques
IC
5. Modeling Techniques
Examples of modeling techniques include, but are not limited
T
to :
What-If Scenario Analysis.
A
Simulation.
IC
7. Schedule Compression
Schedule compression techniques are used to shorten the
T
schedule duration without reducing the project scope, in
order to meet schedule constraints, imposed dates, or other
A
schedule objectives.
8. Scheduling Tool
IM
Automated scheduling tools contain the schedule model and
T
expedite the scheduling process by generating start and
finish dates based on the inputs of activities, network
L
network analysis.
M
S
Tools and Techniques
Critical Path Method
IC
Calculates the longest time path (CP)
T
Calculates ES, EF, LS, LF
A
Determines minimum duration of project
IM
Determines scheduling flexibility (amount of float)
Uses a single duration time estimate
T
The critical path is the longest path in time through the
L
IC
5 4 3 = 12
T
A C D
A
Start Finish
IM
B E
6 2
T
L
If the task durations are as shown in this network
diagram, what is the critical path?
U
M
S
Critical Path Method
Critical Path
IC
5 4 3 = 12
T
A C D
A
Start Finish
IM
= 11
B E
6 2
T
L
If the task durations are as shown in this network
diagram, what is the critical path?
U
M
S
Critical Path Method
Critical Path
IC
5 4 3 = 12
T
A C D
A
Start Finish
IM
= 11
B E
6 2 =8
T
L
If the task durations are as shown in this network
diagram, what is the critical path?
U
M
S
Critical Path Method
Critical Path
IC
5 4 3 = 12
T
A C D
A
Start Finish
IM
= 11
B E
6 2 =8
T
L
If the task durations are as shown in this network
diagram, what is the critical path?
U
A-C-D
M
S
Critical Path Method
Critical Path (cont.)
IC
5 4 3
T
A C D
A
Start 6 Finish
IM
2
B T E
A-C-D
M
S
Calculating the Critical Path
Network Diagramming Conventions
IC
T
Task
description
(optional)
A
Pack up office
IM
Task ID B 1 Duration
ES LS
2 4
T
(early start) (late start)
EF 3 5 LF
L
(early finish) (late finish)
U
M
S
Critical Path Method
IC
Network Diagramming Example
• Task IDs
Task Desc. Task Desc.
• Duration
T
B 1 F 10
A
Task Desc. Task Desc. Task Desc. Task Desc. Task Desc.
IM
A 4 C 3 E 12 H 2 I 1
T
Task Desc. Task Desc.
D 7 G 8
L
Task Desc.
ID Dur.
ES LS
U
EF LF
M
S
Network Diagramming Example
IC
Forward Pass
Calculate:
• ES (early start) & Task Desc. Task Desc.
T
B 1 F 10
• EF (early finish)
A
Task Desc. Task Desc. Task Desc. Task Desc. Task Desc.
IM
A 4 C 3 E 12 H 2 I 1
T
Task Desc. Task Desc.
D 7 G 8
L
Task Desc.
ID Dur.
ES LS
U
EF LF
M
S
Network Diagramming Example
IC
Forward Pass
Calculate:
• ES (early start) & Task Desc. Task Desc.
T
• EF (early finish) B 1 F 10
4 5
5 15
A
Task Desc. Task Desc. Task Desc. Task Desc. Task Desc.
IM
A 4 C 3 E 12 H 2 I 1
0 4 7 19 22
4 7 19 21 23
T
Task Desc. Task Desc.
D 7 G 8
L
Task Desc. 7 14
ID Dur. 14 22
ES LS
U
EF LF
M
S
Network Diagramming Example
IC
Backward Pass
Calculate:
• LS (late start) & Task Desc. Task Desc.
T
• EF (late finish) B 1 F 10
4 5
5 15
A
Task Desc. Task Desc. Task Desc. Task Desc. Task Desc.
IM
A 4 C 3 E 12 H 2 I 1
0 4 7 19 22
4 7 19 21 23
T
Task Desc. Task Desc.
D 7 G 8
L
Task Desc. 7 14
ID Dur. 14 22
ES LS
U
EF LF
M
S
Network Diagramming Example
IC
Backward Pass
Calculate:
• LS (late start) & Task Desc. Task Desc.
T
• EF (late finish) B 1 F 10
4 9 5 10
5 10 15 20
A
Task Desc. Task Desc. Task Desc. Task Desc. Task Desc.
IM
A 4 C 3 E 12 H 2 I 1
0 0 4 4 7 8 19 20 22 22
4 4 7 7 19 20 21 22 23 23
T
Task Desc. Task Desc.
D 7 G 8
L
Task Desc. 7 7 14 14
ID Dur. 14 14 22 22
ES LS
U
EF LF
M
S
Network Diagramming Example
IC
Free Float
Calculate:
• Free float Task Desc. Task Desc.
T
B 1 F 10
4 9 5 10
5 10 15 20
A
Task Desc. Task Desc. Task Desc. Task Desc. Task Desc.
IM
A 4 C 3 E 12 H 2 I 1
0 0 4 4 7 8 19 20 22 22
4 4 7 7 19 20 21 22 23 23
T
Task Desc. Task Desc.
D 7 G 8
L
Task Desc. 7 7 14 14
ID Dur. 14 14 22 22
ES LS
U
EF LF
M
S
Network Diagramming Example
IC
Free Float
Calculate: 5 5
• Free float Task Desc. Task Desc.
T
B 1 F 10
4 9 5 10
5 10 15 20
A
0 0 1 1 0
Task Desc. Task Desc. Task Desc. Task Desc. Task Desc.
IM
A 4 C 3 E 12 H 2 I 1
0 0 4 4 7 8 19 20 22 22
4 4 7 7 19 20 21 22 23 23
0 0
T
Task Desc. Task Desc.
D 7 G 8
L
Task Desc. 7 7 14 14
ID Dur. 14 14 22 22
ES LS
U
EF LF
M
S
Network Diagramming Example
IC
Critical Path
5 5
Task Desc. Task Desc.
T
B 1 F 10
4 9 5 10
5 10 15 20
A
0 0 1 1 0
Task Desc. Task Desc. Task Desc. Task Desc. Task Desc.
IM
A 4 C 3 E 12 H 2 I 1
0 0 4 4 7 8 19 20 22 22
23
4 4 7 7 19 20 21 22 23 23
0 0
T
Task Desc. Task Desc.
D 7 G 8
L
Task Desc. 7 7 14 14
ID Dur. 14 14 22 22
ES LS
U
EF LF
M
S
Critical Path Method
Slack or Float
IC
T
Total (path)
A
Free (task)
IM
T Project
Slack calculations:
LS - ES
L
LF - EF
Early values are calculated on the forward pass.
U
IC
T
Critical chain method accounts for
● Resource limitations are taken into
A
account.
● The focus is on managing the
IM
duration buffer and resources.
● Activities are scheduled based on
LS and LF.
T
L
U
M
M
U
L
T
IM
A
T
IC
S
S
Tools and Techniques
Schedule Compression
IC
T
A
Crashing
Fast trackingIM
T
L
U
M
S
Schedule Compression
Crashing
IC
Trade-offs:
T
Increased costs
Adding resources to
A
critical path activities Unrealistic alternatives
Communications
IM
Changing the resources challenges
T
L
U
M
S
Schedule Compression
Fast Tracking
IC
Current project
T
Task A Task B Task C
A
Project with
IM
Task A
fast tracking
Task B
T
Task C
L
U
Days 1 16 23
M
S
Outputs
IC
1. Schedule Baseline
A schedule baseline is the approved version of a schedule
T
model that can be changed only through formal change
control procedures and is used as a basis for comparison to
A
actual results.
2. Project Schedule
IM
The outputs from a schedule model are schedule
T
presentations.
L
U
M
S
Outputs
IC
3. Schedule Data
The schedule data for the project schedule model is the
T
collection of information for describing and controlling
the schedule.
A
IM
4. Project Calendars
A project calendar identifies working days and shifts that are
available for scheduled activities.
T
L
U
M
S
Outputs
IC
5. Project Management Plan Updates
Elements of the project management plan that may be updated
include, but are not limited to :
T
Schedule baseline,
A
Schedule management plan.
IM
6. Project Documents Updates
Project documents that may be updated include, but are not
limited to :
T
Activity resource requirements.
Activity attributes.
L
Calendars.
U
Risk register.
M
S
Outputs
Project Schedule
IC
Project schedule:
T
Is calendar based
A
Has resource assignments
IM
Is signed off on as part of
the PM plan
After sign-off, forms the
T
baseline for measuring
schedule performance
L
Includes milestones
U
M
S
Project Schedule
Milestone Charts
IC
Milestone Scheduled Date Actual Date
T
Functional requirements signed off 2/1 2/1
A
Phase I coding completed 4/5 4/8
IM
Training complete 6/10
Implementation 6/15
T
Customer acceptance and sign-off 6/23
L
Project closeout 6/23
U
M
S
Project Schedule
Gantt Charts
IC
T
January February March April May June
Task
ID Duration
Name
12/21 1/4 1/18 2/1 2/15 2/29 3/14 3/28 4/11 4/25 5/9 5/23 6/6 6/20
A
1 Task 1 10 days
2 Task 2 5 days
IM
3 Task 3 20 days
4 Task 4 28 days
5 Task 5 30 days
T
6 Task 6 8 days
L
7 Task 7 20 days
8 Task 8 30 days
U
M
S
6.7 Control Schedule
IC
Control Schedule is the process of monitoring the status of
project activities to update project progress and
T
manage changes to the schedule baseline to achieve the plan.
A
IM
T
L
U
M
ITTO
S
Control Schedule
IC
INPUT TOOLS AND TECHNIQUE OUTPUT
T
1. Project management plan 1. Work performance information
2. Project schedule 2. Schedule forecasts
A
3. Work performance data 1. Performance reviews 3. Change requests
4. Project calendars 2. Project management software 4. Project management plan updates
5. Schedule data 3. Resource optimization techniques 5. Project documents updates
IM
6. Organizational process assets 4. Modeling techniques 6. Organizational process assets
5. Leads and lags updates
6. Schedule compression
7. Scheduling tool
T
L
U
M
Project Time Management
S
4.3 6.6
Direct and Develop Project
IC
Manage Project Schedule
Documents
Work
• Work • Project schedule
performance • Project calendars
data • Schedule Data
T
4.4
A
Monitor and
Control
6.7 Project Work
Control
IM
• Project management • Schedule forecasts
4.2 plan Schedule • Work performance
Develop Project information
Management
Plan 4.5
Perform
T
Integrated
• Project management
Change
plan updates
Control
L
U
Enterprise /
Organization
M
S
Inputs
IC
1. Project Management Plan
The project management plan contains the schedule
T
management plan and the schedule baseline.
A
2. Project Schedule
IM
Project schedule refers to the most recent version with
notations to indicate updates, completed activities, and
started activities as of the indicated data date.
T
L
U
M
S
Inputs
IC
3. Work Performance Data
Work performance data refers to information about project
T
progress such as which activities have started, their progress
(e.g., actual duration, remaining duration, and physical
A
percent complete), and which activities have finished.
4. Project Calendars
IM
A schedule model may require more than one project
T
calendar to allow for different work periods for some activities
to calculate the schedule forecasts.
L
U
M
S
Inputs
IC
5. Schedule Data
Schedule data will be reviewed and updated in the Control
T
Schedule process.
A
6. Organizational Process Assets
IM
The organizational process assets that influence the Control
Schedule process include, but are not limited to :
Existing formal and informal schedule control-related
T
policies, procedures, and guidelines;
L
IC
1. Performance Reviews
Performance reviews measure, compare, and analyze schedule
T
performance such as actual start and
finish dates, percent complete, and remaining duration for work
A
in progress.
IM
2. Project Management Software
Project management software for scheduling provides the ability
T
to track planned dates versus actual dates,
to report variances to and progress made against the schedule
L
IC
3. Resource Optimization Techniques
Resource optimization techniques involve the scheduling of
T
activities and the resources required by those activities while
taking into consideration both the resource availability and
A
the project time.
4. Modeling Techniques
IM
Modeling techniques are used to review various scenarios
T
guided by risk monitoring to bring the schedule model into
alignment with the project management plan and approved
L
baseline.
U
M
S
Tools & Techniques
IC
5. Leads and Lags
Adjusting leads and lags is applied during network analysis to find
ways to bring project activities that are behind into alignment with
T
the plan.
A
6. Schedule Compression
IM
Schedule compression techniques are used to find ways to bring
project activities that are behind into alignment with the plan by
fast tracking or crashing schedule for the remaining work.
T
7. Scheduling Tool
L
completed.
M
S
Outputs
IC
1. Work Performance Information
The calculated SV and SPI time performance indicators for
T
WBS components, in particular the work packages and
control accounts, are documented and communicated to
A
stakeholders.
2. Schedule Forecasts
IM
Schedule forecasts are estimates or predictions of conditions
T
and events in the project’s future based on information and
knowledge available at the time of the forecast.
L
U
M
S
Outputs
IC
3. Change Requests
Schedule variance analysis, along with review of progress reports,
results of performance measures, and
T
modifications to the project scope or project schedule may result in
change requests to the schedule baseline,
A
scope baseline, and/or other components of the project
management plan.
IM
4. Project Management Plan Updates
Elements of the project management plan that may be updated
T
include, but are not limited to :
L
Schedule baseline.
Schedule management plan.
U
Cost baseline.
M
S
Outputs
IC
5. Project Documents Updates
Schedule Data.
Project Schedule.
T
Risk Register.
A
IM
6. Organizational Process Assets Updates
Organizational process assets that may be updated include,
but are not limited to :
T
Causes of variances,
L
control.
M
S
Project Document Updates
Revisions vs. Rebaselining
IC
T
A
Start
date
IM
Finish
date
Start
date
Finish
date
T
3/1 3/8 3/15 3/22 3/29 4/6 3/1 3/8 3/15 3/22 3/29 4/6
Dates Dates
L
U