You are on page 1of 1

rtmnuonline.

com
NRJ/KW/17/6750
Master of Business Administration (M.B.A.) Semester—III (C.B.C.S.) Examination
PROJECT MANAGEMENT
Optional Paper—1
(Foundation Courses)
Time : Three Hours] [Maximum Marks : 80

N.B. :— (1) All questions are compulsory.

(2) All questions carry equal marks (16 marks each).

1. (A) Explain project life cycle in detail.

OR

(B) Who are project stakeholders ? Explain the process of stakeholders management.

2. (A) What is Risk Analysis ? Explain Qualitative and Quantitative risk analysis.

OR

(B) What do you mean by cost budget ? Explain importance of budgeting in project management. Also
explain steps of budgeting and costing.

3. (A) What is scheduling ? What are its objectives ? Explain various types of Gantt chart.

OR

(B) Construct the network diagram having the following constraints :

A < D, E; B, D < F; C < G; B, G < H; F, G < I

Find also the minimum project completion time, free float, total float and independent float, when
the time (days) of completion of each task is as follows :

Task : A B C D E F G H I

Time : 23 8 20 16 24 18 19 4 10

4. (A) What do you mean by Team in project management ? Explain the role of team and process of team
building.

OR

(B) Explain various structures of project organization with their advantages and disadvantages.

5. (A) Explain the factors affecting the project.

(B) Explain contract closure.

(C) Describe the various termination strategies.

(D) Describe the barriers to project team development.

POY—30955 www.rtmnuonline.com

You might also like