Projects 2023
I-96 resurfacing from
Cascade Rd. to M-11
(28th St.) & Burton St.
Bridge work
• Total Investment: $6.2 Million
• The project includes three miles of asphalt
milling and resurfacing, pavement markings and
bridge rehabilitation on Burton St. over I-96.
• Schedule: May 2023 – October 2023
• This project will improve ride quality and extend
the service life of both the existing roadway and
bridge.
I-96, Cascade to M-11
Traffic Impacts
• Daily single-lane closures with traffic shifts on EB and
WB I-96.
• The following ramps will be closed for one week:
• Off ramp from EB I-96 to EB M-11
• Off ramp from WB I-96 to WB M-11
• The following ramps will be closed for two weeknights
between 8PM and 6AM:
• Off ramp from EB I-96 to WB M-11
• Off ramp from WB I-96 to M-11
• WB I-96 on and off ramps at Cascade Rd.
Burton St. Bridge over
I-96 Traffic Impacts
• Total closure of Burton Street over I-96
between June 2023 and August 2023
• Burton Street traffic will be detoured using
Patterson Avenue, M-11 and Kraft Avenue.
M-21 (Fulton Street) resurfacing
from I-96 to Grand River Drive
Crossover closures
M-21 Crossover Reconfiguration
• Indirect left-turn lanes added at Taos Avenue and Rippling Drive
• Right-turn lane added at Alta Dale Avenue
• Through movements will be removed at these three intersections
I-96 pavement repair from Whitneyville Ave. to the Kent/Ionia county line
Contact Information
• John Richard, Grand Region
Communications Representative
RichardJ2@michigan.gov
www.Michigan.gov/Drive