Professional Documents
Culture Documents
COMPANY LIMITED
SHIRORO HYDROELECTRIC POWER STATION
AGM (MECH)
CHECKS/TROUBLE SHOOTING.
Physical checks and response of the brakes when applied and released manually were
carried out.
Cleaning of the entire generator housing was carried out.
Isolation of air pressure valve.
Pressure gauge was used to test the brakes one by one to ascertain the Faulty ones.
Brakes Nos.1,3 and 12 did not attain the require pressure of 6bars.
Dismantling of air piping connections of the affected brakes.
Dismantling of brakes base bolts.
Dismantling of brakes limit switches.
Dismantling of brakes lining(pads)
Unscrewing of brakes spring retainers.
Removal of Brake spring.
With the aid of 2tones chain blocks, the piston was removed safely from the brakes
drum.
Brakes diaphragms were inspected and discovered to be defective.
The brake drums were also inspected and some fine particles were found.
For PM (MECHANICAL)