NE1 - 700MW CSP + 250MW PV Hybrid Projec

Commissioning Record and Report

LV switchgear ATS test record


Test object LV switchgear in TES north building Unit PT2/TES

1 Single Line Diagram

2 Test steps
1) Verify that all circuit breakers are in normal state.
M1 I1 M2 I2 T1
Normal operation
Close Close Close Close Open
2) Remote open M1 and I1 will be interlock trip, the LV bus 1 is power failure, T1 can be closed automatically.
M1 I1 M2 I2 T1
LV switchgear 1
Closed
power failure Open Open Close Close
automatically
3)Restore all breakers to normal operation ,then remote open M2 and I2 will be interlock trip, the LV bus 2 is
power failure, T1 can be closed automatically.
M1 I1 M2 I2 T1
LV switchgear 2
Close
power failure Close Close Open Open
automatically
3 Test result
After test, the ATS function is normal.
Commissioning: EPC: Supervisor: Owner:
(Signature) (Signature) (Signature) (Signature)

Date: Date: Date: Date: