3013 SWMS Carpenter Frames and Trusses
3013 SWMS Carpenter Frames and Trusses
Date SWMS Provided to PC: Is carried out on or near energised electrical installations or
services
Person Responsible for ensuring Name: Is carried out in an area that may have a contaminated or
compliance with SWMS Date SWMS Received: flammable atmosphere
What measures are in place to WHS policies and procedures, general and workplace Involves tilt-up or precast concrete
ensure compliance with the induction training, toolbox meetings, SWMS provided to and
SWMS discussed with worker(s) at workplace and signed off,
ongoing workplace spot checks and supervision by
Is carried out on, in or adjacent to a road, railway, shipping
lane or other traffic corridor that is in use by traffic other
experienced leading hand. than pedestrians
How will the SWMS control SWMS control measures to be reviewed if work Is carried out in an area where there are artificial extremes
measures be reviewed? tasks/methods change or unexpected issues arise. of temperature
SWMS Review Date: Date: Signature: Is carried out in or near water or other liquid that involves a
risk of drowning
Have workers been consulted about the SWMS and signed the last page Yes Involves diving work
of this SWMS?
Involves a tunnel
PPE REQUIRED
Hard Safety Eye Breathing Full Face Shield Hearing Hand High Protective Fall Arrest
Hats Boots Protection Protection Protection Protection Visibility Clothing System
Optional PPE & Safety Equipment
Fire Barricades Ventilation Erect Access Erect Warning Welding screen Welding Face Sunscreen 30+ Broad Brim Hat Sunglasses
Extinguishers Scaffolding Signs Shield
Note: Following are some examples of Plant & Equipment, Permits, Qualifications and Safety Data Sheets. These need to be revised.
Plant & Equipment Permits Required
Crane Prestart check of plant and record in logbook, operate as per manufacturer’s instructions. Hot Works Permit
Nail Gun Only trained and competent workers to use the nail gun Excavation Permit
Scaffold Erection by a Qualified Scaffolder Safety Harness Permit
Power Tools To be used in accordance with the manufacturer’s instructions Confined Space Permit
Generator To be used in accordance with the manufacturer’s instructions Electrical Isolation Permit
Concrete Core Drilling Permit
Other:
Note: Following are some examples of Legislation, Codes of Practice and References. These need to be revised.
Legislation, Codes of Practice and References
Work Health and Safety Act 2019 Safe Work Australia – Hazardous Manual Tasks Code of Practice
Work Health and Safety Regulations 2021 Safe Work Australia – Code of Practice for the Prevention of Falls in Housing Construction
Safe Work Australia – Construction Work Code of Practice
Death or permanent
1 1 2 3
disability.
Long-term illness or
1 2 3 4
serious injury.
Medical attention or
several days off 2 3 4 5 How to complete this safe work method statement
work. 1) Adjust all details on the front page. Ensure all proposed HRCW activities are identified, hazards
and risks are listed, and control measures are implemented.
First Aid Needed 3 4 5 6 2) Ensure this SWMS is amended taking into account all relevant matters, including circumstances
at the workplace that may affect the way in which the high risk construction work is carried out. If
the high risk construction work is carried out in connection with a construction project, then include
the relevant maters in the WHS Management Plan that has been prepared for the workplace.
3) Consult with the workers who are going to use this SWMS and make the necessary
adjustments
4) “Risk Assessment Hazard Identification” - Inspect the site, identify the hazards that may be
present and add to this SWMS
5) Job Steps- List the job steps in sequence of tasks required to carry out the work
6) Hazard Identification- List the potential hazards associated with each Job Step
Levels 1, 2 & 3 Indicates unacceptable hazard/risk that must be eliminated
7) Initial Risk- Using the “Risk Matrix Table” rate the identified risks.
Levels 4, 5 & 6 Indicates acceptable hazard/risk
8) Control Measures Implemented- Using the “Hierarchy of Control” measures list the controls you
will implement to reduce the risks to the lowest possible level
9) Revised Risk- Using the “Risk Matrix Table”, rate the level of risk once the controls have been
implemented. If the revised risk rating is still 1, 2 or 3 do not start work until better control
measures are implemented and the revised risk rating is 4, 5 or 6.
10) Person Responsible- List the name or position of the person or persons responsible for
ensuring the controls are implemented
11) Ensure this safe work method statement is reviewed and revised if relevant control measures
are revised.
Uneven ground can cause slip 3 Check for slip and fall hazards and use 5 Supervisor
and fall injuries when moving designated areas to access work area. All Workers
tools and equipment to work
area.
Underground or overhead power 1 Identify the location of underground or overhead 4 Supervisor
can cause electrocution power lines on site All Workers
Underground or overhead gas 1 Identify the location of underground or overhead 5 Supervisor
lines can cause serious burns in gas lines on site All Workers
punctured
Personal Injury 2 Ensure the provision of first-aid equipment for the 5 Supervisor
workplace and that each worker at the workplace All Workers
has access to the equipment and facilities for the
administration of first-aid.
Identify where the first aid kit is located.
Identify who the first aider is on site.
Identify the location of the toilets and amenities on
site
Each worker is required to wear the required PPE
at all times.
MSDS for any onsite materials are to be
registered on site
Exposure to weather conditions 2 Wear a hat 5 Supervisor
UV Radiation when working in Use 30+ sunblock All Workers
the sun Eye and skin protection
Fire 3 Identify where the fire extinguisher is located 5 Supervisor
All Workers
Manual handling issues 2 Use correct Manual Handling techniques. 5 Supervisor
Utilise mechanical lifting devices where possible All Workers
5 Site Establishment Site specific hazard such as 3 Plan out the job with the site supervisor before 5 Supervisor
traffic, excavations, overhead commencing and ensure that suitable All Workers
work, pedestrians access/hazard control is available for the duration
of the works
Conduct and document a “Pre-Start Risk
Assessment” prior to commencement.
COVID-19 Safety 1 Check in every time on entry 4 Supervisor
Check out every time on exit All Workers
Use QR code provided.
Practice respiratory hygiene, wear a mask in the
workplace in accordance with Department of
Health’s requirements.
Maintain 1.5m physical distancing
Maintain good hand hygiene, regularly wash your
hands with soap and water or use an alcohol-
based hand rub.
Stay home when sick
Avoid contact with High Risk People.
6 Delivery of Materials Injury from vehicle 3 Plan space and location requirements before 6 Supervisor
Injury unloading materials materials arrive. All Workers
Injury stacking materials Ensure delivery time has been pre-arranged.
Materials blocking exits or Driver to wear PPE
footpaths Driver to ensure clear view is available or a
Moving materials over long spotter is in place while moving, reversing or
distances unloading the vehicle
Stacked materials falling Keep materials inside site boundaries. People
must not be forced off footpaths or on to
roadways.
Have materials delivered as close as possible to
work areas.
7 Unload materials or Lifting – back injury 3 Ensure that vehicle is parked on flat even surface 5 Supervisor
equipment from Load falling on personnel Use proper lifting technique All Workers
vehicle Fall From vehicle Ensure all employees have undergone manual
Manual handling injuries handling training
Use mechanical assistance (Crane/Hiab)
No personnel to stand under suspended load
Only trained operator to use lifting equipment
Do not exceed SWL of lifting equipment
Use suitable lifting chains/slings that are in good
condition and are related to lift the weight
Ensure slings are secure
Only licenced operator to use forklift
Be mindful of overhead hazards
8 Setting up equipment Slips, trips & falls 2 Set up equipment on level ground. 5 Supervisor
Crush hands, cuts Avoid rough & difficult terrain All Workers
Damage to feet Use P.P.E equipment when required.
Training in the set up of electrical leads.
P.P.E equipment such as safety shoes
9 Unloading of house Being struck by delivery trucks 2 Site staff to be aware of entry & set up area of 5 Supervisor
frames & trusses or crane trucks & cranes. All Workers
Crane or lifting gear failure Crane & truck drives to be made aware of location
of on-site personnel.
Only necessary personnel to be in the immediate
area of the crane operation
Ensure that there are not any personnel working
under the path of travel of the load.
Training & use of P.P.E equipment such as hard
hats, safety vests.
Only suitably trained or licenced personnel to
work with plant & equipment.
© Builderassist All Rights Reserved www.builderassist.com.au SWMS No: 3013.4 P a g e |8
SAFE WORK METHOD STATEMENT
Job Steps Hazard Identification Controls Measures Implemented Person/s
Initial Revised Responsible
Break the job down into Identify any potential hazards associated Decide what control measures to use to eliminate or
Step steps. List the steps in with each step – and any related risks Risk minimise the risks. Detail the control measures in this Risk
For ensuring
No sequence of activities or that may cause harm to workers or the Rating column and enter the revised risk rating in the next column. Rating selected risk
in logical order in this public. Detail the hazards and risks in [1 – 6] Note: If the revised risk rating is still 1, 2 or 3 do not start [1- 6] controls are installed
column. this column and enter the risk rating in work until better control measures are implemented and the and maintained
the next column. revised risk rating is 4, 5 or 6.
Only licenced crane operator and dogmen to work
with crane activities.
Crane operator to complete prestart checklist prior
to load lifting to ensure safety of the crane and its
components.
Crane operator to have current logbooks and
maintenance records available.
Plant & equipment to be maintained & operated
by licenced person only.
10 Placing of house Falls & trips when carrying 2 Clear area used for access 5 Supervisor
frames to ground floor frames Ensure site is clear of any debris, obstructions. All Workers
Team lifting when required
Manual Handling Injuries 2 Training in manual handling, refer to the 5 Supervisor
Back & shoulder injuries when “Hazardous Manual Tasks Code of Practice” All Workers
standing frames Training in manual handling, personnel to be
Back injury & missing target trained & shown the correct procedure in using a
when using sledgehammer while sledgehammer
positioning frames Remove any loose blocking before standing
Crushing, hit by falling objects frames
Fall from step ladder when All workers to be trained in the use of portable
connecting frames ladders with reference to the “Code of Practice for
Injury from nail guns the Prevention of Falls in Housing Construction”
All ladders must comply with Australian Standards
Ensure ladders are level & stable before using
Set up the ladder at an angle of 4-1 (one out &
four up)
Worker to keep at least 3 points of contact with
ladder
Do not overstretch (do not stretch more than
within easy arms reach)
Do not climb higher than the third rung from the
top
Ladder should be firmly secured or tied off
Do not use the top of a step ladder
NAME OCCUPATION, QUALIFICATIONS, SIGNATURE DATE SIGNATURE REVISED SIGNATURE REVISED SIGNATURE REVISED
DUTIES, RESPONSIBILITIES DATE DATE DATE