Professional Documents
Culture Documents
LIFTING METHODOLOGY
CARGO INFORMATION:
1(One) Lot knock down parts of cooling tower, structural beam for foundation and piping
materials to be delivered via large truck.
SCOPE OF WORKS:
Preparation of Lifting Equipment and Basket, Parts unloading to truck, Lifting of Parts
(@approximate weight of 3 Tons max per lift), to be lifted from ground level to Roof deck.
1. Provisions to unload parts from the trucks and load the said parts to the lifting
basket to be lifted from ground level to the roof deck of the MAB bldg. Manpower
will load the parts to the basket and other personnel is position to unload it on the
roof deck.
2. Proposed Equipment to be used will be a 40t crane, and assistance of manpower
with complete rigging tools and lifting gears.
3. Two (2) lanes of fifth ave. will be closed on the time of lifting works.
4. Lifting works will start before rush hour approximately 5am, to prevent the activity
hindering the traffic.
5. The lifting team will provide 2 traffic controller that will control the flow of traffic at
the 5th ave.
6. Isolation of the area with caution tape and early warning devices.
GENERAL METHODOLOGY:
Introduction
This methodology will show the operational handling for the Unloading of parts and
materials of the cooling tower from the truck, after unloading parts are to be placed in the
lifting basket and lifted to the roof deck of the MAB bldg., and to be received and placed
accordingly by other personnel positioned on the roof deck.
The sub-contractor and client must always re-check, re-inspect and re- survey the area or
location of the cooling tower parts to be positioned. It includes all vertical, horizontal, power
electrical cables & wires, underground pit, basement, access ways and doors, floor or soil
elevation conditions, obstruction that may hinder or affect the activity schedules, with
regards to the allotted time for the activity.
SAFETY PRECAUTIONS:
During pre-lift
Debris and other unwanted things must be clear and apply proper
housekeeping
Outriggers is retracted properly; cribbing is properly removed in place
and secure properly in storage.
Warning or caution tape is removed and properly disposed after the
activity.
CARGO CONDITION:
The cargo may be lifted on typical lifting point procedure, lifting eye where we placed
shackle on both ends or on the proposed lifting point of the cargo.
SITE CONDITION:
Site condition is also a great factor. Access leading to working areas for rigging and
Positioning, maneuvering, horizontal and vertical clearances, obstruction and other access
hindrances or improvement are yet to consider. Client must secure necessary permit such
as barangay permit or road closure permit before the lifting activities will be executed
Should there be additional information you may need, please feel free to contact us or
the undersigned for a much better assistance.
LIFTING PLAN LAYOUT:
Traffic Controllers
Pick up point
Mobile crane
CO