You are on page 1of 1

Cooling Tower Piping Methodology

1.After Delivery of pipes and parts to the site hauling and segregation is
done to ensure and orderly installation.
2.Lay outing of the area and positioning of guide post.
3.Cutting down of pipes into size.
4.Fabrication of pipe segments and positioning to the area.
5.Fabrication and Installation of pipe support
6.Pipe fit up and tuck in of pipes to designated position
7.Full welding of pipes and flanges.
8.Securing of pipe segments on the top of pipe support using U-bolts
9.Installation of remaining pipe segments like elbows, tee, & joints.
10. Bolting of the flange connection with rubber gasket and
securing it in place
11. Final inspection of piping to the prepare it for leak testing and
flushing of pipes

Prepared by: Approved by:

Erwin R, Sto Domingo Daniel Ison_


Project in Charge Technical Manager

You might also like