Building Specs of

NFC Juicing Plant

CIVIL/ STRUCTURAL/ ARCHITECTURAL/ PLUMBING

Scope of Works:

Provide where applicable all necessary manpower, supervision, skills,


equipment, materials, tools, consumables and all other incidentals required to be able to
comply with the required project scopes enumerated as follows :

A.1. General Requirements

1. Mobilization / Demobilization

Realize intention to mobilize project resources from manpower,


equipment, tools and project materials and be able to demobilize properly after
project completion.

2. Safety Compliance Requirements

Provide manpower, skills, tools, gadgets, safety program and all


necessary resources in compliance to project's safety objective. The following
should be complied at the minimum:

a. Safety Engineer's presence at all times


b. Safety Program subject for DMPI's review prior to implementation
c. Safety signage's and bulletin boards
d. Full compliance to required PPEs
e. Proper scaffolding materials designed and maintained by Certified Scaffolders
f. Area enclosures and protective covers if necessary to protect critical
equipment in case needed

3. Permits

Provide where applicable all necessary manpower and resources to be


able to secure required construction/building permits and clearances. The
nominated General Contractor will be in-charge of securing all permit
requirements in compliance with PEZA guidelines, as follows:

a. Building Permit
1 of 6
1. Based on the conceptual drawings/lay-out provided, design and develop
drawings and submit complete drawings and documents as required by
PEZA.
b. Occupancy Permit
1. Submit As-built Drawings and documents as required by PEZA.

4. Engineering, Construction Management and QA / QC

Provide where applicable all necessary manpower, resources, skills,


materials, tools, gadgets and other incidentals for the following project services:

a. Quality Management Plan – principles, guidelines, and procedures in


ensuring good quality construction.
b. Construction Safety Plan – compliant to DOLE and OSHA requirements.
c. Engineering - shop drawings, as-builts, project documentations, test reports,
methodologies, etc.
d. Construction Management - full time supervision, project updates, project
program compliance, etc.

5. Equipment use and Temporary Facilities

Provide and supply where applicable all necessary manpower,


supervision, skills, equipment, materials, tools, consumables and all other
incidentals required as follows:

a. Crane, Heavy Lifts, Excavation and Other Equipment - properly rated


equipment for lifting and positioning various project equipment and materials,
excavation, and various erection works etc.

b. Manlifts - properly rated equipment for lifting of personnel to high elevation


works such as roofing and ceiling works.

c. Temporary Facilities - project office, fabrication area, workers quarter, No


sleeping quarters allowed, material lay down area, and portalets etc.

A.2. Detailed Scope of Works

1. Design, Preparation of Plans and Drafting of Building Plans

a. The contractor shall prepare the structural design and drafting of building and
structures as mentioned above, in compliance with NSCP 2015, National

2 of 6
Building Code, National Plumbing Code, Fire Code of the Philippines, and
Philippine Mechanical Code.
b. All construction plans and drawings shall be approved by DMPI before
implementation.
c. Loads:
 Wind
 Earthquake
 Mechanical Service load = 1.0 kPa
 Electrical Service Load = 0.5 kPa
 Maintenance Service Live Load = 1.0 kPa

d. Values to be used in designing for the following structures are as follows:


 Fc’ = 28 Mpa (4000 psi) for slab and column.
 Fc’ = 24 Mpa (3500 psi) for footing and wall.
 Reinforcement steel bars shall be deformed and shall conform to
ASTM 615
 Main Bars, (16mm or larger) Fy = 276 MPa (Grade 40)
 Secondary Bars, (<12mm) Fy = 228 MPa (Grade 33)
 Structural Steel = A36 Structural Steel Shapes
 Anchor bolts shall conform to ASTM A-141.
 Cross bracing with turn buckles shall conform to ASTM A-307.
 Welding electrodes shall conform to AWS A-5.1 or A-5.5; E70
electrodes.
 Machine bolts shall conform to ASTM A-307. Each bolt shall be
provided with standard nuts and washers.

2. Site Clearing and Development

Scope will include site clearing, excavation, earth works, and surface
preparations.

a. Excavation:
 The contractor shall make all necessary excavation for foundation to
grade as indicated in the drawings.
 No footing and columns shall rest in the fill. Where excavations for
foundations reveal that footing will rest on fill, it shall be carried deeper
until the desired stratum for safe bearing power is reached.
 Whenever water is encountered in any excavations, the same shall be
removed using pail of pump. Care being taken that the surrounding
earth is not disturbed.
 All excavation for drainage, water service systems and septic tanks
and such excavation as may be necessary for the completion of the
project are included.

b. Backfilling and Grading:

3 of 6
 Fills shall be placed in layers not exceeding 0.25 m (10 inches) in
thickness, each layer being thoroughly compacted by wetting, tamping
or rolling. After the back fill has settled, the contractor shall fill up all
shallow places to bring same up to grade.

3. Construction of Building
 Lay-out and Excavation for Foundation
 Construction of concrete foundation and pedestal
 Fabrication, Manufacturing and Erection of steel columns
 Fabrication of Trusses, Girders, Strut and cross brace
 Construction of Roofing and SS gutter
 Catch Basin, Waste Water Piping and Storm Drain

4. Architectural

Provide where applicable all necessary manpower, supervision, skills,


equipment, materials, tools, consumables and all other incidentals required for
the defined scopes based on approved drawings and documents, on-site
conditions and other available data. Scope will include all new construction and
related activities as defined in approved drawings and documents that will result
in the required project set-up. Also included will be the detail design based
on issued drawings concepts.
Included areas of work are as follows:

a. Preparation Area
Flooring - 6mm Thick PU Mortar
Ceiling - PVC Ceiling on Light Metal Frame
Walling - PVC Wall on Light Metal Frame

b. Extraction Area
Flooring - 6mm Thick PU Mortar
Ceiling - PVC Ceiling on Light Metal Frame
Walling - PVC Wall on Light Metal Frame

c. Processing Area
Flooring - 6mm Thick PU Mortar
Walling - PVC Wall on Light Metal Frame
Ceiling - PVC Ceiling on Light Metal Frame

d. Drum Cleaning Inspection Area


Flooring - 6 mm thick PU Mortar
Walling - PVC Wall on Light Metal Frame
Ceiling - PVC Ceiling on Light Metal Frame

4 of 6
e. Filling Room
Flooring - 6 mm thick PU Mortar, * with moisture barrier
Walling - 100mm Thick Polyurethane Insulated Wall Panel
Ceiling - 100mm Thick Polyurethane Insulated Ceiling

f. Pre-Staging Area
Flooring - 6 mm thick PU Mortar,* with moisture barrier
Walling - 100mm Thick Polyurethane Insulated Wall Panel
Ceiling - 100mm Thick Polyurethane Insulated Ceiling

g. Genset Room
Flooring - PU Laminated
Walling - 4” CHB Wall smooth cement plaster finish, Wire Mesh,
with louver

h. Offices
Flooring - Vitrified Floor Tiles
Walling - 4" CHB wall smooth cement plaster finish, epoxy finish

i. QA Laboratory
Flooring - PU Laminated
Walling - 4" CHB wall smooth cement plaster finish, epoxy finish

j. Comfort Room
Flooring - Vitrified Floor Tiles
Walling - 4" CHB wall with Vitrified Wall Tile Finish (floor to ceiling)

k. Male Dressing Room


Flooring - Vitrified Floor Tiles
Walling - 4" CHB wall smooth cement plaster finish, epoxy finish

l. Female Dressing Room


Flooring - Vitrified Floor Tiles
Walling - 4" CHB wall smooth cement plaster finish, epoxy finish

m. Boots Wash Area


Flooring - Vitrified Floor Tiles
Walling - 4" CHB wall smooth cement plaster finish, epoxy finish

n. *Empty Drum Storage Area


5 of 6
Flooring - 6 mm thick PU Mortar
Walling - PVC Wall on Light Metal Frame
Ceiling - PVC Ceiling on Light Metal Frame

*Note: Practically the whole building is 6mm thick PU Mortar

o. Roofing
a. Prepainted Galvalume, 0.6mm thick, rib-type with ½” thick thermal
insulation, Double sided foil
b. Provide Ridge Ventilator with SS Insect Screen
5. Plumbing Works

 All Plumbing works shall conform to all the rules and regulation of the
National plumbing code and local health authorities.
 Plumbing works shall include water service to all fixtures within the building.
 Piping shall be concealed whenever possible and shall be carefully pitched
and supported by suitable brackets or hanger.
 Minimum slope of soil and waste pipes shall be two (2) percent.
 Traps shall be of the same diameter as the waste pipe from the fixture which
they serve.
 Pipes:
a. uPVC Sanitary Pipe – Series 1000/SDR 34 Neltex, Atlanta or Approved
Equivalent
b. Water Supply Line – PPR Pipes
c. Down spout – shall be uPVC.
d. Waste water line – *Ø150mm (6 in Ø), HDPE pipe.

6. Fixtures

a. Water closet – Siphon Vortex type, Toto


b. Lavatory – wall mounted, shallow type, porcelain, Toto
c. Urinal – wall hung, Toto
d. Toilet paper holder – porcelain, Toto
e. Laboratory sink – stainless, single well
f. Hand wash – stainless steel sink, single well
g. Faucets – wash room faucets for men and women should be electronic
activated.
h. Hand Dryer – electronic activated
i. Mirror – whole body, ¼” thick minimum.

6 of 6