1.

Structural works
1.1 Substructure works

1.2 Earthwork in Excavation


Machine excavation shall be done for excavation for footing, foundation trenches and other related
works. Code of safety confirming to IS 3764: 1992 or other relevant standards shall be used. Trenches
deeper than 1.5m shall be securely shored and timbered. Sheet piling shall be done wherever
necessary.

Fig: Illustrative sketch of showing timbering in loose soil

1.3 Substructure R.C.C works – Raft slab


All reinforced cement concrete works for raft supported pile, column, basement retaining wall, plinth
beam shall be done using batching plants set up at the site. The grade of reinforced concrete for
different varying members shall be decided as per structural design and for the purpose of mix
proportioning design mix shall be used. The mix material such as aggregate and sand shall be tested
and approved by the consultant’s team prior to use. Reinforced bars of grade HYSD-500 confirming to
relevant IS and NBC shall be used. For formworks, either 19mm waterproof plywood or steel formwork
shall be used wherever necessary.

1.4 Substructure R.C.C works – Retaining wall, Columns and beams.


All reinforced cement concrete works for raft supported pile, column, basement retaining wall, plinth
beam shall be done using batching plants set up at the site. The grade of reinforced concrete for
different varying members shall be decided as per structural design and for the purpose of mix
proportioning design mix shall be used. The mix material such as aggregate and sand shall be tested
and approved by the consultant’s team prior to use. Reinforced bars of grade HYSD-500 confirming to
relevant IS and NBC shall be used (reqd testing). For formworks, either 19mm waterproof plywood or
steel formwork shall be used wherever necessary. Support – Pipe Clamp
1.5 Substructure infill works (Basement)
For the purpose of infill works, periphery wall shall be R.C.C retaining walls and all internal walls shall
be brickworks, if necessary. Basement shear walls shall be made waterproof by pressure grouting with
suitable chemicals. Function missing?

1.1 Superstructure frame and deck slab


Structural Steel shall be used for all structural members including beam, column and
staircase. Member size and grade of structural steel shall be as per structural design. The
flooring system shall consist of metal plate over which 50mm thick plain cement concrete will
be laid.

Roofing
Multilayer Liner-Deck roof system consisting is proposed for roofing. A typical roof section
shall consist of following items
1. Standing seam sheet
2. Insulation
3. E Clip
4. Top hat Sub purlin
5. Vapour control layer
6. Liner-Deck profile steel or aluminum.

Finishing works
1. Floor finishes - Marble, fully vitrified glazed tiles, timber or wood flooring or any other items as
per the discussion with client can be used as flooring material.
2. Infill walls – All infill walls including external and internal partitions for superstructure shall be
of cement board.
3. Ceiling works – False celling works shall be done for which gypsum boards shall be used.
Cement board shall be used in places such as toilets where there is a possibility of contact
with water.
4. Doors – Seasoned Sal wood shall be used for door frames. For door shutters pressed
readymade plywood shutter shall be used.
5. Windows – Aluminum shall be used for all windows and ventilators,
6. Partitions – All partitions shall be made of aluminum framed glazed
7. Expansion joint treatment shall be done as per requirement.
8. Fire proofing – All material for windows, doors and the partitions shall be made fireproof as per
requirement.
9. Painting works – All internal and external wall and ceiling surfaces shall be painted by
emulsion paints. All steel sections shall be sand blasted and painted.
10. Anti-termite treatment – All building area shall be given pre anti-termite application.

Apron shall be made of cement concrete rigid pavement, taxiway and car parking area shall
be made of flexible pavement using asphalt material. All kerbs in the landside area of building
shall consists of interlocking heavy duty tiles for floor portion.