You are on page 1of 6

Qatar Media Corporation

Technical affairs department.


Maintenance section 2021
Construction of the new GYM North Gate Bldg.
No description of works Unit Quantity Rate Amount
1-Preparing site
Demolish, Dismantle and dispose the following of outside QMC camp: -
. Inner building in center of security gate.
· All the Debris.
· Contractors should transport all demolished materials to item
outside QMC campus daily.
Prepare and clean the floor surface properly.
. All interlock and curbstones.
Contractor is responsible to relocate and shift all the ground services. item
Supply and casting 15cm thick ready-mix concrete for all area with m2 488

8mm wire mesh and gage1000 plastic sheet.


2-PAINTING WORKS
Apply two coats of stucco marble paint for the inner walls of m2 66
the entrance as properly and engineer’s instructions.
3- Cement board walls
1-Lay steel sub frames, secure well to the flooring side walls and
soffits.
2- Lay 12mm thick cement board walls. Apply appropriate fillet &
primer and overlay all the newly laid walls. m2 42

3- Execute the cement board walls as per the attached drawings.


4-The contractor must be use rubber mesh in the joints before
starting the Painting for the walls.
5-The contractor is responsible to fix the cement boards properly
otherwise it will be refused.
5 4- GLASS DOOR
I)- supply and Fix 10 to 12mm thick new
double leaves with frameless tempered glass No 2
transparent, floor surface door
closers and all fittings are to be heavy-duty stainless-steel ones.
ii)-Provide &Fix stainless steel frame on the around of the door. item
iii) supply and lay two stainless steel locks at center and
bottom.
vi)- Bilingual name logo for QMC is to be written
on the transparent door. item
complete accessories of door as:-
Supply and fix automatic Door closure machine, Door stopper,
Locks and kick plate.

* 5- Steel structure frame FOR GLASS WALL


1- The contractor is responsible to put supports galvanized steel
columns with dimensions (150*200) mm at the corners and middle Lump sum
span and as per engineer’s instructions (12 columns).
Supply and lay stainless steel hinges and to be fix in glass panels
and steel columns
2-Supply and lay I beam steel (100*100) mm dimensions to be welded
with all columns from up and crossing with itself. (Lump sum).
All steel work is to be as per sketch and engineer’s instructions.
Contractor should take in his consider and his design that steel
structure may be will be loaded by mezzanine.
Steel structure (chassis) ceiling for corridors
1-Supply and lay I beam steel (100*100) mm dimensions for
the ceiling. The distance between each beam and another one is m2 25
70 cm and crossing with itself. (Lump sum).
2- The chassis system is loaded on the cement board walls and
should be connected(welded) with the supports .
6-Floor
• Supply & fix new 5mm PVC sheet for the flooring m2 488
with grade1quality (European type). with all required materials.
7-Polyurethane Sprayfoam Insulation with protective coating for roof
Prior to start spray foam, clean & wash the area properly.
and then
Supply and spray Polyurethane foam of average thick -
ness around 30- 35 mm. Density 40 -45 kg/ m³. 488
All holes on roof Kirby are to be closed & sealed properly
with waterproofing or any bonding agent equivalent to same
as waterproofing materials. Submit warranty.
Cover the spray foam by applying 2 coats of protective
coating or liquid applied waterproofing coating.
Warranty: Submit written warranty of 7 to 10 years.
Use safety helmets, shoes, overall, hand gloves and safety
Supply and fix tempered double glazed glass panels thermal
insulation and sealed with 8 mm thick. And reflection with pure
viewing with tubular aluminum frame. m2 270
supply and lay all accessories stainless steel(hinges,plates,bolts,
sealant) for the glass walls and all requirements.
Supply and fix sand blast with logo on the external glass.
If any existing structures damaged during the work must be
item
repaired
properly.
CONTRACTOR IS RESPONSIPLE OF THE CLEANLINESS AND TIDINESS item
OF THE SITE.
Contractors are responsible to take all measurements.
9-concrete and blockworks
Raft footing
Supply and casting raft foundation with its reinforcement
as per design which contractor will submit it.
Reinforced columns
m2
Supply and casting the column with its L.S
reinforcement as per design which contractor will submit it
Reinforced beams
Supply and casting the beams with its
reinforcement as per design which contractor will submit it
10-Aluminum windows
Supply and fix tempered double-glazed glass windows with 4mm
thick. And reflection with pure viewing with tubular aluminum NO 8
Frame (0.60x1.0)m
11-External Walls
ii) Lay blockwork walls with insulation of the same thickness of
existing wall including mesh &other accessories for blockwork
joints.
If the height is more than 3 m then provide concrete lintels of m2 105
size 20 cm x width of the existing wall. Fix mesh and all other
accessories at all vertical & horizontal joints when laying
blockworks.
Make plastering for the wall.
Make full maintenance for all existing inner marble walls properly.
Paint work
Apply two coats of fenomastic JOTUN paint same as matching colors m2 190
with the existing walls in the same area.
Marble
Supply marble type grade A for the external wall with all its m2 170
requirements and fix it mechanical.
Supply and fix powder coated aluminum louver panel to all
existing windows.
Main entrance
Supply marble type grade A for the steps of the entrance with m2 10
all its requirements.
Make sure that the insurance of all of your labors

who will work at this site and as well the insurance of the work.

You will not be allowed to start the work, if you do not submit

the insurance & if you do not follow all the safety measures

as stated above.

All samples must be approved from the engineer


Time of works: - 140days from work order date.

You might also like