Professional Documents
Culture Documents
1. General
1.1 This Section includes architectural joinery or custom joinery works as indicated
in the drawings, similar exposed custom wood works, required hard wares,
necessary fixtures, anchors, adhesives and related accessories and installation of
finish hardware, light metal and miscellaneous metal which is shown on or
implied by the drawings and required for the work.
1.2 Product data, material sample and color if any should be approved from Engineer
prior to the construction at site.
2. Execution
2.1 Preparation:
a. Co-ordinate sizes and locations of framing, blocking, reinforcements, and other
related units of Work specified in other Sections to ensure that interior
architectural woodwork can be supported and installed as indicated.
b. Examine substrates, with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting installation and performance
of work.
2.2 Execution
a. Install work plumb, level, true, and aligned with adjacent materials. Use
concealed shims where required for alignment.
b. Scribe and cut to fit adjoining work. Refinish and seal cuts as recommended by
manufacturer. Countersink nails, fill surface flush, and sand where face nailing is
unavoidable.
c. Paneling: Select and arrange panels for best match of adjacent panels where grain
character or color variations are noticeable. Install with uniform tight joints
between panels.
Attach panels to supports with manufacturer's recommended panel adhesive and
fasteners. Space fasteners as recommended by panel manufacturer.
Conceal fasteners to greatest practical extent.
Arrange panels with grooves and joints over supports, and fasten to supports with
nails of type and at spacing recommended by panel manufacturer. Use fasteners
with prefinished heads matching groove color.
d. Adjusting: Repair damaged or defective paneling where possible to eliminate
functional or visual defects. Where not possible to repair, replace paneling. Adjust
joinery for uniform appearance.
3.1 Clean paneling on exposed and semi exposed surfaces. Touch up factory applied
finishes to restore damaged or soiled areas.
3.2 Provide final protection and maintain conditions that ensure work is without
damage or deterioration at the time of Substantial Completion.
1 General
1.1 This Section includes Portland cement plasters system and render plaster, and
maximum permissible gap between a 3 m straight edge and any point on the
surface shall be 3 mm.
1.2 Material, mix design and accessories if any should be approved from Engneer
ahead of construction at site.
2 Execution
2.1 Preparation:
Before applying plaster ensure that backgrounds are adequately true and level to
achieve specified tolerances, free from contamination and loose areas.
2.2 Accessories installation
Beads, Lath and Accessories should be installed firmly complying with the
standards or as indicated by Engineers.
Any accessories which are rusted, improperly set or otherwise defective should be
replaced.
2.3 Plaster application
a. Do not use excessive water in mixing and applying plaster materials.
b. Flat Surface Tolerances: Do not deviate more than plus or minus 3 mm in 3
m from a true plane in finished plaster surfaces.
c. Sequence plasters application with installation and protection of other work
so that neither will be damaged by installation of others.
d. Plaster flush with metal frames and other built-in metal items or accessories
that act as a plaster ground, unless otherwise indicated. Where interior plaster
is not terminated at metal frame by casing beads, cut base coat free from
metal frame before plaster sets and groove finish coat at junctures with metal.
e. Corners: Make internal corners and angles square; finish external corners
flush with corner beads on interior work, square and true with plaster faces on
exterior work.
f. Accuracy: Finish surface to a true plane to correct line and level, with all
angles and corners to a right angle unless otherwise specified and with walls
and reveals plumb and square.
g. Frames: Bring plaster out flush with wood and metal frames and grounds and
finish each coat with a small and neat V joint where plaster finishes against
frames.
h. Vertical Surfaces: plaster shall extend full height from floor to 10 cm above
the soffit of ceiling/structural soffit, for suspended ceiling: finish plaster flush
with system bead or angle, or 75 mm above ceiling soffit where there is a
perimeter bead or angle.
i. Corners: Make internal corners and angles square; finish external corners
flush with corner beads on interior work, square and true with plaster faces on
exterior work.
j. Plaster base and finish coats should be Moist-cured as specified
k. Scratch Coat: Apply with sufficient force and cement slurry (1:1) to form a
good key, cure for 3 days and dry for at least 24 hours ahead of brown coat.
l. Brown Coat: Adjust suction by wetting immediately before applying finish
coat.
m. Skim/Finish Coats:
Apply the finish coat and finish with a steel trowel to a smooth, hard finish.
Cure with a light fog spray of water for 4 days, commencing 12 hours after
completion of application.
Protect against rapid drying until thoroughly cured.
Final coat should be left to dry for 30 days after curing period before
proceeding with paint application.
n. Render Finish Coat: Apply render plaster finish in accordance with
manufacturer’s recommendations
o. Treatment:
Make good defective or damaged plaster before starting decoration. Cut or
rake out defective work, moisten background and fill with finish coat mix and
finish to match adjacent work.
Repair, point, cut, and patch plaster around work abutting, setting into or
extending into plastered surfaces on completion of such work.
p. Exposed block work to receive paint finish shall be applied with cement
mortar slurry, rubbed over block work to fill joints.
3.1 Remove temporary covering and other provisions made to minimize spattering of
plaster on other work. Promptly remove plaster from door frames, windows, and
other surfaces not to be plastered. Repair surfaces stained, marred or otherwise
damaged during plastering work. When plastering work is completed, remove
unused materials, containers, equipment, and plaster debris.
3.2 Provide final protection and maintain conditions, in a manner acceptable to
manufacturer and installer that ensure plaster work is without damage or
deterioration at the time of Substantial Completion.
CHAPTER III. GYPSUM BOARD
1. General
2. Execution
2.1 Preparation:
a. Coordinate layout and installation of acoustical panels and suspension
system with other construction that penetrates ceilings or is supported by
them, including light fixtures, HVAC equipment, fire-suppression system,
and partition assemblies.
b. Verify that gypsum board may be installed in accordance with pertinent
codes and regulations, manufacturers' approved recommendations, and the
original design.
2.2 metal stud installation
a. Install runner channels at floor (or top of wall) and ceiling accurately, align
according to partition layout.
b. Install steel studs vertically at 400mm to centres indicated on drawings and
fix studs to runners by screwing or crimping.
c. Splice studs where necessary by nesting and lap a minimum of 200mm,
fixwith minimum of one (1) screw per stud flange.
d. Where openings occur in metal stud walls, reinforce and frame openings to
adequately carry loads. Studs on each side of openings shall be extended
from the floor to ceiling. Erect track at head (also sills, if required) to
accommodate intermediate studs. At end of each horizontal trim track, cut
out flanges, turn up web and screw to studs. Provide and install double
steel studs at door openings, double steel studs shall be replaced by steel U
channel as indicated on drawing for Doors 2600m and higher.
e. Deflection spaces between drywall partitions and the structural framing
components are essential to allow for deflection of the framing
components. Such spaces shall be provided in drywall partitions at top at
underside of structural members, by use of movement joints.
f. Blocking: Nail wood blocking to studs. Bolt or screw steel channels to
studs.
g. Co-ordinate installation of anchors, blocking, electrical and mechanical
work placed in or behind partition framing.
h. Stiffen stud walls over 2100 mm in height at a maximum 1200mm (or
equal spacing otherwise) with one (1) horizontal 19mm bracing channel
wire tied inside to each metal stud or secured as recommended by stud
manufacturer.
i. Partition Heights: as detailed either to suspended ceilings or full height
floor to roof construction above.
a. General: Treat gypsum board joints, interior angles, edge trim, control
joints, penetrations, fastener heads, surface defects, and elsewhere as
required to prepare gypsum board surfaces for decoration. Promptly
remove residual joint compound from adjacent surfaces.
b. Profile open joints, rounded or leveled edges, and damaged areas using
setting-type joint compound.
c. Apply joint tape over gypsum board joints, except those with trim
accessories having flanges not requiring tape.
d. Fill openings around cutouts with compound or acoustical sealant as
recommended by manufacturer.
e. Reinforce all joints at tapered edges and interior corners with joint
reinforcing tape set in joint compound.
f. Fill all joints, fastener heads, trim recesses, cracks and other depressions
with joint compound. Finish smooth and flush so that joints, screws and
other items will not be visible after painting.
7. Cleaning
1. General
2. Execution
a. Cleaning thoroughly sponge and wash tile. Polish glazed surfaces with clean dry
cloths. Methods and materials used shall not damage or impair appearance of tile
surfaces.
Clean tile grouted with epoxy, furan and commercial Portland cement grout and
tile set in elastomeric bond coat as recommended by the manufacturer of the grout
and bond coat.
b. Protection Keep traffic off tile floor, until grout and setting material is firmly set
and cured. Where traffic occurs over tile floor, cover tile floor with not less than 9
mm (3/8 inch) thick plywood, wood particle board, or hardboard securely taped in
place. Do not remove protective cover until time for final inspection. Clean tile of
any tape, adhesive and stains.
CHAPTER V. LAMINATED WOODEN FLOORING
1. General
2. Execution
2.1 Preparation:
a. all masonry, painting, plaster, tile, marble and terrazzo work should be
completed ahead, and overhead mechanical trades and painters have finished
in the wood floor areas. The building shall be enclosed and weathertite.
b. Permanent heat, light and ventilation shall be installed and operating during
and after installation, maintaining a range of temperature and humidity
compatible with the expected low and high moisture content of the flooring.
The wood moisture content range is determined by the flooring contactor
based on the facility’s mechanical controls and/or geographical location.
2.2 Execution
a. Subfloor: Cover concrete with poly, sealing and lapping joints a minimum of
6”.Subfloor Install lower layer of subfloor perpendicular to finish maple
flooring spacing all edges 1/4” and stagger joints 4’. Provide 1-1/2”
expansion voids at perimeter and at all vertical obstructions. The underside of
first layer shall have Neo Shook pads attached 12” on center (32 per sheet)
and 6” from edges on all sides. Install solid blocking at doorways, under
bleachers in the stacked position, and below portable goals.
b. The second layer of subfloor shall be laid at a 45-degree angle over the first
layer, spacing all edges 1/4” stagger joints 4’. Provide 1-1/2” expansion voids
at perimeter and at all vertical obstructions. Attach second layer of subfloor
with fasteners 12” on center.
c. Maple Flooring
d. Install maple flooring by power nailing or stapling approximately 12” on
center with end joints properly driven up.
e. If required, size joints between flooring strips to allow for intermediate
expansion in accordance with local humidity conditions. Provided 1-1/2”
expansion voids at perimeter and at all vertical obstructions. Machine sand
with coarse, medium, and fine paper to a smooth, even and uniform surface.
f. Remove sanding dust from entire surface by tack or vacuum. Inspect entire
area of floor to insure that surface is acceptable for finishing, clean and
completely free from sanding dust. Apply two (2) coats of approved seal and
two (2) coats of approved finish per manufacturer’s instructions. Buff and
clean floor between coats.
g. Games Lines: Apply game lines as indicated on drawings, between seal and
first coat of finish.
3 Cleaning
1. General
1.1 This Section includes recommendations for “natural” linoleum tile and sheet
floor coverings, which are composed of renewable materials.
1.2 Sample for linoleum tile, sheet flooring and adhesive if any should be
approved from Engineer ahead of construction at site.
2. Execution
2.1 Preparation:
Comply, at minimum, with the linoleum manufacturer recommendations for
space ventilation during and after installation. Where feasible, the following
ventilation conditions shall be maintained during the linoleum installation, and
for a period of 72 hours after installation: 1) supply 100% outside air 24 hours
a day; 2) supply airflow at a rate of 6 air changes per hour, when outside
temperatures are between 55 degrees F and 85 degrees F and humidity is
between 30% and 60%; and 3) supply airflow at a rate of 1.5 air changes per
hour, when outside air conditions are not within the range stipulated in item 2
above.
2.2 When installed over concrete slabs, verify compatibility of the linoleum and
adhesives with curing compounds, leveling agents, or sealing agents used for
slab preparation.
3. Cleaning
1. General
1.1 This Section includes carpet like soft surface flooring, and constructed
monolithically to provide good traction designed to cushion accidental falls
especially for general manager, theatre, meeting room.
1.2 Sample of carpet and plastic edge strip should be approved from Engineer
ahead of construction at site.
2. Execution
2.1 Preparation:
a. Subfloor shall be level and smooth.
b. Concrete slabs shall be cured and dry.
c. Curing compounds, hardeners or sealers shall not be used on the slab. If a
curing compound, hardener or sealer has been used; all residues must be
removed prior to installation of flooring.
d. Flooring over existing surface such as wood or resilient tile: install in
accordance with manufacturer's printed installation instructions.
2.2 Execution
a. Follow manufacturer's recommendations for matching pattern and texture
directions.
b. Cut openings in flooring where required for installing equipment, pipes,
outlets, and the like. Bind cut edges and replaces flanges or plates. Use
additional adhesive to anchor flooring around pipes and other vertical
projections.
c. Lay flooring lengthwise in longest dimension of space, and with
minimum seaming area, uniformly to provide a tight smooth finish.
Flooring shall be free from movement when subjected to traffic.
d. Seaming: Use a special adhesive system that permanently welds the seams
together.
e. Adhesive shall be permanently resistant to cleaning solutions. Seams shall
not be visible after flooring is installed.
f. Edge strip should be installed over exposed edges of flooring, anchor
strips to floor with suitable fasteners. Apply adhesive to edge strips, insert
flooring into lip and press lip down over flooring.
3.1 Remove waste, strips, fasteners and other cuttings from flooring. Vacuum
flooring and provide suitable protection. Unnecessary traffic will not be
permitted on unprotected soft surface flooring.
3.2 Just before final acceptance of work, remove protection and vacuum clean
soft surface flooring.
1. General
3.1 Remove waste, strips, fasteners and other cuttings from flooring.
Vacuum flooring and provide suitable protection. Unnecessary traffic
will not be permitted on unprotected soft surface flooring.
3.2 Just before final acceptance of work, remove temporary protection.
1. General
1.1 This Section includes surface preparation and field painting of the following
Exposed interior items and surfaces
Surface preparation, priming, and finish coats specified in this Section are in
addition to shop priming and surface treatment specified in other Sections.
Revise paragraph below to suit the Project.
1.2 Sample of required coating material, procedure and selected color should be
approved from Engineer ahead of construction at site.
2. Execution
2.1 preparation
a. Verify that site environmental conditions are appropriate for application of
coatings as specified.
b. Immediately prior to coating application, ensure that surfaces to receive
coatings are dry.
c. Ensure that moisture-retaining substrates to receive coatings have moisture
content within tolerances allowed by coating manufacturer, using moisture
measurement techniques recommended by coating manufacturer.
d. Immediately prior to coating application, examine surfaces to receive
coatings for surface imperfections and for contaminants which could
impair performance or appearance of coatings, including but not limited
to, loose primer, rust, scale, oil grease, mildew, algae, or fungus, stains or
marks, cracks, indentations, or abrasions.
e. Correct the above conditions and any other conditions which could impair
performance or appearance of coatings in accordance with specified
surface preparation procedures before proceeding with coating application.
f. Remove or protect hardware, electrical plates, mechanical grilles and
louvers, lighting fixture trim, and other items not indicated to receive
coatings which are adjacent to surfaces to receive coatings.
g. Remove mildew from impervious surfaces by scrubbing with solution of
trisodium phosphate and bleach. Rinse with clean water and allow
substrate to thoroughly dry.
h. For specific substrate preparation, see individual specifications.
2.2 Application
a. Apply paint according to manufacturer's written instructions. Use
applicators and techniques best suited for substrate and type of material
being applied.
b. Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces, or
conditions detrimental to formation of a durable paint film. Provide finish
coats that are compatible with primers used.
c. The term "exposed surfaces" includes areas visible when permanent or
built-in fixtures, grilles, convector covers, covers for finned-tube radiation,
and similar components are in place. Extend coatings in these areas, as
required, to maintain system integrity and provide desired protection.
d. Paint surfaces behind movable equipment and furniture the same as similar
exposed surfaces. Before final installation of equipment, paint surfaces
behind permanently fixed equipment or furniture with prime coat only.
e. Paint interior surfaces of ducts with a flat, nonspecular black paint where
visible through registers or grilles.
f. Paint back sides of access panels and removable or hinged covers to match
exposed surfaces.
g. Sand lightly between each succeeding enamel or varnish coat.
h. Scheduling Painting: Apply first coat to surfaces that have been cleaned,
pretreated, or otherwise prepared for painting as soon as practicable after
preparation and before subsequent surface deterioration.
i. The number of coats and film thickness required are the same regardless of
application method. Do not apply succeeding coats until previous coat has
cured as recommended by manufacturer. If sanding is required to produce
a smooth, even surface according to manufacturer's written instructions,
sand between applications.
j. Omit primer over metal surfaces that have been shop primed and touchup
painted.
k. If undercoats, stains, or other conditions show through final coat of paint,
apply additional coats until paint film is of uniform finish, color, and
appearance. Give special attention to ensure that edges, corners, crevices,
welds, and exposed fasteners receive a dry film thickness equivalent to
that of flat surfaces.
l. Allow sufficient time between successive coats to permit proper drying.
Do not recoat surfaces until paint has dried to where it feels firm, and does
not deform or feel sticky under moderate thumb pressure, and until
application of another coat of paint does not cause undercoat to lift or lose
adhesion.
m. Application Procedures: Apply paints and coatings by brush, roller, spray,
or other applicators according to manufacturer's written instructions.
n. Prime Coats: Before applying finish coats, apply a prime coat, as
recommended by manufacturer, to material that is required to be painted or
finished and that has not been prime coated by others. Recoat primed and
sealed surfaces where evidence of suction spots or unsealed areas in first
coat appears, to ensure a finish coat with no burn-through or other defects
due to insufficient sealing.
o. Completed Work: Match approved samples for color, texture, and
coverage. Remove, refinish, or repaint work not complying with
requirements.
3.1 Cleanup: At the end of each workday, remove empty cans, rags, rubbish, and
other discarded paint materials from Project site.
3.2 After completing painting, clean glass and paint-spattered surfaces. Remove
spattered paint by washing and scraping without scratching or damaging
adjacent finished surfaces.
3.3 Protect work of other trades, whether being painted or not, against damage
from painting. Correct damage by cleaning, repairing or replacing, and
repainting, as approved by Architect.
3.4 Provide "Wet Paint" signs to protect newly painted finishes. After completing
painting operations, remove temporary protective wrappings provided by
others to protect their work. After work of other trades is complete, touch up
and restore damaged or defaced painted surfaces.
CHAPTER X. FURNITURE
1. General
1.1 This Section includes the furniture as shown in furniture layout design
drawing and subject to the approval from Engineer.
1.2 Sample should be approved prior to the arrangement at site.
2. Execution