2015/2016 - 2019/2020
NOVEMBER 2015
RUKUNGIRI MUNICIPAL COUNCIL VISION STATEMENT
“A HEALTHY
POPULATION IN A SECURE
ENVIRONMENT”
i
RUKUNGIRI MUNICIPAL COUNCIL MISSION STATEMENT
OF RUKUNGIRI MUNICIPALITY”
ii
THEME OF THE PLAN
“CORDINATED QUALITY
DEVELOPMENT’’
iii
MAP OF UGANDA SHOWING THE LOCATION OF RUKUNGIRI AS OF 2007
Rukungiri
Municipality
iv
Map of Rukungiri District showing the location of Rukungiri Municipality.
Rukungiri
Municipality
(Former
Rukungiri
Town Council
and Kagunga
v
LIST OF ACRONYMS/ABBREVIATIONS
vi
MCC : Municipal Contracts Committee
DLB : District Land Board
RMC : Rukungiri Municipal Council.
RTC : Rukungiri Town Council.
RTI : Respiratory Transmission Infections.
RUGADA : Rukungiri Gender and Development Association.
SACCOs : Savings and Credit Co-operative Organizations.
SATC : Senior Assistant Town Clerk.
SCO : Senior Commercial Officer.
SIA : Senior Internal Auditor.
SLEO : Senior Law Enforcement Officer.
ST : Senior Treasurer.
STIs : Sexual Transmission Infections.
SWOT : Strength, Weakness, Opportunities and Threats.
TASO : The Aids Support Organization.
TB : Tuberculosis.
TC : Town Clerk
TE : Town Engineer.
UBC : Uganda Broadcasting Co-operation.
UC : Urban Council.
Ug. Shs : Uganda Shillings.
UPE : Universal Primary Education.
USE : Universal Secondary Education.
UTL : Uganda Telecommunications Limited Communication.
VCT : Voluntary Counseling and Testing.
YLP : Youth Livelihood Programme
vii
Foreword
The vision of Rukungiri Municipal Council that connects to the overall Council’s desired
direction is “A Healthy and Wealthy Urban Population in a Secure Environment”.
Arising out of this vision is the Council’s mission “To serve the Community through
Coordinated delivery of Services, focusing on National priorities and Significant Local
Needs in order to promote Sustainable Development of Rukungiri Municipality” all these
embraces the theme “coordinated quality service delivery for sustainable urban
development”.
In order to achieve the vision, the Council focuses on strengthening planning as one of
the main priority areas. The process of developing this plan involved extensive
participation and consultations at lower local level, to capture stakeholders’ contributions
to development of this plan and ensure that the plan is totally owned by stakeholders.
I wish to commend all technical officers and all stakeholders for their contributions in
various ways and efforts put in production and success of this five year development
plan. It is my sincere hope and belief that the community, political leaders, management
staff, NGO’s, Development Partners and other stakeholders, will support the
implementation of this plan.
FOR GOD AND MY COUNTRY
CHARLES MAKURU
MAYOR
RUKUNGIRI MUNICIPAL COUNCIL
viii
Acknowledgement
The Process of developing this five year development plan involved wide and extensive
participation and consultations at lower local level, to bring stakeholders’ contributions to
development of this plan and ensure that it is fully owned by stakeholders.
I wish to express sincere gratitude and extend appreciation to many individuals who
contributed in various ways to the success of this development plan, in general and its
production, in particular. I may not mention all by names and their specific contributions
but however feel indebted to their work.
It is my sincere hope that this plan will go a long way in guiding effective service
delivery for the benefit of Rukungiri Municipal Council. I urge and appeal to all
stakeholders to support the implementation of this development plan.
ix
Executive Summary
The plan comprises of the following but not limited to the following, Municipal Council
Situation, Goals and Strategic Objectives, development partners, planning process,
planned interventions, monitoring and evaluation control mechanisms.
Rukungiri Municipal Council with the obligation of achieving the Mission, the following
are the Council’s strategic objectives which are inter-linked with the development goals
and Vision of the Council:-
To identify and continue collecting sufficient local revenue to ensure service
delivery through local revenue enhancement plan i.e. proper enumeration,
assessment, tendering revenue sources and effective planning. Proper utilization of
existing resources will be ensured for the development of Rukungiri Municipality.
To improve on Rukungiri Municipality’s infrastructure and improve communication
through continuous routine road maintenance, rehabilitation and opening up of new
access roads to increase the marketability of produced products.
To improve democratic and accountable governance through strengthening
Council’s operations by training and sensitizing political leaders.
To enhance the sustainable growth of the economy through increasing household
incomes and promoting equity
To improve on the accountability through strengthening and facilitating proper
Internal Audit systems and financial management mechanisms to increase value for
money.
To improve and increase accessibility to basic health services through sensitization
of the communities on sanitation and hygiene, provision of sanitary facilities,
facilitating health centers and training health workers to improve their performance.
x
To continue providing safe water and sanitation improvement by protecting springs,
constructing boreholes and community water tanks, cleaning of the Town. Construct
and clean toilets at public places. Mobilizing and sensitizing community members on
operation and maintenance of water and sanitation facilities.
To improve access, infrastructure, learning environment and quality of Education
Services in the Municipality.
Promoting sustainable population and the use of environmental and natural
resources.
Rukungiri Municipal Council remains and is still committed to provide effective and
improved services that have enabled continuous developments and they include; Micro
and Small Enterprise Growth and Development, Construction of market and storage
facilities, Promotion of High Value Crops, Street Lighting, Land Physical Planning,
Procurement and, Installation of Culverts, Periodic Road maintenance, Extension of
piped Water, Energy and Environmental Construction, Community Empowerment
Programme and Gender Programme, Community Driven Development Programmes and
Gender mainstreaming into development programmes.
In the coming five financial years, the following are the priority interventions; increase
accessibility to basic health services, sensitization of the communities on sanitation and
hygiene, provision of sanitary facilities, Provision of safe water, Physical planning,
community empowerment, Sensitization and enforce laws and regulations on Trade,
Industry and cooperatives, modern markets construction, Office block construction,
Construction of Health Centres and staff quarters, opening of community access roads,
maintenance and rehabilitation of existing roads, identification of source for supply of
water to the Municipality, Laying of culverts at critical parts, extension of street lights
and power. Lower income earners are to be supported with a range of projects to boost
the recent Production-Marketing strategy that is Wealth Creation Programme. Special
xi
interest groups particularly PWDs shall be supported to carryout self-help projects using
special grants from central government.
The Five Year Development Budget estimates resource envelope which include locally
generated revenue and central government transfers estimated at the tune of Uganda
Shillings as indicated in the table below;
The above mentioned resources may not be enough and the Council appeals to all the
Development partners and others stakeholders to support the effective implementation of
the plan in order to improve the standards of living of people of Rukungiri Municipal
Council in particular and the entire District in general.
Rukungiri Municipality as a fast growing Urban Council has the following development
challenges; low local revenue which is attributed to general poverty in the society, poor
road network that would facilitate development if proposed and surveyed roads are
opened, low productivity of the population since most of the entrepreneurs are involved
in micro enterprises with inadequate business skills and finally most people are not
developmental in nature hence not participating in development programmes.
xii
TABLE OF CONTENTS
RUKUNGIRI MUNICIPAL COUNCIL MISSION STATEMENT..................................ii
MAP OF UGANDA SHOWING THE LOCATION OF RUKUNGIRI AS OF 2007......iv
Map of Rukungiri District showing the location of Rukungiri Municipality......................v
LIST OF ACRONYMS/ABBREVIATIONS.....................................................................vi
Foreword..........................................................................................................................viii
Acknowledgement..............................................................................................................ix
Executive Summary.............................................................................................................x
TABLE OF CONTENTS.................................................................................................xiii
CHAPTER 1: INTRODUCTION........................................................................................1
1.1 INTRODUCTION....................................................................................................1
1.2 RUKUNGIRI MUNICIPAL COUNCIL PROFILE.................................................1
1.2.1 HISTORICAL BACKGROUND..........................................................................1
1.2.2 LOCATION................................................................................................................1
1.2.3 SIZE AND TOPOGRAPHY..............................................................................2
1.2.4 SOILS AND DRAINAGE..........................................................................................2
Drainage...............................................................................................................................2
1.2.5 CLIMATE.................................................................................................................2
1.2.6.1 WATER COVERAGE........................................................................................3
1.2.6. 2 INFRASTRUCTURE – HOTEL FACILITIES...................................................3
1.2.6. 3 COMMUNICATION SERVICES AND INFRASTRUCTURE........................4
1.2.6.4 POLITICAL AND ADMINISTRATIVE STRUCTURE...................................4
Table 1: Administrative units for Rukungiri Municipal Council.................................4
1.2.6.5. POPULATION PROGRAMME............................................................................7
POPULATION PROGRAM CHALLENGES AND CONSTRAINTS..............................8
Proposed future actions/activities:.......................................................................................8
1.2.6.6 EDUCATION........................................................................................................8
Key problems in Health:....................................................................................................15
Lessons learnt in Health.....................................................................................................15
1.3 MUNICIPAL POCC ANALYSIS............................................................................16
1.11 THE PLANNING PROCESS....................................................................................30
1.11.1 How the Plan Was Developed............................................................................31
xiii
1.11.2 Strategic Planning...................................................................................................31
1.11.3 Consolidating the Development Plan.....................................................................32
1.12 MUNICIPAL PROBLEMS AND CHALLENGES:.................................................34
1.12.2 STRATEGIES TO EXPLOIT THE OPPORTUNITIES AND ADDRESS THE
CHALLENGES:................................................................................................................35
1.13 MENTORING........................................................................................................35
Lower Local Governments................................................................................................37
1.14 ENERGY FOR RURAL TRANSFORMATION......................................................41
1.15 Linking identified Key Development Problems/issues to the NDP.......................45
1.16 Prioritization of strategic interventions and LG investment Priorities....................46
CHAPTER 2: SITUATION ANALYSIS......................................................................49
MUNICIPAL COUNCIL GOAL......................................................................................49
2.1 Review of Sector Development Situations..................................................................49
2.1.1 Management Support Services.................................................................................49
FINANCE DEPARTMENT..............................................................................................52
PLANNING UNIT............................................................................................................53
WORKS AND TECHNICAL SERVICES:.......................................................................54
EDUCATION AND SPORTS:..........................................................................................56
HEALTH SERVICES DEPARTMENT............................................................................60
COMMUNITY BASED SERVICES................................................................................62
Department Objectives and strategies.........................................................................62
PLANNING UNIT............................................................................................................63
INTERNAL AUDIT..........................................................................................................64
CROSS-CUTTING ISSUES.............................................................................................65
2.4: POVERTY ANALYSIS............................................................................................65
2.4.1 Definition of Poverty:...............................................................................................65
2.4.2. Indicators of Poverty in the Municipality and actual problems that are leading
people into poverty............................................................................................................66
2.4.3 Basic Characteristics of the poor in Rukungiri Municipality...................................66
2.4.4 Geographical poverty pockets and categories of poverty affected groups.............66
2.5 GENDER ANALYSIS..........................................................................................71
2.5.1 Household/Production Division of Labour...............................................................72
xiv
2.5.2 GENDER ANALYSIS IN TERMS OF RESOURCES ACCESS, CONTROL AND
OWNERSHIP....................................................................................................................72
2.5.4 DEPARTMENTAL GENDER ANALYTICAL MATRIX...................................74
2.6. HIV/AIDS ANALYSIS..............................................................................................75
2.6.1 Drivers of the HIV/AIDS Pandemic.........................................................................76
2.6.2 HIV/AIDS MAINSTREAMING IN THE MUNICIPAL DEVELOPMENT PLAN.
...........................................................................................................................................76
2.6.3 Challenges facing the delivery of HIV/AIDS services in Rukungiri Municipality
include the following:........................................................................................................78
2.7 FAMILY PLANNING ANALYSIS............................................................................79
2.7.1 Challenges in family planning...............................................................................79
2.7.2 Strategies to address family planning issues............................................................79
2.7.3 Stake holders of family planning..............................................................................80
2.8 ENVIRONMENTAL ANALYSIS............................................................................80
2.8.1 ENVIRONMENTAL ANALYSIS...........................................................................80
2.8.2 Environmental opportunities....................................................................................82
2.8.3 Environmental challenges / constraints....................................................................82
2.8.4 Strategies for improved Natural Resources Management/environment sustainability
...........................................................................................................................................82
2.9 STAKEHOLDERS ANALYSIS............................................................................83
2.9.1 Rukungiri Municipal Council local Government has the following stakeholders:. .83
CHAPTER 3: FIVE YEAR DEVELOPMENT PROGRAMMES..............................84
3.1 BROAD MUNICIPAL DEVELOPMENT PROGRAMMES AND PROJECTS
OVER THE 5 YEARS.......................................................................................................84
3.2 MUNICIPAL PROGRAMME OF ACTION.........................................................84
CHAPTER 4: MUNICIPAL IMPLEMENTATION PLAN FOR 2015/2016...........104
CHAPTER 5: MONITORING AND EVALUATION ARRANGEMENTS............119
INTRODUCTION AND OBJECTIVES OF THE FRAMEWORK...............................119
5.1 Introduction................................................................................................................119
5.2 Goals and objectives of M&E framework.................................................................119
5.3 Justification of the M&E frame work and methodology...........................................120
5.3.1. Justification of the M&E.......................................................................................120
xv
5.3.2. Methodology..........................................................................................................120
5.4 Current situation and existing M&E arrangements..................................................120
5.5. Conceptualization, design, data and reporting requirements....................................120
5.7. Roles and responsibilities of key authors in M&E...................................................121
5.7.1 Local Governments.................................................................................................121
5.8 IMPLEMENTATION COST ESTIMATES:-.........................................................121
5.7.1 FINANCING........................................................................................................123
5.7.2 POLICY IMPLICATIONS:....................................................................................123
CHAPTER 6:...................................................................................................................125
COMMUNICATION STRATEGY (DEVELOPMENT OF MUNICIPAL
COMMUNICATION STRATEGIES /PLAN.................................................................125
6.0 Communication strategy (development of Municipal communication strategies)
125
6.1 Introduction:.........................................................................................................125
6.2 Dissemination of the MDP and Annual Progress Report of the implantation of the
MDP. 125
6.2.1 Annual Progress Report...................................................................................125
6.3 Stakeholders, roles and responsibilities.....................................................................125
6.4 Feedback on the performance of the Municipality....................................................126
CHAPTER 7 PROJECT PROFILES.......................................................................127
MANAGEMENT SUPPORT SERVICES..................................................................127
WORKS AND TECHNICAL SERVICES......................................................................131
Budget and financing plan:..............................................................................................132
Budget and financing plan:..............................................................................................135
Budget and financing plan:..............................................................................................137
Budget and financing plan:..............................................................................................140
COMMUNITY BASED SERVICES DEPARTMENT..................................................142
Financing plan:............................................................................................................142
Financing plan:............................................................................................................143
Financing plan.............................................................................................................144
PLANNING UNIT ROFILES.........................................................................................145
INTERNAL AUDIT UNIT.............................................................................................154
xvi
xvii
CHAPTER 1: INTRODUCTION
1.1 INTRODUCTION
The plan covers the fiscal period of 2015/16 to 2019/20 and stipulates the Rukungiri
Municipality’ strategic direction, development priorities and implementation strategies.
The theme of this development plan is “coordinated quality service delivery for
sustainable urban development”. The driving force is to step up objectives and strategies
to achieve the Municipality mission of serving the Community through Coordinated
delivery of Services, focusing on National priorities and Significant Local Needs in order
to promote Sustainable Development of Rukungiri Municipality
1.2.2 LOCATION
1
1.2.3 SIZE AND TOPOGRAPHY
Rukungiri Municipal Council has a total area of 64.9 sq kms, 11% of which comprises
forests, woodland with an approximate total area of 26 hectares of planted eucalyptus
trees. Rukungiri Municipality is comprised of 3 Municipal Division Councils, 12 wards
and 84 villages. The Municipality lies at approximate attitude range of about 615m to
1864m above sea level.
Drainage
The Municipality is neither endowed with rivers nor major lakes but has several streams
like Nyakibale Lower stream.
1.2.5 CLIMATE
The Municipality experiences bimodal rainfall with long rains received from February to
May and short rains from September to November. The mean annual rainfall ranges
between 700mm to 1200mm.
Climatic changes have resulted into unpredictable heavy rainfall and prolonged drought.
The Municipality is generally cool with daily temperatures ranging from 15 oC to 20oC.
There is no readily available data on humidity and winds.
2
1.2.6 OTHER CHARACTERISTICS
3
1.2.6. 3 COMMUNICATION SERVICES AND INFRASTRUCTURE
Fax Services
Internet Services
FM Radio Broadcasting.
The Head of the Civil service is the Town Clerk. There are 7 Heads of Departments, 1
Assistant Town Clerk, , Sectional Heads and other members of staff at the Municipal
level. At Division level there are Senior Assistant Town Clerks, Treasurers, extension
staff and Town Agents who assist in the implementation of Central and Local
Government Policies and Programmes.
4
Table 1: Administrative units for Rukungiri Municipal Council
Name of
Municipality Divisions Wards Villages
Rukungiri Western Div 1. Karangaro 1. Kafunda
2. Nyamabare
3. Kibaare
4. Mutara
5. Kahororo
6. Nyakihanga
7. Kabwire
8. Furuma
2. Kitimba 1. Kigina
2. Katoobo
3. Kanyanku
4. Kaaro
5. Maaya
6. Kinyabushaisha
3. Kinyasano 1. Kinyasano
2. Makobore High
School
3. Kayembe
4. Karucumitsi A
5. Butimba
6. Butagatsi
4. Northern A 1. Kiyaga
2. Kagyera
3. Kaceeka
4. Kakabada
5. Kagarama A
5
2. Kanyinya 1. Kafunjo
2. Kataruka
3. Marumba A
4. Kitazigurukwa
5. Nshure
6. Kyeshoro
7. Marumba B
8. Marumba C
3. Kigaaga 1. Katungu
2. Rwobo
3. Rwagana
4. Kigina
5. Kibimbiri
4. Rwakabengo 1. Katojo
2. St. Geralds
3. Nyakibale
4. Rwakabengo A
5. Rwakabengo B
6. Katenga
7. Bunura/Go-Down
8. Rwenkuba
9. Rwarubira
2. Rwentondo 1. Byara
2. Kyarugamba
3. Kamuri
4. Rwempitsi
5. Kagugu
6
6. Kafunjo
7. Nyabihinga
8. Katwekamwe
9. Rwakatunduri
10. Kanyanga
11. Kikyenkye
12. Nyamiko
13. Rugongi
14. Nyamayenje B
3. Kagashe 1. Kagashe
2. Kinombe/Runyinya
3. Rwabuteneka
4. Immaculate Heart
4. Northern B 1. Kakabada
2. Keitumura
3. Kagarama B
7
1.2.6.5. POPULATION PROGRAMME
3. The Municipality has not attracted funding for population programmes from the
centre, donors and NGOs to tackle population challenges.
9
1. Implementation of the population policy and population action plans for
sustainable development
1.2.6.6 EDUCATION
The Municipality has 15 Government aided Primary Schools and 16 private schools with
an enrolment of 3959 girls and 6705 boys. The girls constitute 57% of the total
enrolment. There are 942 primary school teachers and all of them are trained. Female
teachers constitute 43% of the teaching force. The teacher pupil ratio is 1:39 while the
textbook pupil ratio is 2:1
facilities
Existing
Existing
Existing
Existing
Lacking
Lacking
Stances
lacking
lacking
stances
blocks
Pupils
sitting
%
Kahororo 4 3 248 0 0 0 7 3 12
Rukondo 7 1 298 30 0 0 7 2 8 4
Ruruku 4 4 470 50 10.6 0 8 2 6 12
Kiyaga 4 3 417 100 24 0 7 2 9 8
Kinyasaano 18 4 601 0 0 7 9 6 20 5
Kakonkoma 3 4 122 0 0 0 7 1 4 2
Kitazigurukwa 6 1 235 0 0 4 3 4 16 0
Nyakibale Lower 26 5 793 108 13.6 0 20 7 28 5
Rukungiri 4 5 402 100 25 0 8 2 10 6
Kashozi 4 3 183 0 0 0 7 2 6 2
Katwekamwe 4 3 288 52 18 0 7 3 8 3
Kyatoko 4 4 346 0 0 0 7 3 9 4
Nyabihinga 4 3 336 278 83 0 7 4 20 0
Nyakibale Upper 8 14 100 100 10 20 12 5 22 18
0
Town council 7 0 207 0 0 0 7 2 8 2
Total 107 57 594 818 14.1 13 121 48 186 71
6
HEALTH DEPARTMENT
Table 6. Health units by category by ward
No Division Ward Health unit Ownership Level Comments
1. Western Karangaro Karangaro Government 2 Functional
11
Rwentondo Katwekamw Government 2 Functional
e
Kyatoko NGO 4 Functional
NKD-MCH
Kyatoko NGO 2 Functional
Nyabihinga
Kyatoko NGO 2 Functional
Kyatoko
Northern B Government 2 Functional
Prisons
Kyatoko Government 2 Functional
Police
3 Southern Kanyinya Marumba Government 2 Functional
12
(a) Kinyasano Ward
Kinyasano 91 73 164 47 47 100%
Cathedral
Butimba 144 187 331 76 76 100
Kinyasano Girls 33 41 74 16 16 100
Karucumitsi 100 96 196 79 79 100
Butagatsi 246 291 537 110 110 100
Makobole 65 54 119 34 34 100
Kayembe 189 189 378 86 84 98
TOTAL 868 931 1799 446 446 100
(b) Karangaro
Ward
Nyakihanga 225 199 424 102 90 88
Furuma 234 229 463 108 98 91
Nyamabale 222 229 463 108 82 91
Kahororo 222 235 457 88 96 91
Mutara 200 186 386 92 83 90
Kafunda 339 358 697 125 106 85
Kabwire 365 372 737 152 140 92
Kibale 487 420 907 167 160 96
TOTAL 2241 2144 4385 941 855 91
© Northern ‘A’
Kiyaga 299 330 629 139 116 84
Kakabada 344 298 642 110 102 93
Kagarama 180 215 395 85 79 93
Kaceeka 202 224 426 79 64 81
Kagyera 227 261 488 137 130 95
TOTAL 1252 1328 2580 550 491 89
(d) Kitimba
Kanyanku 192 211 403 81 73 90
Kaaro 161 160 321 65 57 88
Maaya 129 119 248 63 59 94
Kinyabushisha 232 225 457 83 80 96
Katobo 300 333 633 116 110 95
Kigina 201 217 418 110 102 93
TOTAL 1215 1265 2480 518 481 93
(2) SOUTHERN DIVISION
MALE FEMALE TOTAL HOUSE LATRINE LATRINE
HOLDS COVERAGE
%
(a) Kanyinya Ward
Kataruka 218 234 452 78 67 86
Kitazigurikwa 188 171 359 71 62 87
13
Kafunjo 166 165 331 67 61 91
Nshure 126 135 261 54 51 94
Marumba C 131 126 259 40 37 93
Marumba B 45 61 106 24 23 96
Marumba A 53 87 140 22 21 95
Kyeshoro 75 90 165 37 35 95
T0TAL 1002 1069 2071 393 357 92
(b) Kigaga Ward
Rwagana 76 81 157 31 30 96
Rwobo 166 174 340 63 60 95
Kibimbiri 99 174 340 42 40 90
Katungu 163 187 350 60 58 96
Kigina 104 105 209 37 34 90
TOTAL 608 721 1329 233 222 93
(c) Ndorero Ward
Ndorero 205 216 421 70 66 94
Kibirizi 163 158 321 71 70 99
Nyamayenje 423 363 786 130 97 74
Nyaruzinga 201 212 413 90 72 80
TOTAL 992 949 1941 361 305 87
(d) RWAKABENGO
WARD
Go – down 423 437 860 251 246 98
Katenga 247 319 566 125 113 90
Rwenkuba 114 123 237 81 75 92
Rwarubira 130 141 271 83 80 96
Rwakabengo A 127 115 242 79 72 90
Katojo 112 126 236 98 95 97
Rwakabengo B 217 232 449 90 86 95
Nyakibale Hospital 120 129 249 102 100 98
St. Geralds 34 79 113 21 19 90
TOTAL 1524 1701 3225 930 886 94
(3) EASTERN DIVISION
MALE FEMALE TOTAL HOUSE LATRINE LATRINE
HOLDS COVERAGE
%
(a) Rwentondo
Ward
Katwekamwe 216 203 419 83 83 100
Kanyanga 219 197 416 88 88 100
Kicence 112 118 230 47 47 100
Byara 136 126 262 44 44 100
Kyarugamba 190 200 390 73 73 100
14
Nyamiko 134 150 284 54 54 100
Kafunjo 164 135 299 53 53 100
Kagugu 162 172 334 64 64 100
Nyabihinga – 187 206 393 92 92 100
Rwere
Rugongi 111 121 232 49 46 94
Rwempitsi 250 266 516 86 86 100
Nyamayenje 92 109 201 43 40 93
Kamuli 164 165 329 65 64 98
Rwakatunduri 186 206 392 82 82 100
TOTAL 1839 1958 3797 923 916 99
(b) Kyatoko
Ward
Rwakahinju 186 203 389 67 67 100
Ruhega 186 199 379 72 72 100
Kacwa 78 76 154 28 28 100
Kifunjo 234 246 480 110 110 100
Mugamba 126 87 213 40 40 100
Nyaruharo 212 267 479 78 98 100
Isherero 191 190 381 66 66 100
Nyakashaka 96 113 209 44 44 100
Karucumitsi 232 277 509 151 108 72
Nyabihinga 128 123 251 46 43 93
Nyakihanga 108 125 233 42 40 95
Police 70 52 122 60 60 100
TOTAL 1847 1958 3805 824 776 94
(c) Kagashe
Ward
Kagashe 131 127 258 79 69 87
Runyinya – 202 169 371 83 73 88
Kinombe
Rwabiteneka 127 119 248 49 48 98
Immaculate 58 83 141 52 52 100
TOTAL 518 490 108 263 242 92
(d) Northern
Ward B
Kagarama 210 231 441 100 100 100
Kakabada 76 106 182 44 42 95
Keitumura 304 310 614 109 94 86
Prison 78 69 149 86 46 53
TOTAL 668 716 1384 339 282 84
15
Table 15. SUMMARY ON LATRINE COVERAGE PER DIVISION
1. WESTERN DIVISION
HOUSE LATRINES COVERAGE
HOLDS
(a) Kinyasano Ward 448 448 100%
(b) Karangaro Ward 941 855 91%
© Northern A Ward 550 491 89%
(d) Kitimba Ward 518 481 93%
Overall coverage for Division
93%
2. EASTERN DIVISION
(a) Rwentondo Ward 929 916 99%
(b) Kyatoko Ward 824 776 94%
© Kagashe Ward 268 242 90%
(d) Northern B Ward 339 282 83%
Overall coverage for Division
92%
3. SOUTHERN DIVISION
(a) Kanyinya Ward 393 357 91
(b) Kigaga Ward 233 222 95
© Ndorero Ward 361 305 84
(d) Rwakabengo Ward 930 886 95
Overall coverage for 1917 1770 91%
Division
16
Inadequate Health infrastructure.
17
1.3 MUNICIPAL POCC ANALYSIS
This was conducted in a participatory manner, involving Heads of Departments, the
LLGs and other stakeholders. The table below shows the potentials, opportunities,
constraints, and challenges of the Municipality.
18
Services planning and supplement - Under staffing in supply
management team and development some departments. - Inadequate G.Tax
the other staff. In the partners. - Inadequate compensation.
Municipality there is a - Enabling transport means. - Frequent budget cuts
conducive political Government - inadequate office and delay of Central
support. Policies and space Government releases.
Programmes -Inadequacy of
alternative sources of
revenue to replace
G.Tax.
Works and The department Existence of - The road Heavy rain down
Technical Has qualified staff. projects and equipments is now powers washes away
Services Central governments NGOs to too old to be relied road surfaces and
fund almost all the supplement road on save the bull culvert crossings.
road and water works. and water works Landslides destroy
dozer which is still
in the water sources for
good.
Municipality gravity flow schemes.
- The approved
structure puts the Long dry spells lower
Municipal Engineer water tables and
at U1 while the reduces yield leading
next immediate to increased un
cadres are at U4 functionality Planting
- There is need to of Eucalyptus trees
customize the post close to water sources
of senior engineer makes them dry
after the Municipal
Engineer.
Natural - Presence of - Enabling laws - Inadequate field -Poverty forces people
Resources competent personnel and policies staff to rely entirely on
to handle - Political support - Low household natural resources
Environment, at Municipal and incomes hence - Land fragmentation
Wetlands, Forestry Division levels people relying on - Very inadequate
and Lands issues - Improved natural resources budget
community - Adamancy of some - High population
participation and individuals in growth
attitude towards complying to - Cross boarder
environment Mgt environmental pollution of water
- Integration of standards bodies
environmental - Non presence of - Absence of field
issues into the partners NGOs in the staff at Sub County or
MDP Municipality county levels
- False feeling by
some people that
environment
management
sabotages and delays
development.
19
Table 27: Major NGO/FBOs operating in the Municipality
KEY Category MAJOR ACTIVITIES AREA OF
STAKEHOLDER OPERATION
Rukungiri Gender NGO HIV/ AIDs activities/ services Municipal wide
and Development
Association
(RUGADA)
North Kigezi FBO -Management of Disabilities. Municipal Wide
Diocese Paying school fees for disabled
children(PAPSAC)
- Water Supply and Sanitation
improvements (NKKD WATSAN)
-Education services ( primary,
secondary and Tertiary Institutions)
-Health services ( Kisiizi Hospital,
Rugarama and Other Health
centres)
- OVC Support (whole package)
Compassion NGO Education support to OVCs Municipal wide
International (in IGAs to OVC families
partnership with
Psychosocial support
Local churches in
the Municipality) Medical care (children are
taken to health centers)
HIV Counseling
MDD
TASO Uganda Ltd NGO HIV/AIDS services Municipal wide
Income generating activities
amongst their clients
Scholastic support to children of
TASO clients.
Literacy Action & NGO -OVC support with school fees, Municipal wide
Development materials & uniforms.
Agency (LADA). - Water and sanitation (construction
of tanks)
- IGAs (Piggery)
- Distribution of mosquito nets.
Rukungiri District NGO - HIV/AIDS services Municipal wide
Network of People Income generating activities
Living with HIV amongst their clients
(RUDINET)
20
TABLE 28. NGO’s /CBO’s OPERATING IN RUKUNGIRI MUNICIPALITY AS AT 30 th JUNE 2015.
21
SN Name of CBO /NGO Activities Village Ward Division
1. Literacy Action & -OVC support with school fees, Kifunjo Kyatoko Eastern
Development Agency materials & uniforms.
(LADA). - Water and sanitation
(construction of tanks)
- IGAs (Piggery)
- Distribution of mosquito nets.
2 Rukungiri Gender & -HIV prevention Town centre Kyatoko Eastern
Development - VCT services (opp. Round
Association -condom distribution about)
(RUGADA) - Distribution of mosquito nets.
- Family Planning services.
3. The Aids Support -Child social support Kakabada Northern B Eastern
Organization (TASO) - Community sensitization.
-Treatment.
-Opportunistic Infections.
-Home visiting.
-Psychosocial support.
4. Rukungiri District -Selection planning and Kyatoko Kyatoko Eastern
Farmers Association. management of enterprises.
(RUDFA) -Child protection and legal
services to OVC.
- Food and nutrition program.
5. Compassion -School fees contribution. Kinyasaano Kinyasaano Western
International -Scholastic materials to OVC.
- Health services to care givers of
OVC.
6. Abateganda PWD -Training in IGAs and self help. Kyatoko Eastern
group - Self help project of goat rearing,
Heifer e.t.c.
7. Highland Investment -NAADS programme Kibaale Karangaro Western
Project -Water & sanitation
-Opening access feeder roads to
link all projects home stead.
8. Rukungiri Mobile -Issuing of identity cards of the Karucumitsi Kinyasaano Western
market Traders. group.
-Behavior maintaining.
- Good coordination with
Government officials.
9. Rukungiri Town -Always work for the good
22 of the Katenga Katenga Southern
United Group group.
- To ensure that every member
meet his /her obligation as per
group decisions.
Health related NGOs have contributed a lot in supplementing Government efforts to
fighting mortality and mobility especially in combating malaria and HIV/AIDS in
Rukungiri Credit goes to Nyakibale Hospital (Kabale Diocese) Kisiizi Hospital (North
Kigezi Diocese), TASO and RUGADA in providing both care, support and treatment of
HIV/AIDS and Malaria in the municipality.
In the area of orphans and vulnerable children, the efforts of NGOs and FBOs cannot be
under established NGOs like Compassion International in partnership with local
churches is supporting OVCs by paying school fees and offering social support to over
500 pupils/students in the Municipality in both Primary and Secondary schools.
Rukungiri Municipality is grateful to the SACCOs that have come up in the Municipality
and are offering credit to the population especially RUDECs, NYADESA, and MDIs like
PRIDE to mention a few.
23
Dissemination of policy planning guidelines; Dissemination of the necessary
information related to planning to the lower councils and to all lower local governments
was done in September 2015. Sharing of ideas, lessons learnt and feedback on National
Assessment Results was also done. The Council further facilitated village/wards on the
new planning guidelines that emphasize the vision based approach to decision making.
Review and Integration of Ward and sectoral plans into the Development Plan; The
Technical Planning Committee reviewed ward investment plans along with sectoral
committees’ proposals, for integration and inclusion in the Council’s Development Plan.
These were consolidated and submitted to the Council Executive Committee for
consideration. The Technical Planning Committee formulated the plan and prepared
investment profiles and work plans.
Preparatory processes. The planning process started in July 2014 with the situation
analysis which included feedback to lower local governments and an assessment of the
24
current situation in the district. An assessment of the performance under different sectors
was undertaken using the routine mentoring and evaluation reports and Feedback visits to
LLGs. The LLGs were mentored and prepared for the new planning cycle. They were
also engaged in actual discussions about strategic planning and development issues.
1.11.4 Details of the Planning Process: Rukungiri Municipal Council fully embraces the
Policy of Decentralization as mandated by the Constitution of the Republic of Uganda,
1995 under Article 196 and the Local Government Act (Cap 243).
The Rukungiri Municipal Council Local Government considers Decentralization as a
powerful cornerstone in its efforts to implement the Development Plan in line with the
framework of Government Poverty Action Plan (PEAP) and the second Millennium
Development Goals (MDGs).
The Rukungiri Municipal Council reviews and rolls over its Development Plan every
year. The main aim is at achieving the Council Development Goals.
The main steps undertaken in producing this Development Plan include among others the
following; The Council had opportunity to take stock of the major achievements
registered during the 2014/2015 and 2015/2016 financial years, constraints that were
encountered during the implementation of programmes and lessons learned.
The Council reflected further on its strategic development framework in terms of its
adequacy in responding to the development challenges and aspirations of the people and
25
finally the Council set new targets for the future (next five years)in a participatory
manner including all the Stakeholders namely all the Divisions/Wards, Non
Governmental Organisations and Civil Society organizations who had representations
during the Budget Conference for FY 2015/16
Rukungiri Municipal Council has come up with a truly integrated and harmonized Plan
which does not only take care of sectoral linkages and bottom up priorities and needs but
must be consistent with the national priority programmes, policies and standards. The
problems that the council is tackling are all poverty related.
Besides the outcome, the process has also been more rigorous. During this year planning
process, the proposed interventions by different sectors were appraised and screened
using a set of nine criteria namely; Consistency with the district strategic and
intermediate objectives, Technical feasibility, Availability of funds (especially for the
first year), Number of people benefiting, Development of local potential, Sustainability
considerations including provisions for recurrent costs, Environmental considerations,
Gender responsiveness and Political acceptability. The appraisal aimed at screening and
prioritizing investment proposals.
26
governments and other LLGs Threshold for and Division
relevant Stakeholders in integration into Municipal Town clerks
Development plans
06 To ensure that peoples LLGs priorities to be HODs
priorities get the attention integrated in the sector
\during the planning process development plans.
07 Sector Working groups to -Sector technical staff HODs
consolidate department plans came up with sector
development plan
proposals
-Sector Committees
discuss the departmental Sector
proposals and consolidate Committees
plans
08 Technical Planning - Hold TPC to discuss each Municipal
Committee to review and sector proposals Planning Unit
appraisal the sector - A task force/team to
development plan proposals. integrate sector MDP Task Force
development plans and and Planning
cross-cutting issues. Unit.
09 Blessing the Draft The development plan was Municipal
development plan presented to Municipal Executive
Executive Committee Committee
10 Municipal Stakeholders Presentation and approval Secretary
consensus on the of the District development Finance and
development interventions plan Administration
Rukungiri Municipality has a potential to grow and reduce the current high levels of
poverty among the population. However a number of problems and challenges still pause
a big threat to expected growth potential for development.
Another challenge facing the Municipality is limited Local Revenues both at the Lower
Local Governments and the Municipal Council levels. This is caused by low tax base,
low production and productivity, a big number of defaulting tax payers, thus constraining
service delivery.
27
The Municipality also faces the challenge of environmental degradation, land
fragmentation high population densities thus leading to low production. As a result, the
feeding habits have deteriorated; morbidity remains high leading to poor academic
performance in schools in addition to high illiteracy levels already existing. This stifles
the positive trends out of poverty.
To overcome the above problems and challenges, appropriate strategies geared towards
poverty eradication either directly by increasing the incomes of the poor or by increasing
the ability of the poor to raise their incomes/enhance the quality of life of the poor,
enhance good governance and cause economic growth have been designed as mentioned
below.
Formulation and policy implementation by councils and ensuring good governance and
accountability at all levels of governments. This will lead to effective and honest public
service delivery.
28
Enhance bottom-up planning, monitoring and mentoring lower councils. This will lead to
more realistic plans that enhance ownership of the programs thus strengthening
sustainability and value for money.
1.13 MENTORING
Rukungiri Municipal Council has mentored the LLG/Division staff in mainstreaming
environmental issues, HIV/AIDS and poverty. Mentoring has also been done in planning
and financial management. The issues above have been incorporated in the Capacity
Building Plan.
The following sector achievements have been made amidst gaps outlined which still
exist.
Table 31: Sector Mentoring Achievements.
Sector Achievements Gaps
Administration Induction of new staff Politician need exposure visits in order to
was carried out. effectively perform their duties by
Mentoring staff and learning from other Local Governments.
head teachers in Capacity gaps were identified in
performance appraisal Resource Mobilization for Councillors.
of staff. Mentoring gaps in participatory planning
Mentored staff in were identified.
participatory There is need for training in OBT for
Development Planning. Municipality Staff.
Finance and Mentoring staff on Capacity Needs Assessment Exercise
Planning preparation of financial revealed capacity gaps in producing
reports quality and timely final accounts.
Mentoring staff and Gaps in production of books of accounts.
politicians in revenue Need to mentor staff in making timely
generation and accountabilities to avoid audit queries
collection.
Public Health Health centres in Health managers have capacity building
charges undertook gaps in the management of the new
training sources in emerging technologies in health
health services programmes.
management It was also identified that medical
personnel have capacity gaps in Human
Resource management and have capacity
gaps in communication skills and
customer care.
There is generally limited knowledge of
Public Service rules and regulations
29
among the medical staff.
Lack of Government Hospital.
Education and Head teachers and their During Capacity Needs Assessment
Sports Deputies mentored in exercise, it was identified that
Management Skills and Headteachers have training gaps in
staff performance Human Resource management and
appraisal. Records keeping.
Capacity gaps in performance appraisals
were identified amongst head teachers.
Gaps in Education Planning and
Management.
Community General gaps in integrating gender
Based awareness and gender mainstreaming in
Services all programmes.
Attachments and exchange visits by
Gender Focal point Persons to bridge the
gender gaps.
Lower Local Mentoring Division There still exist Capacity Building gaps
Governments. ACDOs in participatory among Chairpersons LC III, law
planning. Enforcement staff in revenue
Mentoring LLG staff in mobilization.
book keeping and Limited skills and knowledge of legal
production of books of application in the implementation of
accounts. Government policies.
Mentoring of LLG staff There is a need to mentor LLG Staff in
in the assessment making realistic budgets and revising
manual. them accordingly to avoid audit queries.
Training and orientation of Local Council
Courts.
Mentoring LLG staff in financial
management and accountability.
Gaps
It was discovered that some of the above Organizations have inadequate skills in
care and counseling.
There are also Capacity gaps in Community sensitization and mobilization skills
for leaders of Women, Youth, PWDS, CSOs and Private Sector.
Limited skills and knowledge for NGOs, CSOs, CBOs and the Private Sector in
Planning, Entrepreneurship and Financial Management.
32
-Periodic maintenance/rehabilitation
of 3.5Km of paved road network
-Mechanised routine road
maintenance of 148.7Km of road
network
-Routine road maintenance of
160.3Km of road network
-Production of detailed plan for 4
wards
-Production of structural plan for
Municipality Phase 1
-Construction of 1No water closet
toilet
-Fencing with chain link of RMC
Headquarter offices
EDUCATION -Inspected all the Schools: -Lack of provision
& SPORTS Government & Private. for Co curricular
DEPARTMEN -Produced inspection reports & activities i.e
T submitted the reports to MOE & S in games & Sports,
accordance with the guidelines music etc
-Improved sanitation in Schools by -Lack of provision
constructing pit latrines and for continuous
providing water tanks using SFG professional
-Provided 3 seater twin desks to development
Government aided primary schools (CPDS) for
-Installed lightening arrestors to all teachers
government primary schools -Lack of means
-Run PLE for the years without any for transport
problems and maintained good -Severe lack of
standard (over 98% pass) at PLE accommodation
-Organised end of terms examination for teachers at
and tests for all primary schools Primary schools
-Carried out support supervision for -Lack of public
both Primary & Secondary Schools library
HEALTH - Upgrading of Rukungiri HC from - Marumba twin - Staffing gaps
III to IV status. staff house due to recruitment
- Regular supply of EMHS by NMS construction. freezing.
and delivery to 8 Government HCs. - Staff promotion
-Rukungiri Municipal Council - Upgrading of limitations in
contributed to District maintenance Rukungiri HC IV to Municipal
of 5th position out of 112 districts in District hospital. structure.
perform ace of financial years 2013- - Inadequate staff
2014 and 2014-2015 accommodation.
-Received UNEPI fridge at - Inappropriate
Rukungiri Health IV for Municipal supply of slow
Cold Chain system. moving EMHS
- Upgrading of North Kigezi MCH items by NMS.
33
from HC III to IV status and -Low functionality
operationalisation of theatre. of Health Centres
- Community Sanitation and -No Health Sub
Hygiene. District funds for
- Urban street cleaning, sanitary Municipality
lanes and open space clearance. - Inadequate
- Town beautification exercises. garbage dumping
- Building plans recommendation in site.
line with Public Health Act. - Lack of
- Garbage management with cemetery land.
collection at household and skips
level and appropriate disposal.
- Curative, Preventive and Health
Promotion services by 11 HCs.
- Support Supervision and
Monitoring of service delivery by 11
HCs.
- Planning, Coordination,
Cooperation and Harmonisation of
service delivery with District, Central
Government and Development
Partners.
- Provision of abattoir services.
FINANCE & -Increased revenue collection by -The department
PLANNING percentage needs enough
-Sensitisation of communities &tax office space
payers using workshops seminers -Need for more
and radio talk shows departmental
-Some staff have been aided in computers
training -There is a need
-Financial reports and statements are for a money safe
prepared and submitted to relevant -Increased
bodies timely facilitation of
-Revenue enhancement plan is revenue
always prepared intime. mobilisers and
-Two computers and two laptops staff in accounts
have been procured section
-Strong room and file shelves have -Need of transport
been put in place – facility for
-Books of accounts, subsidiary revenue collection
ledger, general ledgers and other -The department
relevant accounting documents are need increased
always prepared in time logistical
-Audit queries are always answered allocation e.g
and responded to in time as required stationery,
by Law. calculators,
-The department has embarked on cashbooks, ledger
34
timely planning and budgeting books etc.
-Equal allocation of resources to all -The department
departments lacks bye laws to
-Timely enumeration and assessment aid it in
of revenue sources prosecution of tax
defaulters
There are various sources of energy in the Municipality which include among others
Biomass, e.g. wood, animal dung and charcoal, Fossil fuels which include diesel, petrol,
kerosene, and solar energy.
The possible energy services should be promoted in the Municipality for poverty
reduction and promote projects that utilize energy for productive uses e.g. Agro-
processing, development of fuel wood plantations and promotion of energy saving
Techniques (improved cook stoves).
Fuel wood is the commonest source of energy especially for cooking and it is
increasingly being depleted.
There are quite a number of business opportunities in the energy sector that can be
ventured into for Social-economic development including public private partnerships;
development of the potential water falls in the Municipality
Development of the various energy sources will speed up development through boasting
of business e.g. metal fabrication, grain milling and coffee hulling, food processing, milk
cooking, development of ICT, creation of employment, value addition to agricultural
products, improving service delivery in Health centers and improving communications.
2014/15
BUDGET
Revenue: Actual Budget
Local revenue 358,179,227 423,040,559
Government grants 5,043,007,770 5,280,271,775
Capital grant (road machinery) 1,157,665,408
Total 6,558,852,405 5,703,312,334
Expenditure:
Administration 744,213,505 778,422,712
Finance 2,556,100 2,661,620
Commission and Boards 9,768,000 11,592,632
Council 139,535,279 147,207,600
Production and marketing 10,486,426 10,912,804
Health & Environment 586,586,654 694,433,981
Education and sports 3,005,114,424 3,021,508,071
Works & Technical services 832,895,000 899,233,205
Community Services 120,927,107 148,465,701
Internal Audit 10,139,480 26,748,576
Enforcement 2,556,100 2,661,620
Planning 13,673,400 25,602,276
Clerk office 27,452,546 28,151,412
Depreciation 871,393,913 1,233,940,128
Other expenses
Total 6,619,829,597 6,218,363,533
36
Table 35. PROJECTED REVENUE AND EXPENDITURE FOR 2015/16-2019/20 FOR RUKUNGIRI MUNICIPAL COUNCIL
Expenditure
Management & Support Services 376,275,935 800,484,821 811,836,502 852,428,327 895,049,744
Council, committees & Boards 47,589,500 111,380,000 117,799,505 123,689,481 128,936,273
Production and marketing 90,000 8,742,000 9,179,100 9,638,055 10,119,958
Health services 308,870,844 364,761,500 382,999,575 402,149,554 422,257,031
Education & sports 2,471,465,297 2,125,276,400 2,231,540,220 2,343,117,231 2,460,273,093
Works & Technical services 427,982,192 846,603,489 888,933,663 933,380,347 980,049,364
Gender & Community services 33,789,800 47,221,551 49,582,629 52,061,760 54,664,848
Finance & Planning 86,539,163 163,098,793 171,253,732 179,816,420 188,807,240
Internal Audit 12,804,000 17,228,800 18,090,240 18,994,752 19,944,490
37
1.15 Linking identified Key Development Problems/issues to the NDP
38
High maternal and child Implementation of Uganda National
Mortality, HIV/AIDS &TB, Minimum Health Care Package
and Communicable and non-
communicable diseases
Inadequate capacity of Regular support supervision, procurement
Health Management of computers and internet, timely report
Information System making
Education and Maintenance of high Inspection, Support supervision and
Sports performance standards in monitoring, Regular tests and exams
schools
Inadequate management and Involvement of stakeholders in the
administration in schools management of schools
Lack of functional office Repair and procure office equipment
Equipment
Inadequate human and Training of Teachers for Special Needs
material resources for and establishment of a Special needs
Special needs education centre
Poor participation in Sports, Mobilisation of funds and organizing
and other co-curricular regular competitions
activities.
Inadequate teaching and Provision of scholastic materials and
Learning support supervision, holding regular
meetings with stake holders, training
workshops and seminars
39
-
Sensitization of Human Rights, National Values and Patriotism Municipal
wide.
STRATEGIES FOR UNLOCKING THE MOST BINDING CONSTRAINTS
There will be sensitization on the need for men to increase their participation in
Agricultural production. On inadequate funding, the Government shall be urged to
increase funding for local Government activities.
There will be increased health education, treatment and control of communicable and
non-communicable diseases.
There will be strict implementation of Municipal Council maintenance Policy
Rukungiri Municipal Council has a potential to grow and reduce the current high levels
of poverty among the population. However a number of constraints still pause a big threat
to expected growth potential for development.
Over reliance on women labor for agricultural production mainly as a result of excessive
drinking by men, has resulted into very low production, which also impact on the levels
of income at household level. This is further compounded by lack of work ethic and poor
saving culture among the population hence perpetuating poverty.
Another constraint facing the Municipality is limited Local Revenues both at the Lower
Local Governments and the municipal Council levels. This is caused by low tax base,
low production and productivity, inadequate markets for the commodities produced, thus
constraining service delivery.
The Municipality relies up to over 95% funding from the Central Government. Over
time, central Government has continued to reduce the amount of funds granted to the
local Government, which affects the effectiveness of operations.
40
POLICY ON OPERATION AND MAINTENANCE IN THE MUNICIPALITY
In a bid to achieve all the set goals and strategic objectives by Rukungiri Municipal
Council, the Council is hereby committed to maintain, sustain and implement the projects
made for this FY 2015/2016; It is from this that the Council has an operation and
maintenance policy for public investments here stated in this 5-year development plan
(2015/16 – 2019/20).
This operation and maintenance policy is aimed at mainstreaming the public investments
and ensures their sustainability and continued service to the community.
On behalf of Rukungiri Municipal Council, We guarantee that Council staff will work
hand in hand for effectiveness and efficient coordination of service delivery so as to
promote socio-economic development of Rukungiri Municipality which in turn will
simultaneously bring Health and Wealth for the Urban Population in the Secure
Environment.
……………………………………… …………………………………………
CHARLES MAKURU OTIM ANDREW KIBWOTA
MAYOR TOWN CLERK
RUKUNGIRI MUNICIPAL COUNCIL RUKUNGIRI MUNICIPAL COUNCIL
41
CHAPTER 2: SITUATION ANALYSIS
Mandate:
To coordinate, supervise and monitor the Municipal Council, Lower Local Councils and
Central Government activities, employees and departments to ensure transparency in
management and delivery of services as provided for by the Constitution of the Republic
of Uganda 1995, the Local Government Act Cap. 243 and any other legislation
Composition:
- Administration
- Municipal Council
- Contracts Committee
- Audit
- Records and Information
- 3 Divisions
Education
Department Established Filled Vacant Masters PGD Degrees Diploma Others
Post Post Post
Management 60 39 21 1 5 5 0 24
Finance 13 10 3 1 2 8 2
Production and 2 - - - - -
Marketing
Education and 383 3 1 1 2 1
Sports
Technical 23 8 15 1 1 2 5
Services Works
Gender and 7 5 2 1 1 2 5 11
Community
Services
Health 113 69 44 2 1 7 59
42
Planning Unit 6 4 2 3 1
Internal Audit 4 2 2 - - 1 1 -
Departmental objectives, strategies and activities
Objective (1):
To have in place sufficient, motivated, well equipped and trained manpower.
Strategy:
To recruit and retain the most qualified manpower
Activities:
- Recruitment of Staff
- Rolling over of the Capacity Building Plan
- Networking with Central Government and other Development Partners on
training opportunities
- Processing submissions for staff.
- Training staff
- Regular staff meetings
- Processing and payment of salaries, allowances and terminal benefits.
- Planning for and allocation of offices and equipment to relevant staff.
Objective (2)
To ensure proper utilization and accountability of Resources.
Activities:
- Procurement of goods, services and works.
- Processing of payments.
- Monitoring and evaluation of Projects.
- Posting and displaying of Mandatory Notices.
- Study tours.
- Staff Performance Appraisal.
- Board of Survey.
Objectives (3)
To promote Democratic Governance and Public relations.
Activities:
- Providing technical support to Lower Local Governments.
- Sensitization of Political Leaders on their roles and responsibilities.
- Enforcing laws, rules, regulations and guidelines.
- Coordinating Meetings.
- Coordinating and implementing good policies and decisions.
- Discussing and deliberating on policies.
- Attending to public complaints and problems.
- Organizing Public Functions or Celebrations.
Objective (4)
Objectives (5)
To establish an efficient and effective Records Management System
Activities:
- Training of staff in Records Management.
- Updating and computerizing data.
- Writing of Reports and filing vital documents.
- Dissemination of information.
Objective (6)
To increase Public awareness on important development issues
Activities:
- Mobilization of the masses and organizing sensitization meetings.
- Organizing Workshops and Seminars for the Stakeholders.
- Notices and information dissemination through the Mass Media.
Objective (7)
To promote effective and efficient Management of Land Matters
Activities:
- Setting Land disputes.
- Handling new applications for registration of land.
- Renewal and extension of land tittles.
- Mobilizing and sensitizing the masses on land matters.
44
FINANCE DEPARTMENT
Mandate:
To mobilize, collect and manage the Municipal Council finance resources at all levels of
Governance in the Municipality.
Composition:
The sector has five sections.
- Administration
- Revenue
- Budgeting
- Expenditure
- Accounting
Objectives:
- To identify and collect revenues for service delivery.
- To ensure proper management and accountability public funds.
Strategies:
- Carry out research on possible new sources of Local Revenues and update the
existing ones.
- Train staff on modern methods of Book-keeping, financial and accounting
regulations.
- Timely production and submission of accountability documents.
- Preparation of quarterly financial statements.
Activities:
- Processing and payment of salaries, allowances and other benefits.
- Planning and allocation of offices and equipment to relevant offices.
- Field visits in Divisions.
- Monitoring budget performance and utilization of resources.
- Coordinating of sectors on production and submission of accountabilities and
OBT report.
45
- Preparation of financial statements.
PLANNING UNIT
Mandate
Under part II of the Local Government Financial and Accounting Regulations 1998 and
Sections 36-38 of the Local Act 1997, the unit is mandated to coordinate the planning
process, mentor, monitor and evaluate development projects and carry out programmes
that address population issues at all levels of governance in the Municipality.
Composition:
The Planning Unit has the Planning Office, Statistics, Population, projects Development
Planning, Management information systems operation planning, Monitoring and
Evaluation
46
WORKS AND TECHNICAL SERVICES:
Mandate:
The Constitution of the Republic of Uganda 1995, the Local Government Act 1997 and
other Legislations mandate the department to construct and maintain civil infrastructure,
water development, and plant and vehicle maintenance.
Composition:
Works department is comprised of works (civil and building), electrical, mechanical, and
water & sanitation.
Departmental Objectives:
- To improve the livelihood of the population through provision of road
infrastructure and increase safe water coverage.
- To ensure proper sanitation of communities through sensitization and
mobilization on the use of various modes of waste disposal e.g ecosan toilets,
pit latrines, waste management and personal hygiene.
- To provide coordinated development through production and implementation
of structural and detailed development plan.
-
47
Strategy:
- Construction and maintenance of roads, water, and housing infrastructure
- Construction, maintenance and sustainability of water infrastructure
- Emphasizing software implementation activities.
Sector objectives:
- To raise the safe water coverage
- To improve housing/office infrastructure in the Municipality.
- To maintain vehicle fleet, plants and equipment.
- To increase the length of truck roads in the Municipality and improve
accessibility.
- To raise latrine coverage to 100%.
Sector Strategies:
- Construction and maintenance of water infrastructure
- Construction and maintenance of housing and office infrastructure.
- Procurement of specialized personnel to maintain vehicles and road
equipment.
- Construction and maintenance of roads and training of labour based routine
maintenance workers.
- To ensure construction of water pipelines along the main roads in the
Municipality.
- Ensuring safe latrines at every household and advocate for.
- Production and implementation of detailed plans
48
EDUCATION AND SPORTS:
Objective: Improve access and quality of education services in the Municipality.
49
Interventions: - Setting evaluation tests.
- Administering of tests and examinations
- Marking and grading of tests and examination.
- Dissemination of results
-Training examiners
- Conducting seminars and workshops for examiners and teachers .
Background Despite high enrolment at the beginning of primary education the retention
and completion of the girl child and children with special needs has been
challenged by various circumstances. The project therefore aims at
improving conditions for education of girl and children with special needs.
50
Background: Many schools in the Municipality cannot accommodate all pupils in the
classrooms and others cannot provide enough furniture for all pupils. In
almost all the schools, sanitary facilities are demanding, this situation
impinges negatively on the provision of quality education. The project
therefore aims at addressing the existing situation.
Background: There are 15 government aided primary schools and 201 teachers in the
Municipality. If every teacher was to be accommodated at school the
number of houses would be 201 against 30 that are in existence. This
means only 15% of the teachers are currently accommodated at schools.
Lack of accommodation at schools causes teachers to provide irregular
service as they commute to and from schools. The teachers who hire
accommodation have found it difficult due to prevailing rising costs. They
therefore need to consider construction of teacher’s houses at schools to
address the situation.
Background: Many places in the Municipality are prone to lightning and thunderbolts
and on several occasions; teachers and pupils have fallen victims. There is
therefore a need to protect lives and property against thunderbolts at
schools.
51
Interventions: Identifying needy schools
-Procurement of services
- Witnessing deliveries and installations
- Supervision of works
- Sensitizing schools on maintenance of installation.
Background: The existing teachers’ resource Centre was for the entire Rukungiri
District and especially to cater for secondary schools in the fields of
science and language. The general public and teachers have no access to
any form of library and resource Centre. Lack of such a facility downturns
the quality education in away. It is therefore necessary to provide such a
facility in order to enhance the quality of provision of education.
Mandate:
The sector derives in mandate from the Constitution of the Republic of Uganda 1995 of
the Local Governments Cap. 243, the Public Health Act 2000. The National Health
Policy 1999, to plan, coordinate, monitor and utilize resources in order to ensure delivery
of effective, efficient, equitable and quality health services to the population of Rukungiri
Municipality, so that major causes of ill health and disparities are reduced therein, as a
contribution to poverty eradication, economic and social development of the people.
Composition:
The Department is composed of the following sections: Curative, Sanitation and
Hygiene, Health Promotion and Education.
Department Objectives:
- To improve and increase accessibility to basic health care services. This will
be achieved by improving functionality of all Health Centres and facilitating
the NGO Health Centres in order to improve their services delivery standards.
- Recruiting and training of health workers, mobilization of the communities
and civil society organizations.
53
- Available staff adequately trained.
- Monitor environmental health activities
- Supervises staff.
4. To control vectors
- Monitor vector related diseases
- Procure and distribute medicine for specific vector diseases.
54
COMMUNITY BASED SERVICES
Mandate:
The Department is responsible mainly for ensuring protection and proper development of children;
empowerment of special interest groups - Youth, Women, PWDs and Elderly, as well as ensuring
harmonious industrial relations. This is pursuant to provisions in the Constitution of the Republic of
Uganda 1995, the Local Governments Act, the Probation Act, the Children’s Act, the Labour
Legislations, the National Youth Policy, the Uganda Gender Policy 2007, the OVC Policy 2006 and
other policies and legislations that aim at empowering special interest groups. The department is also
responsible for community mobilization for development.
Composition:
- Administration
- Youth and Children Affairs
- Gender and Culture
- Disability and Elderly
- Labour, Employment and Industrial relations
- Community Development
Table 42: Equipment and tools under Community Based Services Department:
Item No Condition
Office tables 02 Operational
Filing cabinet 01 Operational
Office chairs 04 Operational
Office trays 02 1 Old, 1 Good
Office tables 2 Functional
Departmental Objectives:
To ensure that the community fully participates in and benefits from Development initiatives and
particularly the integration of special interest groups (Youth, Women, PWDs and the Elderly) in the
main stream, socio economic development of the Municipality.
Sectional Objectives:
Objective (1)
To promote community participation in Development initiatives.
Strategy:
Mobilisation and Sensitization/trainings
55
Objective (2)
To ensure participation of the Youth in socio-economic Development of the Municipality
Strategies:
- Sensitization
- Training
- Group formation, assessment and funding
Objective (3)
To empower PWDs and Elderly to participate in and benefit from Development initiatives
Strategies:
- Training
- Sensitization
- Group formation, assessment and funding
Objective (4)
To promote equitable participation and distribution of opportunities between men and women
Strategies:
- Mobilization and sensitization
- Training.
- Gender awareness trainings
- Gender mainstreaming into development programmes
- Gender responsive planning and budgeting
Objective (5)
To promote harmonious industrial relations
Strategies:
- Sensitization
- Enforcement.
PLANNING UNIT
Goal:
To provide an Integrated Planning for services covering sectoral plans, policies and to monitor and
evaluate the implementation activities
56
Objective (1)
To facilitate and coordinate the process of development planning and budgeting both at the Municipal
Council and Division Levels.
Strategies:
- Training of staff in Development planning
- Integration of Work plans into the Development plan
- Producing work plans and reports.
Objective (2)
To strengthen data collection, analysis and implementation
Strategies:
- Conducting skills training workshops and seminars for Technical Staff civil society
organization at all levels.
- Developing formats and questionnaires for use in data management.
- Analyzing and interpreting data.
- Disseminating information to stakeholders for planning purposes
- Training data management and equipping the Data Bank to improve data management for
effective planning and decision making.
Objective (3)
To enhance the importance of population factors in development
Strategies:
- Increased public awareness on the relationship between population factors in relation to
development.
- Registration, collection and analysis of vital statistics
- Dissemination of population data to all Stakeholders
- Promote research in the causes of high population growth rate.
INTERNAL AUDIT
Mandate:
To oversee Government Income and Expenditure and proper utilization of resources in an
independent and objective manner to provide an assurance and consulting services that adds value to
the Municipality and improves its operations.
Composition:
The Department is one independent unit that reports to Council.
57
Staffing Position:
Objectives:
- To improve financial management and accountability to ensure compliance with the Local
Government Act and Local Government Financial and Accounting Regulations and other
existing laws.
- To strength the internal control system and accounting procedures
- To provide assurance and consultancy services on the adequate and effectiveness of the
control, risk management and governance processes so as to add value.
Strategies:
- Regular audit visits to departments and institutions funded by Government.
- Site visits for projects under implementation.
CROSS-CUTTING ISSUES
The definition of Poverty embraces various aspects of the failure to defray the costs of a genuine
human life, hunger, sub-standard housing, disease, inability to participate freely in the life of the
community because of the accumulated burden of handicaps, exploitations/humiliations,
abandonment of any ideas of a future, inability to build a future and inability to build the future
generally.
In order to address poverty effectively, it is important to understand the nature and extent of the
problem that affects the livelihood of the population.
58
This section presents and characterizes the key development challenges and poverty issues, their
causes and effects from the Municipal point of view. They are derived from the numerous studies
conducted by the Municipal Council in collaboration with UBOS and other agencies. It is also
derived from the numerous other reports available in the registry.
2.4.2. Indicators of Poverty in the Municipality and actual problems that are leading people into
poverty.
- Poor housing/accommodation
- Food insecurity - Early marriage
- Dependency - Low life expectancy
- Poor hygiene and sanitation
The general poverty situation in the Municipality is not empirically defined but some indicators show
that high levels of poverty still persist. This affects the level of community contribution to the
development process in the entire setting. However, there are diverging levels of poverty from
Division to Division, ward to ward and village to village.
High poverty pockets are evident in the Division of Eastern and Southern in the extreme ends of the
Divisions. The most vulnerable poor include: widows, vulnerable children, PDWs and HIV/AIDS
affected households.
The causes of poverty in the Municipality include diseases especially malaria and HIV/AIDS, Land
shortage, exhausted soils which cause dwindling yields year after year.
Basing on the selected indicators of poverty in the Municipality, it is clear that the most affected areas
and groups exist in the poverty pockets below in the table.
59
Table 18: POVERTY AND LIVELIHOOD ISSUES ANALYSIS
Poverty Causes Effects Solutions
Issue
Hygiene and Low incomes Poor standards of Hygiene and
Sanitation Cultural values living sanitation campaign.
60
Low investments
Public outcry High Tuition Fees High dropouts Sensitization
on tuition High investment costs especially girls Support UPE, USE
fees Many Government taxes Poor performance and other education
Secondary and programmes
Tertiary Involve Parents in
Institutions School management
Unpleasant casual
employment like
house maids
High street
children
Illiteracy Culture: that bias to girl Lack of Promote FAL
education, Low income and Employment programme
Polygamy Limited capacity Sensitize
to productive communities to
activities change attitude on
Large families Girl education.
Low incomes Unemployment Dependency Equip peasant with
at household Lack of saving culture Low saving and faming skills
and investment law investment Promotion of IGA’s
Idleness and High morbidity and joining micro-
Drunkardness Disease and mortality finance institutions.
Lack of access to Inadequate basic Increased economic
economic factors of facilities at opportunities for
production. households women
Poor attitude towards Home improvement
work. campaigns
61
Table 19: Actions undertaken and proposed by sectors and LLGs to reduce poverty
Sector Poverty Concern/Issues Actions Undertaken Proposed Actions
Management Inadequate capacity for Developing skills of Build capacity of Municipal
the various stakeholders. LLGs, Municipal, and Officials and other
other stakeholders through stakeholders to facilitate
training. service delivery.
Low incomes among the Award of contracts to Award of contracts to
population. prospective local prospective local contractors.
contractors for goods,
services and works.
Trained leaders of women, Training in business skills and
youth, and PWDs in entrepreneurship.
project proposal writing
and management of IGAs
Finance Low local Revenue Mobilization and Revenue enhancement for
sensitization of increased local revenues.
stakeholders on new
revenues and their roles.
Production - Low incomes of - Provision of high quality - Access to high quality
Agricultural Farmers. inputs to increase inputs
productivity of crops and - Control of animal and crop
- Low Involvement of hence profits. pests and diseases.
the population in - Training of farmers on - improved infrastructure
Agriculture programs. crop pests and diseases. (accessibility).
- Provision of Advisory - Provision of high quality
and Technology inputs to increase productivity
Development Services of crops and hence profits.
- Training of farmers on crop
pests and diseases.
- Provision of Advisory and
Technology Development
Services
- Livestock Improvement.
Works and - Inaccessibility to - Opening up new roads. - Opening up new roads.
Technical markets. - Routine maintenance of - Routine maintenance of the
Services - Poor Hygiene and the existing roads. existing roads.
sanitation - Construction of safe - Construction of safe water
- Unplanned water systems. systems.
urbanization -Sensitization of -Sensitization of communities
communities on O&M and on O&M and ownership of
ownership of facilities. facilities.
Education - High illiteracy levels - Mainstreaming education Mainstreaming education
and Sports - High school dropouts. policies. policies.
- Improved infrastructure. - Improved infrastructure.
- Implementation of UPE - Implementation of UPE and
and USE. USE.
62
- Payment of capitation - Purchase of instructional
grants to schools. materials to reduce the burden
- Construction of pit of poor parents.
latrines. - Payment of capitation grants
- Sensitization of to schools.
education stakeholders. - Construction of pit latrines.
- Support supervision and - Senisitisation of education
inspection of schools. stakeholders.
- Support supervision and
inspection of schools.
63
Strategies to Address Poverty
Though poverty is still rampant in the poverty pockets, elsewhere in the Municipality there is an
indication of a positive change out of poverty as a result of different strategic interventions put in
place.
This is manifested by rapid growth of different centres like Kagashe, Marumba and many
others in the country side whose number of buildings, shops, bars and agriculture processing
plants have increased.
Social services in the Municipality have improved through a number of projects i.e. water and
sanitation facilities, health centres, TASO, NAADS and Compassion activities. Functional
Adult Literacy has increased the level of literacy among the population. Primary Health Care
services.
Agricultural production has increased in the peri-urban areas. Improved crop varieties like
Bananas, Cassava, Fruits, Sweet potatoes, Vegetables are being grown. Livestock husbandry
has improved through increased pigs, introduction of new breeds of poultry and goats through
NAADS funded activities.
64
2.5.1 Household/Production Division of Labour
Data was collected from households of all wards looking at prominent Prevailing Areas: Production,
Consumption and Management aiming at knowing males and female’s participation in provision of
labour in production, cooperation in household care/home activities. Six major crops grown in
Rukungiri Municipality were considered. The findings are presented in the table below:
It is only in respect of coffee that more men than women participated in planting, weeding &
harvesting. For the rest of the crops more women than men participated. When it came to selling;
more men than women participated in respect of two crops which bring in the biggest income i.e.
bananas and coffee.
The data below was collected from 50 household in different villages of Rukungiri Municipality
during the period early – mid June 2014
65
Table 21: Gender Resources Access, Control and Ownership.
Access Control Ownership
Resources
Men Women Men Women Men Women
Land 49 33 46 25 48 10
Livestock 47 32 38 23 45 9
Radio 43 42 42 27 45 10
As presented in the above table; men have more access to land and livestock than women, men and
women have equal access to radio. More men than women have more control over land, livestock and
radio. More men than women own land, livestock and radio. More men than women own the strategic
assets of land, livestock, and radio (Information). Fortunately, as seen from table 6 above, men and
women have almost equal access to radio thus Radio should therefore be used as a strategy to
sensitize the community that both men and women should strive to own the strategic assets of land,
livestock and radio so that they can invest, produce and make money and become equal partners in
the development of Rukungiri Municipal Council in particular, Rukungiri District in general and
Uganda as whole.
Heads of Departments 6 1
66
2.5.4 DEPARTMENTAL GENDER ANALYTICAL MATRIX
During the participatory planning and gender consultations, stakeholders identified various sectoral
gender issues, outlined below by sectors, along with the development concerns and strategies to
mitigate the gender issues as shown in the table below.
67
AND SPORTS facilities for the girl child absenteeism and drop facilities in schools.
in schools. out of the girl child. - Training of Senior
- Senior Women Teachers - Girls not adequately Women Teachers.
do not have adequate guided and counseled.
knowledge on counseling
requirements of the girl
child.
HEALTH Men not showing interest Inappropriate family Sensitization of males on
SERVICES in family planning. size, poor maternal family planning.
health and poverty
HIV/AIDS is one of the top causes of morbidity and mortality in the Municipality thus impacting on
the poverty levels. The number of orphans, widows and widowers has increased because of
HIV/AIDS. The amount of time lost during funerals, looking after the terminally sick, expenditure
on medication etc. lead to an increase in the number of people becoming poor in the Municipality.
68
Committed NGOs, CBOs and FBOs in the Municipality.
69
-Training in Life skills involves
HIV/AIDS prevention
70
-Scaling up of HCT and Health workers.
PMTCT services to HC IIIs -Monitoring and provision of
-Scaling up ART services to support supervision services to
cover all HCs IV. all sites providing the services.
-Distribution of medicines, -Distribution of medicines and
condoms and other supplies to other supplies on quarterly basis.
lower H/Units. -Supply HIV test kits to lower
-Organising Radio talk shows H/Units.
on HIV/AIDS, TB. -Organise Radio talkshows on
-Distribution of HIV test kits to VOD.
lower H/Units. -Dissemination of messages on
-Distribution of IEC materials. HIV/AIDS/TB through music,
-Film/Video shows on Dance and Drama.
HIV/AIDS/TB. -Film/Video shows on
-Organising MDDS on HIV/AIDS/TB.
HIV/AIDS/TB. -IEC materials distribution
-Review HIV/AIDS -Establishment of nutrition
performance with District Demonstration gardens at Health
leaders. Units
2.6.3 Challenges facing the delivery of HIV/AIDS services in Rukungiri Municipality include
the following:
The increasing number of orphans.
Limited HIV/AIDS testing kits.
Laboratory facilities not well established and facilitated
Limited access to ant-retroviral drugs.
Stigma amongst victims
Increasing number of rape and defilement
Most women are not yet empowered to say “NO” to unprotected sex
Treatment of opportunistic infections is expensive
Condom distribution channels not convenient for certain groups especially youths.
Under funding.
ARV, HCT, PMTCT Coverage still low.
Inadequate transport.
Poor male involvement.
Low TB case detection rate and CB-dots coverage.
Orphan care inadequate.
71
Recommendations:
Improve funding.
Expanding of ART, HCT and PMTCT coverage.
Community mobilization.
More support for orphans.
Transport for DHAC.
District to continue lobbying for HIV funding.
Male medical circumcision
Develop an HIV/AIDS strategic plan.
1. There is low male involvement in family planning and some men are opposed to family
planning practice by their spouses.
2. There are frequent stock outs of family planning methods in the health facilities especially the
injectable methods which is the most preferred methods.
3. Some health facilities belong to religious denominations that are opposed to modern family
planning methods which limit access to these services to the communities.
72
2.7.3 Stake holders of family planning
The key stakeholders in family planning in the district are Government through the network of
government health centres, the private not for profit health facilities under the churches, community
based organizations, the private sector through private clinics, drug shops and private maternity
centres.
In order to achieve sustainable development in the Municipality, environmental issues are put into
consideration during the planning process and project design stages. The quality of the environment
and Natural Resources on which the population in the Municipality depend is getting depleted thus
negatively impacts on their livelihoods and increases the level of poverty. Sound and air pollution,
poor garbage disposal and water erosion pertinent issues regards environment and below is a matrix
showing environmental issues/concerns in the Municipality. It deals with environment opportunities
available in the Municipality, the challenges and constraints and give a suggestion to the strategies
that can deliver environmental sustainability.
73
Table 25: Environmental Issues Analysis.
Environmental Location Causes Impacts Intervention
Issues
Soil Erosion Farmers zone Steep slopes Soil erosion Good drainage
Over fishing
Tree cover loss Kiyaga Lumbering Poor climate Re –afforestation
modification
Wetland Kataruka Encroachment Drainage of Demarcation of
degradation Agriculture the wetland wetland
boundaries
Soil fertility Nyaruzinga Brick laying
loss
Water pollution/ Nyakibale Car washing Water pollution Carrying out
lack of clean river Killing of water environmental
water species csreens for
Water born washing bays or
diseases any activity to
take place.
Poor Rukungiri Increased Bad smell Collection of
sanitation /poor central population Diseases garbage to a
refuse disposal market landfill.
Air and noise Kagogo and Factories present Air born Transfer of
pollution town centre diseases factories to a far
Ear destructions place.
74
2.8.2 Environmental opportunities
The use of Kataruka wetland since there is a natural made lake which can be developed as a
recreational site as well as a ramzar site.
There is still poor and inadequate funding for environment management activities
Development of an environmental action plan for municipal council.
Practical demarcation of wetland boundaries
Community sensitization, involvement and awareness on environmental management.
Increased address of environmental policies and laws to communities and creation or
formulation of bye laws.
There is population increase hence increased pressure on environmental resources
Some resources such as wetlands seem to belong to everybody or nobody thus rendering them
prone to over exploitation.
Some community individuals are still adamant and pay no respect to natural resources
Conservationists are still envisaged by communities as saboteurs and anti-development
especially when they are ensuring environmental compliance
High demand and ready market for these resources such as the demand for mud fish as a bait
in major fishing areas makes it hard to control mud fish exploitation
Lower local governments still seem not to appreciate that they have full responsibility over
natural resources management in their areas of jurisdiction.
Encroachment on some resources such as wetlands
Some developers want to carry out development outside specified standards
75
2.9 STAKEHOLDERS ANALYSIS
Local Government service delivery and development are comprehensive and needs efforts of
stakeholders. Stakeholders are people who are affected by the impact of activities and those who can
influence the impact of the activities in a given area and period. Stakeholder management is critical to
the success of every project in an organization.
2.9.1 Rukungiri Municipal Council local Government has the following stakeholders:
- Rukungiri Municipal Local Community
- NGOs, CBOs and FBOs
- Political Leadership
- Private sector
- Municipal public servants
- Central Government
- Donor community
76
CHAPTER 3: FIVE YEAR DEVELOPMENT PROGRAMMES
3.1 BROAD MUNICIPAL DEVELOPMENT PROGRAMMES AND PROJECTS OVER THE 5 YEARS.
Management
- Recruitment of staff.
- Rolling over of the capacity building Plan.
- Networking with Central Government and other Development Training opportunities.
- Processing submissions for staff.
- Training of staff.
- Regular staff meetings.
- Processing and payment of salaries, allowances and terminal benefits.
- Planning for and allocation of offices and equipment to relevant staff.
- Monitoring and evaluation of programmes and LLGs.
- Support services to departments and Lower Local Governments.
- Processing payments.
- Enforcement of laws, rules, regulations and guidelines.
- Coordinating meetings.
- Dissemination of Public Information to all stake holders.
MANAGEMENT
Municipal Strategies Activities Indicators Indicative Budget Year Implementing
Objectives agency
(Department/s-
county
1 2 3 4 5 Gvt Donor Lead Collaborati
ng
77
To have Recruitment - Recruitment of -No. of staff
489,309,600
513,775,080
539,463,834
566,437,026
594,758,877
sufficiently and retention staff. recruited
motivated, of qualified - Formation of -Capacity
well staff capacity building building in Manage
equipped Plan. place. ment
and trained Recruitment - Networking with -No. of
manpower. and Central network
placement of Government and formalized.
staff other Development -No. of staff
Training submissions
Staff opportunities. made
performance - Processing -Staff meeting
appraised. submissions for minutes
staff. -Salaries paid
- Training of staff. by 28th of
- Regular staff every month
meetings. -No. of staff
- Processing and appraised.
payment of salaries,
allowances and
terminal benefits.
-Planning for and
allocation of offices
and equipment to
relevant staff.
78
-Support services to -No. of
departments and meeting
Lower Local coordinated.
Governments.
-Enforcement of -Laws, rules
laws, rules, guidelines
regulations and enforced
35,080,290
36,834,119
38,675,825
40,609,616
42,640,097
guidelines.
-Coordinating
meetings.
79
FINANCE AND PLANNING
Municipal Strategies Activities Indicators Indicative Budget Implementing agency
objectives Year (Department/Divisions)
1 2 3 4 5 Govt Donor Lead Collaborating
To identify, Carry out Enumeration Radio talk
collect research on assessment & shows held
revenue for possible new collection of and
service sources of local Local revenue. sensitization
12,000,000
13,000,000
14,000,000
15,000,000
16,000,000
delivery. revenue and Sensitization of carried out in
maintain the stakeholders on Divisions
existing ones. tax payments
&
Monitoring of
revenue FIN.
collection.
Train staff on Preparation of A copy of
modern local revenue revenue
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
methods of enhancement enhancement
books keeping plan and plan produced FIN.
financial and changing and presented
accounting policy. to council for
regulations. approval.
Preparation of Annual budget
budget and and work
annual work plans 3,000,000 FIN.
4,000,000
5,000,000
6,000,000
7,000,000
plans to be approved.
presented to
council.
80
Timely Procurement of Books of
production and books of Accounts and
submission of accounts e.g counter foils
accountability books, ledgers, procured.
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
documents. abstracts and FIN.
counter foils
for the
Municipality
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
committees B produced
including and submitted
performance to MOFPED.
form B &
submission to
MOFPED &
other line
ministries.
To ensure Production of Annual
proper Annual Financial FIN.
management Financial Report 4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
and statements. statement
accountabilit Final Accounts produced and
y of public and submission submitted to
funds to the office of OAG by 30/9
Auditor
General
81
Servicing f Departmental
departmental computers FIN.
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
computers and serviced and
photocopiers. ant viruses
installed.
Payment of Staff
allowances for allowances FIN.
6,220,500
9,360,000
7,680,000
7,680,001
7,680,002
staff paid
Payment of E filing of
1,500,000
2,000,000
3,000,000
4,000,000
5,000,000
VAT & PAYE VAT and FIN.
to URA- PAYE returns.
Rukungiri
24,737,368
41,747,288
56,000,000
56,000,000
awarded
-No.of
projects
supervised
82
To promote Land issues Handling No.of
effective Addressed new applications
management of application handled.
land matters for land No.of titles MCC RMC
registration. produced.
18,000,000
20,000,000
20,000,000
7,958,000
7,958,000
Processing No.of
land titles. meetings
NB held.
meetings
Mobilizatio
n&
sensitization
Promotion of Hold Sensitize Sensitization
participatory regular political meetings
democracy and meetings leaders on held.
democratic and their roles & No.of
116,556,878
116,556,878
130,000,000
148,000,000
150,000,000
governance consultatio responsibilit complaints
ns ies. attended to
Attending to and referred. MLG MCC
public No.of
complaints policies
& problems. initiated &
Policies in passed.
initiated.
Promotion of Review Meetings. No. of
accountability of PAC reports
public resources reports and reviewed. GOU
3,000,000
3,000,000
4,000,000
5,000,000
5,000,000
Auditor
General’s
report
83
HEALTH
Municipal Strategies Activities Indicators Indicative Budget (Million) Implementing agency
Objectives Year (Department/s-County)
3,955,000
4,500,000
5,000,000
and quality of mobilizatio contractors rehabilitated
6,000,000
7,000,000
health n, -Rehabilitation of 2 -No. of HCs
infrastructure rehabilitati Health facilities. upgraded.
on. -Upgrading of HC -No. of
IV to hospital supervision
-Supervision of visits.
rehabilitation work
- Completion of 1
Twin staff house.
To ensure Timely - Ordering No. of
142,547,798
145,000,000
150,000,000
155,000,000
availability of supply medicines on time, Health
160,000,000
safe and proper distributing facilities
efficacious storage , medicines to health receiving
medicines and distribution units, support medicines
other health and supervision of on time
supplies in the dispensing medicine use, -No. of
health storage and health units
facilities. dispensing. with no
stock out of
medicines
84
To ensure Coordinati -Holding regular No. of
strong public on & meetings. meetings
760,000
850,000
800,000
900,000
private advocacy -Training health held
950,000
partnership meetings. workers on standard -No. of
guidelines and health
financial workers
management, trained
support supervision No. of
of PNFP health health
units. facilities
receiving
grants.
To ensure Strengthen MCH-ANC, -No. of
access to HPE, conducting deliveries MoH
Uganda Private deliveries PNC, conducted.
National MCH PMTCT, HCT, - No of
Minimum services, immunization, TM clients
Health Care control of of ailments in tested for
Package. cmmunicab pregnancy, IMCI, HIV.
le diseases, adolescent friendly -No. of
improve health services, care mothers
CB-dots, of new born , HPE receiving
case procurement of IEC, IPT2.
detection materials & their -No. to
of HLTN, distribution. Radio Radio
improve talk shows on all programmes
vector programs. .
control , Prevention of mental -No. of
strengthen illness. Prevention of school
HIV oral conditions. visited.
prevention, Control of -No. of
care and communicable patients
support diseases. Treatment treated.
activities, of eye condition . -No. of
control of Treatment of households
85
non communicable with pit
communica diseases. ENT,latrines.
ble Home improvement No. of
diseases. campaigns, epidemic
sanitation promotion detected and
campaigns, school controlled.
health promotion, -No. of
Epidemic disaster
cases of
prevention control NCDs
non communication, detected and
mental illness,
treated.
management -No. of oral
treatment, TM & and dental
management of oral cases
conditions, control treated.
oral condition of life
-No. of TB
styles., TM of oral cases
/dental conditions detected.
-No. of
AIDS
patients on
ART.
-No. of
radio
programmes
held
-No. of
ITNS
distributed.
-No. of HIV
tests done.
-No. of
MARPS
reached.
To ensure Planning, Support supervision, No. of
86
functionality supervision procurement of 5 meetings
of the health . Capacity computers, internet held.
systems in the building unit, recruitment of -No. of
district. coordinatio H/Ws(AHE, mental computers
n. Data health nurses in all procured.
manageme HC III). Hold review -No. of
nt meetings with H/Ws
compilatio incharge and other recruited.
n. Analysis categories of H/Ws. - No. of
and Hold technical supervision
reporting planning meetings. visits done.
Identify and sponsor - No. of
further training of plans made.
H/Ws. To collect - No. of
reports in time. reports
Compile, analyse made and
and report to submitted.
relevant authorities.
Support supervision
on data management
in the district M/E
87
EDUCATION DEPARTMENT
Indicative budget per year Implementing Agency
(Department)
Sector Strategies Activities Indicators 1 2 3 4 5 Gov’t Donor Lead Collaboration
objective
Consolidating Regular Routine Quarterly school
12,532,00
0
13,000,000
13,500,000
14,000,000
14,500,000
and monitoring school inspection
Improving on -supervision inspection reports &
gains made in and submission
Education
academic inspection of -Conducting
performance in schools PLE and -Examination
the last year -Evaluating Municipal results and
from 98-99% performance Examinations reports
of teachers
and pupils
throughout
the term and
end year
examinations
Improving Train Training of -No. of games
participation in teachers games teachers and
sports, music teachers and scouts leaders
Dance and Organize scouts leaders trained
Education department
drama scouting school -No. of schools
and girl competitions Holding co participating in
1,500,000
2,000,000
2,500,000
3,500,000
4,000,000
guiding in co- curriculum co-curricular
curricular competitions competitions.
activities at - Level of
Municipality competition of
& national schools
levels
88
To improve the -Provision of -Provision of No. of teachers
school learning toilets toilets houses
Education Department
environment construction construction constructed
210,000,000
215,000,000
220,000,000
225,000,000
230,000,000
of teachers of teachers Improved
house house sanitation and SFG
hygiene.
Provision of
lightening
conductors &
furniture
89
WORKS
226,776,730
229,000,000
230,000,000
227,000,000
228,000,000
Municipal roads - \kirite,Kyatoko motorable
road Buhumuriro,
network Rwempitsi-Kagashe,
Kakonkoma-Nshure
and Independence
road.
To increase Maintenan Construction of Road easily WKS
maintainab ce of water crossings motorable Dept
le roads and points (culverts) by heavy
municipal bridges along Rwakabengo- vehicles
road Nshure
network road,Kakonkoma,Ka
gashe-
Rwanyambari,Kinya
sano-
Kigina,Kagashe-
Karere,Kakyeka-
44,000,000
42,500,000
43,000,000
43,500,000
44,500,000
Nyabikuku,Rwamah
wa,Butimba,Rugara
ma,Ndimbirwe,Vall
ey Nyerere
Kifunjo,Stadiun
bend,Furuma-Karere
improvement of
Kyatoko,Rwakaben
go bridges.
90
To increase Maintenan Routine Road WKS
maintainab ce of maintenance of surfaces in Dept
220,090,000
225,000,000
230,000,000
235,000,000
240,000,000
le roads 316km of Municipal good
municipal roads condition
road
network
To improve Constructi Construction of WKS
housing/offi on and administration block Dept
ce maintenan
240,000,000
245,000,000
250,000,000
255,000,000
260,000,000
infrastruct ce of
ure in the housing
municipalit infrastruct
y. ure
To - To hire , repair of vehicles Operational WKS
maintain specialize and road equipment, office and Dept
vehicle d people tyres, and other vehicles/
fleet, plant to consumables. Plant
and maintain
equipment vehicles
and road
equipment
. - Train of
72,500,000
73,000,000
74,000,000
74,500,000
73,500,000
labour
based
routine
maintenan
ce
contractor
s.
91
To have an Productio Monitoring and Planned
orderly and n of supervision, environmen
15,000,000
15,500,000
16,000,000
16,500,000
17,000,000
organized structure sensitization t
town and programmes
detailed
plans
92
COMMUNITY BASED SERVICES DEPARTMENT
Municipal Strategies Activities Indicators Indicative budget per year Implementing agency
objectives (departments)
Year
1 2 3 4 5 Gov Donor lead collaboratin
t g
Objective 1
Institute Provide Implement People CBS
social different social social /cash benefiting
protection protection transfer from cash
33,767,000
34,000,000
34,500,000
35,000,000
35,500,000
measures measures for programme to transfer,
that reduce The Youth, the identified PWDs Grant ,
vulnerabilit Women, poorest section Women’s
y and Children and of the grant
enhance People with population Support to CBS
2,360,000
2,500,000
3,500,000
productivity Disabilities Women,
3,000,000
4,000,000
of the Youth and
people PWDs
councils
Carry out Data on CBS
Community PWDS
Based collected,
1,452,000
1,500,000
2,000,000
2,500,000
3,000,000
Rehabilitation support
supervision
done.
Objective 2
Promote Promote Ensure gender Gender issues CBS
Gender Gender responsive highlighted in
equity and mainstreaming budgeting and plans and
Women in Gender budgets,
776,000
800,000
850,000
900,000
950,000
Empowerm Development responsive Monitoring
ent plans, monitoring and and
programmes evaluation evaluation
and projects done.
93
Minimize Conducting Trainings CBS
Gender based Gender done
violence and awareness
2,000,000
2,500,000
3,000,000
1,036,000
1,500,000
promote trainings
Women’s
rights
Objective 3
To ensure Carrying out Conducting Learners CBS
Effective the functional Functional instructed
community Adult Literacy Adult Literacy
2,588,000
3,000,000
3,500,000
4,000,000
4,500,000
mobilization programme classes
and
participation
in
developmen
t initiatives
Objective 4
Increase ensuring Inspection of Workplaces CBS
1,000,000
800,000
850,000
protection improved workplaces inspected
900,000
950,000
of workers. compliance
with labour
standards
94
PLANNING UNIT
PROGRAMMES OF ACTION AND DEVELOPMENT PROJECTS FOR THE 5 YEAR MDP 2015/16 – 2019/20
Municipal Strategies Activities Indicators Indicative Budget Implementing
objectives Year agency
(Department)
1 2 3 4 5 Gov Donor Lead Collaborating
Training of staff t
1. To facilitate in planning. - Organizing and Budget MPU
and coordinate holding the Conference
3,500,000
4,000,000
4,500,000
5,000,000
5,500,000
the process of Production of Municipal held √
Development work plans and Budget
Planning and reports conference.
Budgeting both - Coordinating Annual plans MPU
4,500,000
5,000,000
5,500,000
6,000,000
6,500,000
at the Strengthening the preparation and budgets
Municipal coordination of of Annual Work in place √
Council and Departments and plans.
Division Development
Levels - Coordinating One BFP MPU
Partners.
the preparation prepared and
2,100,000
2,500,000
3,000,000
3,500,000
4,000,000
of BFP and submitted √
submissions
made
Multi sectoral Quarterly MPU
Monitoring of PAF reports
1,380,000
1,500,000
2,000,000
2,500,000
3,000,000
PAF activities √
in the
Municipality.
95
AUDIT
17,228,800
17,500,000
18,000,000
18,500,000
19,000,000
with the LG Act and of departments, projects. visits.
LG Financial Divisions and -Enforcement -Adherence to
Accounting institutions. of internal internal Int.
Regulations and controls controls Audit
other existing laws -Preparation -No, of
of quarterly quarterly audit
reports. reports.
- Attending - No. of
LG Internal meetings
Audit attended.
meetings.
96
CHAPTER 4:MUNICIPAL IMPLEMENTATION PLAN FOR 2015/2016
4.1 The Municipal Annual Action Plan for FY 2015/2016. The Municipal Annual Action Plan 2015/2016 is linked to the
BFP and the Annual Budget and work plan for 2015/2016.
MANAGEMENT
Objectives Annual activities Location Indicator Time Frame Indicator Budget Implementing
(Quarterly) agency
(Department)
1 2 3 4 Govt Donor Lead Collaborating
To have a - Payment of salaries to -Salaries paid HRM
sufficient Staff and political monthly
motivated, leaders Municipal -HRM office run and
well -Running and Wide managed
equipped management of HRM -End of year party
and trained Office held
manpower -Holding of end of year -pay change reports
122,327,400
122,327,400
122,327,400
122,327,400
489,309,600
party prepared and
- Preparation and submitted
submission of pay
change reports
To transfer Disbursement of grants Municipal -Funds disbursed to TC’s
central to LLGs wide LLGs Office
government
funds to
LLGs
97
To establish Updating and District records
an effective computerizing data. managed properly.
records - Writing reports and Municipal
managemen filing vital documents. wide
t system - Retrival of
information Record
35,080,290
- Classifying and s office
8,770,072
8,770,072
8,770,072
8,770,072
categorizing
information.
- Dispatching mails
98
FINANCE
Objectives Annual activities Location Indicator Time Frame Indicator Budget Implementi
(Quarterly) ng agency
(Departme
nt)
1 2 3 4 Gov’t Donor Lead Collaboratin
g
To ensure - Preparation of - No. of training reports.
proper budgets and annual - No. of staff trained
management workplans. - Annual budget and
and - Procurement of workplans.
accountability books of accounts. Municipal - No. and type of books
750,000
750,000
750,000
750,000
3,000,000
of funds - Production of wide of accounts procured.
monthly and - No. of reports
quarterly reports. - Final accounts
- Compilation of produced.
data for Board of - Board of Survey report
Survey of reports. in place.
-Payment of Municipal
deducted money to wide
consolidated fund
375,000
375,000
375,000
375,000
1,500,000
-Payment of VAT
on markets
-Filling of books of
accounts
-Preparation and Municipal
submission of final wide
accounts 1,500,000
1,500,000
1,500,000
1,500,000
-Servicing of
6,000,000
departmental
computers and
laptops.
-Compilation of
accountabilities
99
To identify - Procurement of - No. of different
and collect counterfoils. counterfoils procured
revenue for - Preparation of and delivered.
service Local Revenue Municipal - Local Revenue
delivery enhancement Plan Wide enhancement Plan and
and charging charging policy
policy. produced.
- Enumeration, - No. of tax payers
assessment and enumerated and
collection of Local assessed.
Revenue. - Amount of revenue
- Sensitization of collected.
stakeholders on tax - No. of sensitization
3,750,000
3,750,000
3,750,000
3,750,000
payments. meetings.
15,000,000
-Collection, - No. of radio talk shows
supervision and held.
Monitoring of - No. of monitoring
revenue. visits and reports made.
To ensure -Presentation Municipal -Draft budgets and
proper &approval of draft wide workplans approved
budgeting and budgets and annual -LREP prepared and
planning workplans to approved
council
-Submission of
approved budgets
to central
government
1,000,000
-Preparation and
1,000,000
1,000,000
4,000,000
1000,000
submission of local
revenue
enhancement plan
and charging policy
100
HEALTH
2,226,000
2,226,000
2,226,000
2,226,000
8,904,000
we HCII,
Karangaro
HCII
To properly -Payment of Municipal -no of visits RMC MOH
run and salaries wide made
manage the -Suppoprt - drugs and
health care supervision and vaccines
management monitoring procured
services -Delivery of -HIV/AIDS
drugs and services
vaccines delivered 2,087,250
2,087,250
2,087,250
2,087,250
8,349,000
-Planning and
review meetings
-Rolling out the
new HMIS
-Supporting
PMTCT ,ART,
HCT and
immunization
-Training on
HIV/AIDS
101
Improve urban -training health Municipal -No Of RMC MOH
Environmental worksers wide worker
protection and -Functionalising trained
sanitation VHTs -No of VHTs
-Recruitment of functional
10,637,459
health workers -strengthened
2,659,365
2,659,365
2,659,365
2,659,365
-Coordination of coordination
health care systems.
delivery
To strengthen -Improving Municipal No. of
Human coordination of wide deliveries
Resource for health care conducted
He alt delivery -No of
-Conducting inpatients and
294,450,000
73,613,500
73,613,500
73,613,500
73,613,500
deliveries in the out patients
NGO hospitals that visited
the facilities
Enhance Municipal
coordination wide
25,450,000
and
6,365,000
6,365,000
6,365,000
6,365,000
communicatio
n for improved
Health care
102
EDUCATION
Objective Annual Activities Location Indicators Time frame Indicative Implementing
(Quarterly) Budget (Department)
1 2 3 4 Govt Donor Lead Collaborating
To facilitate -Payment of Municipal No. of teachers paid
1,359,307,00
1,359,307,00
1,359,307,00
1,359,307,00
5,437,228,00
and improve Primary teachers’ wide
primary salaries
teaching -Coordination of
services education office
0
To improve -Disbursement of - Improved
and strengthen UPE grants to performance.
the primary schools - No of
management - Effective Municipal accountability
of 15 teaching and wide reports.
29,134,300
Government learning.
Education
7,283,575
7,283,575
7,283,575
7,283,575
Aided Primary -Accountabilities
Schools of UPE Funds.
Education
3,792,500
948,125
948,125
948,125
500,000
- Passing co- - No of co-
curricular curricular
competitions competitions held.
103
Promotion of -Payment of Municipal No. of staff paid
education allowances for wide salaries
management staff in the -education activities
services education office coordinated
-workshops and -No of reports
meetings submitted
11,678,100
-Submission of
Education
2,919,525
2,919,525
2,919,525
2,919,525
accountability
reports
-conducting PLE
104
WORKS
Objective Annual Location Indicators Time frame Indicative Implementing agency
Activities (Quarterly) Budget ‘000’ (Departments/s-
county)
1 2 3 4 Govt Donor Lead Collaboratin
g
Operation of -12 months H/Qs at No.of
District Roads salary paid to specified meetings
Office Natural Resource venues conducted.
To raise safe Staff District No.of
water - Field wide participants
coverage supervision visits trained.
Maintain done. staff
District and -50 Road Gang appraised
community Leaders trained (forms filed)
access roads. in road
maintenance.
- Annual
Municipal Roads
Inventory and
Condition
123,098,000
30,774,500
30,774,500
30,774,500
30,774,500
survey(ADRICS)
carried out
(Traffic counting,
structure servey
and road
consition servey).
- Municipal
Works Depatment
road office
managed.
- Bid documents
prepared for
Municipal
105
Promotion of -192.2km Gravel
Community and earth
Based roads.kms
Management maintained on
318,397,000
79,599,250
79,599,250
79,599,250
79,599,250
to Road Municipal roads
Maintenance - More Plants
and machinery
maintained
Municipal -Money
16,860,500
16,860,500
16,860,500
16,860,500
67,442,000
Community transferred to the
Access Road 3 divisions
mainatenance
(LLS)
106
Promotion of -1 (water and MWO
Community sanitation week
Based to be held in
Management, March 2016 and
Sanitation activities will be
and Hygiene Municipal wide)
-14 (Advocacy (7
Radio programs
consucted on
Radio Rukungiri,
3 drama shows
- 5 (Private
sector
stakeholders
trained in
preventive
maintenance,
hygiene and
sanitation).
24,580,000
6,145,000
6,145,000
6,145,000
6,145,000
- 135 (user
committee
members trained.
- 30 (Water user
committees
formed)
- Community
sentised on
critical
requirements of
sanitation by
conducting 11
visits.
107
PLANNING UNIT
Objectives Annual activities Locatio Indicator Time Frame (Quarterly) Indicator Implementing
n Budget agency
(Department/
Division
1 2 3 4 Gov’t Dono Lead Collaborati
r ng
2,406,000
2,406,000
2,406,000
2,406,000
Assessment for
2015/2016 conducted.
108
Municipal -Unit staffed with -No. of reports
Planning qualified staff. made
-12 minutes of TPC No. of TPC
meetings recorded. minutes recorded MPU
-BFP 2016/2017
prepared and submitted
to MoFPED and
LGFC.LGBFP
approval
-Annual Work plan for
2016/2017 prepared.
-Quarterly monitoring
of the implementation
of MDP
1,846,000
1,846,000
1,846,000
1,846,000
-Budget Conference
held at Municipal
Headquarters.
Operational -3 Divisions of Eastern, MPU
Planning Western and Southern Participatory
1,097,940
1,097,940
1,097,940
1,097,940
supported in planning carried
participatory planning. out in all
Divisions.
Monitoring -3 LLGs of Western, -An integrated MPU
and Eastern, and Southern M&E system
Evaluation of monitored and -A reporting
Sector Plans mentored. matrix in place.
-PAF activities
1,305,000
1,305,000
1,305,000
1,305,000
monitored and reported -PAF and
on. LGMSD projects
monitored
109
INTERNAL AUDIT
Objectives Annual activities Location Indicator Time Frame Indicator Budget Implementi
(Quarterly) ng agency
(Departme
nt/Divisions
1 2 3 4 Gov’t Donor Lead Collaboratin
g
5,000,000
5,000,000
5,000,000
5,000,000
Kampala for institute
of Internal Auditors
Uganda Chapter.
110
Internal Audit -By 15th (Quarterly
Internal Audit
Quarterly report
submitted by 15th after
the quarter.
-28 (Internal
department audits
conducted.
-4Quarterly Internal
Audit reports prepared
and submitted to
Council, relevant
3,567,760
3,567,760
3,567,760
3,567,760
ministries and
departments.
111
CHAPTER 5:MONITORING AND EVALUATION ARRANGEMENTS.
5.1 Introduction
This section provides an overview of the measurements, analysis and reporting needed to monitor and
evaluate the MDP. The detailed monitoring and evaluation (M&E) strategies, including the results
and M&E framework, the plan for data collection, analysis and storage, reporting flows and formats,
the plan for the communication of MDP results and review, the capacity building plan as well as the
implementation schedule.
- To establish a well-coordinated Municipal wide system for tracking efficiency and effectiveness in
service delivery; and enhancing transparency and accountability in use of Public Resources.
112
5.3 Justification of the M&E frame work and methodology.
5.3.2. Methodology
A well-coordinated Municipal wide M&E system for effective tracking evaluation and feedback on
MDP implementation and results will be established. A participatory approach that entails the
involvement of all key actors to fully internalize and own the system as well as use the results to
inform their actions.
This strategy institutionalizes the use of M&E as a tool for better public sector management,
management, transparency and accountability geared to support the overall strategic direction of the
MDP and achievement of results.
Currently few departments produce annual performance reports. It’s important that all sectors
produce performance reports owning their performance, challenges and the proposed solutions. Those
reports will be produced by August of the flowing financial year and this will be the input to the
budget conference and chief executive will reprimand Heads of Departments that do not submit their
reports in time.
5.6. Framework implementation strategy: The implementation framework has been developed and
contains key intended results of the strategies and key performance indicators. It contains a full list of
113
indicators, data collection methods, timetables and responsibilities. It contains an evaluation plan
detailing specific policy and programme evaluations to be conducted during the life of the MDP.
114
ESTIMATES IN UGANDA SHILLINGS (MILLIONS)
5.7.1 FINANCING
There is need to undertake infrastructures to mobilize resources for operational zing the framework. There is need to search support
from the Development partners and the Municipality own locally generated sources of financing and other support from the central
government.
5.7.1. Local Governments: The Municipal will be responsible for monitoring service delivery and accountability for results. The
municipal departments will be responsible for reporting on progress of implementation and achievement of planned outputs. This will
involve reporting on the process of implementation focusing on implementation constraints.
116
5.7.2. Community Level actors: These comprise of Divisions, community based NGOs,
administrative units. They will provide information on delivery of various services, transparency of
resources given and challenges and gaps experienced in delivery of various services. They also
validate outcomes of implementation of the MDP in their respective areas.
5.7.3. Household actors: These comprise of individual citizens and constitute the primary
beneficiaries of the DDP strategies and initiatives. The role of citizens is to provide information on
the MDP implementation and delivery of target outputs as well as validating results for better service
delivery and accountability mainly through the Division Baraza’s.
5.7.4 Development partners: These will support the implementation of M&E activities, capacity
building for M&E and use of M&E products.
117
CHAPTER 6:
6.1 Introduction:
Creation awareness on the expected roles of stakeholders in the implementation of the plan, and
promotion of dialogue and generation of feedback on the performance of the Municipality.
6.2 Dissemination of the MDP and Annual Progress Report of the implantation of the MDP.
The MDP will be disseminated to the various stakeholders by the Municipality through a number of
means which shall include, print media, broadcast, workshops, seminars, meetings, mandatory notices
and the Municipal Website. The sector of information shall take the leading role in popularizing and
disseminating the information in the MDP to the stakeholders.
On the use print media, the Municipal Council shall secure funding for making a supplement in one
the local dailies in its 3rd year of implementation. This will be Orumuri Newspaper in the local
language due to its advantage of covering a big area of the Municipal Council, Division Councils and
the Technical Personnel plus posting of mandatory notices, pin conferences.
Annexes:
1. Below the budget line off LLG investments.
119
CHAPTER 7 PROJECT PROFILES
MANAGEMENT SUPPORT SERVICES
SECTOR MANAGEMENT
SUB-SECTOR HUMAN RESOURCE MANAGEMENT
PROJECT TITLE CAPACITY BUILDING
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPAL COUNCIL
LOCATION RUKUNGIRI MUNICIPALITY
PLANNED EXPENDITURE 16,885,600
SECURED FUNDS -
FUNDING GAP NIL
RECURRENT/EXPENDITURE -
START DATE: .JULY 2015 COMPLETION DATE JUNE 2016
Objective
To build capacity of Municipal officials and other stakeholders
To facilitate implementation of government programmes
Background
With decentralization a number of programmes have been devolved to Local Governments, moreover
the responsibility of quality service delivery and strategic decision making has been put to the Local
Government Officials. Government policy emphasizes participation of communities and stakeholders
in planning, decision making, supervision and monitoring. For this to be effected, capacity must be
built for the various players.
Technical description
The following types of capacity building will be done and these are career development, discretionary
capacity building and skills development. This will be done through:
Workshops, Seminars and refresher courses will be organized for the various sectors. Professional
short courses will be facilitated to boost performance of officials.
Study Tours will be facilitated to enable Municipal officials learn from other players.
Benefits Staff, political leaders and other stakeholder’s performance will improve.
Plan of Operation:
Capacity building activities will be coordinated by Human Resource Officer & Town Clerk,
recognized institutions of learning and other identified resource persons.
120
Budget and Financing plan
Sources of funds Expenditure by quarters Total
Q1 Q2 Q3 Q4
Rukungiri Mun.Council - - - -
LGMSD 4,221,400 4,221,400 4,221,400 4,221,400 16,885,600
Funds secured 4,221,400 4,221,400 4,221,400 4,221,400 16,885,600
Total 4,221,400 4,221,400 4,221,400 4,221,400 16,885,600
Monitoring and Evaluation:
Monitoring of activities under capacity building will be done by the council committee of finance and
administration.
SECTOR MANAGEMENT
SUB-SECTOR MUNICIPAL CONTRACTS COMMITTEE
PROJECT TITLE PROCUREMENT OF GOODS AND SERVICES
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPAL COUNCIL
LOCATION RUKUNGIRI MUNICIPALITY
PLANNED EXPENDITURE 8,400,000
SECURED FUNDS 8,400,000
FUNDING GAP NIL
RECURRENT EXPENDITURE
START DATE: JULY 2015 COMPLETION DATE: JUNE 2016
Objective
To procure goods, services and works in conformity with public procurement and disposal of public
accounts.
Background
Under the Local Government Public Procurement and Disposal of Public assets, regulation 2007,
Municipal Contracts Committee have come in place in accordance with the local government Act to
handle the procurement and disposal of assets in the Municipalities.
Technical Description
Advertising for good, services and works
Technical evaluation of tenders
Awarding of tenders
Monitoring and evaluation of projects
Benefits: The community will benefit by availing them goods and services. The municipality will
benefit by providing services to the community and fulfilling its mandate. The service providers by
earning profit.
121
Beneficiaries: Communities, Municipal local government and service providers
Plan of Operation:
The Municipal Contracts Committee members in liaison with the procurement and disposal unit and
the Evaluation Committee will implement the activities.
SECTOR MANAGEMENT
SUB-SECTOR COUNCIL AND STANDING COMMITTEES
PROJECT TITLE PROMOTION OF PARTICIPATORY
DEMOCRACY AND GOOD GOVERNANCE
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPALITY
LOCATION RUKUNGIRI MUNICIPAL HEADQUARTERS
PLANNED EXPENDITURE 1ST JULY 2015 - 30TH JUNE 2016
SECURED FUNDS 62,000,000
RECURRENT EXPENDITURE
START DATE: JULY 2015 COMPLETION DATE: JUNE 2016
Background
122
Under the LGS Act CAP 243, and the Constitution of the Republic of Uganda 1995, Local
Government Councils are established to exercise all political and executive powers and functions;
provide services, project the constitution and other laws of Uganda and promote democratic
governance and ensure the implementation and compliance with government policy.
Technical Description
Formulation of bye laws, policies and ordinances
Overseeing the enforcement of bye laws and ordinances
Approving budgets and plans
Appointment of members of statutory bodies
Monitoring and evaluation of government and donor projects
Benefits: Rule of law in place and good policies approved and implemented.
Feasibility Study:
The need assessment was carried out and gaps identified through councilors, Chairperson LC IIIs,
heads of departments and sectors, CSO, S/county administrative officers.
Plan of Operation:
The council will execute its mandate through the various standing committees, assisted by the various
departmental technical staff.
Monitoring and Evaluation Plan: Monitoring will be carried out by the Town Clerk.
123
WORKS AND TECHNICAL SERVICES
Objective:
To ensure that roads are regularly maintained in motorable conditions to foster social economic
development of the people through easy access to social services and markets for their agricultural
produce and goods.
Background
Experience has shown that when a road is rehabilitated or periodically maintained and no routine
maintenance is done, its general condition depreciates very fast. This has been proved by
observations on some rehabilitated roads. It was realized that there is a big difference between
sections where there is routine maintenance and where it is not. This has therefore, made us
undertake routine maintenance of Municipal roads with priority given to newly rehabilitated and
major roads. Some roads are beyond maintenance using manual labour. We have therefore, planned
to do mechanized maintenance.
Technical Description
Road condition assessment of all Municipal roads in addition to minor and spot repair
inventory.
Culvert and bridge inventory on all municipal roads.
Grading and shaping
Spot gravelling
Desilting of culverts and side drains
Excavation of offshoots and side drains.
Inspection, Spot Supervision and monitoring with compilation of field activity reports.
Benefits:
Easy access to markets.
Less maintenance costs on vehicles, motor cycles and bicycles.
Easy access to social amenities by service providers/ seekers and supervisors
124
Reduction of time waste by road users to get to their destinations.
Increase on traffic flow / attraction of new vehicles
Beneficiaries:
The community and other road users.
Feasibility study:
Not applicable.
Plan of operation
This project will start with assessment of roads condition by the Works Department, and preparation
of cost estimates and specifications for the road maintenance inputs.
Procurement requisition form 1 with appended cost estimates for road maintenance inputs shall be
submitted to Municipal Contracts Committee for approval.
Project execution by force account mechanism using the acquired road equipment.
125
Operation and Maintenance Plan
Project Output What is to be done Responsible Cost Remarks
officers
Maintained -To conduct regular site -ME If any
roads inspections on the -SAEO bottleneck
maintained roads to 6,228,000 identified it
ascertain any occurrence of should be fixed
any bottleneck. immediately.
Environmental Concerns:
Environmental Nature of the Mitigation measures
component affected environmental concern
Land -Soil erosion -Open many off shoots
-Grub during a dry season.
-provision of scour checks
-Loss of vegetation cover -Plant creeping grass
Objective:
To ensure that roads are regularly maintained in motorable conditions to foster social economic
development of the people through easy access to social services and markets for their agricultural
produce and goods.
126
Background
Experience has shown that when a road is rehabilitated or periodically maintained and no routine
maintenance is done, its general condition depreciates very fast. This has been proved by
observations on some rehabilitated roads. It was realized that there is a big difference between
sections where there is routine maintenance and where it is not. This has therefore, made us
undertake routine maintenance of Municipal roads with priority given to newly rehabilitated and
major roads. Some roads are beyond maintenance using manual labour. We have therefore, planned
to do mechanized maintenance.
Technical Description
Road condition assessment of all Municipal roads in addition to minor and spot repair
inventory.
Culvert and bridge inventory on all municipal roads.
Grubing and bush clearing
Spot gravelling
Desilting of culverts and side drains
Excavation of offshoots and side drains.
Inspection, Spot Supervision and monitoring with compilation of field activity reports.
Benefits:
Easy access to markets.
Less maintenance costs on vehicles, motor cycles and bicycles.
Easy access to social amenities by service providers/ seekers and supervisors
Reduction of time waste by road users to get to their destinations.
Increase on traffic flow / attraction of new vehicles
Beneficiaries:
The community and other road users.
Feasibility study:
Not applicable.
Plan of operation
This project will start with assessment of roads condition by the Works Department, and preparation
of cost estimates and specifications for the road maintenance inputs.
Procurement requisition form 1 with appended cost estimates for road maintenance inputs shall be
submitted to Municipal Contracts Committee for approval.
127
Operation and Maintenance:
This activity will be monitored / supervised from time to time to ensure that all the loopholes are
curtailed during implementation to ensure that the right job for effective results is achieved.
128
Environmental Concerns:
Environmental Nature of the Mitigation measures
component affected environmental concern
Land -Soil erosion -Open many off shoots
-Grub during a dry season.
-provision of scour checks
-Loss of vegetation cover -Plant creeping grass
SECTOR : WORKS, WATER & ROADS
SUB-SECTOR : ROADS AND BRIDGES
CODE : 778/01/07/263312
TITLE : PERIODIC MAINTENANCE/OPENING OF MUNICIPAL
ROADS
IMPLEMENTING AGENCY: RUKUNGIRI MUNICIPAL COUNCIL
LOCATION : MUNICIPAL WIDE
PLANNED EXPENDITURE: 226,776,500=
FUNDS SECURED : 226,776,500=
FUNDING GAP : NIL
OPERATION EXPENDITURE 10,204,943
START DATE: 1ST JULY, 2015.
COMPLETION DATE: 30TH JUNE, 2016.
Objective:
To increase on the roadnetwork and regularly maintained in motorable conditions to foster social
economic development of the people through easy access to social services and markets for their
agricultural produce and goods.
Background
Experience has shown that when a road is rehabilitated or periodically maintained and no routine
maintenance is done, its general condition depreciates very fast. This has been proved by
observations on some rehabilitated roads. It was realized that there is a big difference between
sections where there is routine maintenance and where it is not. This has therefore, made us
undertake routine maintenance of Municipal roads with priority given to newly rehabilitated and
major roads. Some roads are beyond maintenance using manual labour. We have therefore, planned
to do mechanized maintenance.
Technical Description
Road condition assessment of all Municipal roads in addition to minor and spot repair
inventory.
Bush clearing and earthworks.
Grading and shaping
129
Spot gravelling
Installation of new culverts and desilting of existing culverts and side drains
Excavation of offshoots and side drains.
Inspection, Spot Supervision and monitoring with compilation of field activity reports.
Benefits:
Easy access to markets.
Less maintenance costs on vehicles, motor cycles and bicycles.
Easy access to social amenities by service providers/ seekers and supervisors
Reduction of time waste by road users to get to their destinations.
Increase on traffic flow / attraction of new vehicles
Beneficiaries:
The community and other road users.
Feasibility study:
Not applicable.
Plan of operation
This project will start with assessment of roads condition by the Works Department, and preparation
of cost estimates and specifications for the road maintenance inputs.
Procurement requisition form 1 with appended cost estimates for road maintenance inputs shall be
submitted to Municipal Contracts Committee for approval.
Project execution by force account mechanism using the acquired road equipment.
130
Total 2,509,000 129,446,000 67,553,500 27,268,000 226,776,500
Environmental Concerns:
Environmental Nature of the Mitigation measures
component affected environmental concern
131
Land -Soil erosion -Open many off shoots
-Grub during a dry season.
-provision of scour checks
-Loss of vegetation cover -Plant creeping grass
Objective:
To maintain the paved road section in a motorable conditions to foster social economic development
of the people through easy access to social services and markets for their agricultural produce and
goods.
Background
Experience has shown that when a road is rehabilitated or periodically maintained and no routine
maintenance is done, its general condition depreciates very fast. This has been proved by
observations on some rehabilitated roads. It was realized that there is a big difference between
sections where there is routine maintenance and where it is not. This has therefore, made us
undertake routine maintenance of Municipal roads with priority given to newly rehabilitated and
major roads. Some roads are beyond maintenance using manual labour. We have therefore, planned
to do mechanized maintenance.
Technical Description
Road condition assessment of all Municipal roads in addition to minor and spot repair
inventory.
132
Bush clearing and earthworks.
Grading and shaping
Pothole filling/shoulder maintenance
Pothole patching and shoulder maintenance with premix
Installation and desilting existing culverts.
Construction of drainage channel and desilting existing ones.
Inspection, Spot Supervision and monitoring with compilation of field activity reports.
Benefits:
Easy access to markets.
Less maintenance costs on vehicles, motor cycles and bicycles.
Easy access to social amenities by service providers/ seekers and supervisors
Reduction of time waste by road users to get to their destinations.
Increase on traffic flow / attraction of new vehicles
Beneficiaries:
The community and other road users.
Feasibility study:
Not applicable.
Plan of operation
This project will start with assessment of roads condition by the Works Department, and preparation
of cost estimates and specifications for the road maintenance inputs.
Procurement requisition form 1 with appended cost estimates for road maintenance inputs shall be
submitted to Municipal Contracts Committee for approval.
Project execution by force account mechanism using the acquired road equipment.
133
URF 122,272,360 13,902,730 10,000,000 5,000,000 151,175,09
0
Compiled Physical
field verification
activity Municipal
Periodic reports Engineer’s
maintenance Pothole filled and through Office Municipal
of shoulders maintained. supervision Engineer
municipal Pothole patched and July, 2015 to
roads-Paved shoulder maintained June, 2016
with premix.
Culverts installed and
desilted
134
immediately.
Environmental Concerns:
Environmental Nature of the Mitigation measures
component affected environmental concern
Land -Soil erosion -Open many off shoots
-Grub during a dry season.
-Loss of vegetation cover -provision of scour checks
-Plant creeping grass
Objectives:
To increase the level of literacy in the Municipality
Background:
The literacy rate in the municipality is still low There is need to strengthen Functional Adult Literacy
Programme to enable the whole municipal population read and write with understanding.
Technical Description:
Procurement of Instructional materials.
Conducting municipal review meetings.
Testing Adult learners and proficiency testing.
FAL Instructors review meetings.
Municipal Supervision of FAL activities.
Purchase of chalk boards and chalk
135
Financing plan:
Sources of funds Expenditure by quarters Total
Q1 Q2 Q3 Q4
Central Gov’t 3,141,750 3,141,750 3,141,750 3,141,750 12,567,000
Objectives:
To promote income generation among persons with disabilities
Background:
People With disabilities are stigmatized, poor, Lack appropriate appliances, skills and capital.
Therefore there is need to identify key concerns of the people with disabilities so as to empower them
and promote integration of their concerns into the development process.
Technical Description:
Routine assessment, management and referral of disability cases.
Training of people with disabilities and Parents/ helpers on disability management
Training of PWDs in income Generating activities.
Provision of grants to PWDs groups
Provision of appropriate appliances.
Support supervision
Implementation plan:
Registration of PWDs Shall be updated annually by the Community Development Officers at
Division Level.
Financing plan:
Sources of funds Expenditure by quarters Total
Q1 Q2 Q3 Q4
Rukungiri MC 400,000 400,000 400,000 400,000 1,600,000
Central Government 5,983,000 5,983,000 5,983,000 5,983,000 23,932,000
Total 6,383,000 6,383,000 6,383,000 6,383,000 25,532,000
136
Operation and maintenance Plan:
The PWDs will maintain their appliances and the activities
Objective:
To promote women participation in Socio- economic Development programmes
Background:
Most women lack knowledge about their rights, leadership and entrepreneurship skills. They spend a
lot of time on household chores. There is need for advocacy for women causes
Technical Description:
Monitoring women projects
Mobilization and Sensitization.
Holding women council meetings
Financing plan
Objectives:
To enhance youth participation in Social Economic Development
Background:
137
The Youth generally lack access to productive resources and skills for participation in Socio
Economic development. As a result a large number of them are unemployed, dependent and involved
in unproductive activities such as substance abuse, hence; need to empower them with productive
skills and capital
Technical Description:
Mobilisation of youth into Youth interest groups
Provision of startup materials/capital to the youth for IGAs
Provision of revolving loans to the youths for income generation
Holding a radio programme
Holding youth council meetings
Monitoring youth projects
Implementation Plan:
Mobilisation, monitoring, youth council meetings, giving of loans will be done on a quarterly basis
Financing plan:
Sources of funds Expenditure by quarters Total
Q1 Q2 Q3 Q4
Central Gov’t 5,750,000 5,750,000 5,750,000 5,750,000 23,000,000
Operation and Maintenance Plan:
The youths will look after their projects
SECTOR PLANNING
SUB-SECTOR POPULATION
PROJECT TITLE DEMOGRAPHIC DATA COLLECTION
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPAL COUNCIL
LOCATION MUNICIPAL WIDE
PLANNED EXPENDITURE UGX 1,000,000
SECURED FUNDS UGX 1,000,000
Objectives:
To enhance the importance and integration of Population factors in
development programmes
Background:
Demographic data collection is of significance in planning, budgeting and decision making. Vital
registration had for a long time not been taking place, until the 2002 population and housing census
when it was launched in the Country. However, up to now it’s not moving on smoothly. The
registration aims at tracking the population changes and will be continuous, thus a need to update
births and deaths information.
138
Population and development are related and hence the need to inform the population to make the right
decisions.
Technical description:
- Sensitizing and training of LC’s and Parish Chiefs
- Monitoring and support supervision
- Equipping sub-counties with registration certificates and registration forms
- Data collection, entry, analysis and dissemination
- Increased public awareness on the relationship between population and development
- Population coordination meetings
Feasibility Study: The population and housing census 2002 and 2014 revealed the importance of this
project.
Plan of Operation:
The population officer shall implement the project in liaison with heads of departments, subcounty
chiefs, LC’s and Parish Chiefs.
139
population and
development
- Population
coordination
meetings
Supervision and Certification Arrangement: The project will be supervised by the District
Population Officer
SECTOR PLANNING
SUB-SECTOR DEVELOPMENT PLANNING
PROJECT TITLE PRODUCTION OF THE DDP, BFP, SDPs, ANNUAL
WORKPLANS AND HOLDING THE BUDGET
CONFERENCE
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPAL COUNCIL
LOCATION MUNICIPAL WIDE
PLANNED EXPENDITURE UGX 2,394,000
SECURED FUNDS UGX 2,394,000
START DATE: 1st JULY 2015 COMPLETION: 30th JUNE 2016
Objectives:
To facilitate and co-ordinate the process of development planning and budgeting both at the district
and sub-county levels
Background:
With increased responsibility to Budget, plan and co-ordinate development programmes, there is need
for enhancing capacity to do so. There is lack of co-ordination and planning capacity at divisions as
reflected in their plans, hence the need to strengthen them.
Technical Description:
Production of plans and budgets
Revision/rolling over of the plans
Integration of sub-county plans
Production of the budget frame work papers
Holding of the budget conference
Revision and production of Division Development Plans
Benefits: Funding for the priority projects in the Municipality and their implementation
140
Beneficiaries: The community/population, civil society organizations, political leaders and technical
officers
Plan of Operation:
The Municipal Planning Unit shall implement the project in liaison with Head of departments and
sections, NGOs and lower local government councils.
Supervision and Certification Arrangement: The project will be supervised by the Head of the
District Planning Unit.
141
SECTOR PLANNING
SUB-SECTOR MONITORING AND EVALUATION
PROJECT TITLE MONITORING AND MENTORING
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPAL COUNCIL
LOCATION MUNICIPAL WIDE
PLANNED EXPENDITURE 9,039,000
SECURED FUNDS 9,039,000
START DATE: 1ST JULY 2015 COMPLETION: 30TH JUNE 2016
Objectives:
To develop an efficient and effective monitoring and mentoring system at all levels of local
government
Background:
The implementation of municipal programmes demands the establishment of an effective and
efficient monitoring and evaluation mechanism to assess the progress of work under municipal
programmes especially LGMSD and PAF. There is also need to mentor all the lower local
governments in the areas of participatory planning and budgeting, so that they are able to produce
quality development plans, hence the need for this project
Technical Description:
Monitoring development projects
Producing monitoring and evaluation reports
Mentoring sub-counties in participatory planning and budgeting
Dissemination of reports and findings to stakeholders
Feasibility study: No feasibility studies have been made, however project monitoring is fundamental
for the success of projects.
Plan of Operation:
The District Planning Unit will implement the project in liaison with heads of departments, NGOs
and lower Local Governments.
142
Budget and Financing plan
Sources of funds Expenditure by quarters Total
Q1 Q2 Q3 Q4
PAF Grant 2,000,000 2,500,000 2,500,000 2,039,000 9,039,000
Supervision and Certification Arrangement: Theproject will be supervised by the Head of District
Planning Unit
143
SECTOR PLANNING
SUB-SECTOR MONITORING AND EVALUATION
PROJECT TITLE INTERNAL ASSESSMENT
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPAL COUNCIL
LOCATION MUNICIPAL WIDE
PLANNED EXPENDITURE 10,606,000
SECURED FUNDS 10,606,000
Objectives:
i) To develop an efficient and effective internal assessment system at all levels of local government to
ensure quality works and value for money.
ii) To ensure the municipal departments and divisions satisfy the minimum conditions and
performance measures.
Background:
Internal assessment is a requirement by the ministry of local government; it is done annually. The
municipality and divisions are assessed on minimum conditions and performance measures.
There is also need to mentor all the lower local governments in the areas of assessment so that they
are able satisfy the minimum conditions and performance measures. Failure to do assessment attracts
a penalty from MOLG hence the need for the project.
Technical Description:
Mentoring/training of assessors
Carrying out the annual internal assessment exercise
Assessment of municipal departments
Assessment of divisions
Producing Assessment reports
Submitting assessment reports to MOLG
Dissemination of reports and findings of assessment exercise to stakeholders
Benefits: Adherence to the guidelines, Increased physical accountability and rewarded performance
under the Annual Assessment of performance.
Feasibility study: No feasibility studies have been made, however internal assessment is
fundamental for better performance in the municipality and divisions
144
The Municipal Planning Unit will implement the project in liaison with, Heads of departments,
section heads and lower Local Government staff.
Assessment will be carried out by a multidisciplinary team. The exercise will be done annually and
reports will be produced. The municipal planning unit shall coordinate the activity
145
Supervision and Certification Arrangement: The project will be supervised by the Head of
Municipal Planning Unit.
SECTOR PLANNING
SUB-SECTOR STATISTICS
PROJECT TITLE DATA COLLECTION, ANALYSIS AND STATISTICAL
ABSTRACT
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPAL COUNCIL
LOCATION MUNICIPAL WIDE
PLANNED EXPENDITURE 4,000,000
SECURED FUNDS 4,000,000
Objectives
To have an updated data bank for information and proper decision making
Background
The implementation of municipal programmes requires the establishment of an effective and efficient
data collection and analysis mechanism. The existing data has to be updated from time to time for
information and proper decision-making. A statistical abstract is now one of the areas of assessment
by the Ministry of local government hence the need for the project.
Technical Description
Data collection from departments and divisions
Data entry and analysis
Dissemination of results/reports and findings to stakeholders including Uganda Bureau of statistics
(UBOS)
Benefits: Enriched data bank and quick access to information for decision making by all stakeholders
Feasibility study: No feasibility studies have been made, however internal assessment is
fundamental for better performance in the municipality and divisions
146
Sources of funds Expenditure by quarters Total
Q1 Q2 Q3 Q4
PAF Grant 2,000,000 2,000,000 4,000,000
Supervision and Certification Arrangement: The project will be supervised by the Statistician.
Objective
To provide independent objective assurance and consultancy services designed to add value and
improve the local government’s operations so that it can accomplish its objectives by bringing a
systematic, disciplined approach to evaluate and improve the effectiveness of risk management,
control and governance processes.
To provide reasonable assurance that the information recorded in the books of accounts is reliable and
free from material misstatement.
Background
147
Ever since the decentralization policy started in 1993, the central government has continuously been
committed to developing Local Governments through development programs such as LGDP, PAF,
and Local Government management and service delivery. All these programs have rules regulations
and guidelines which must be complied with before accessing them.
Experience has shown that many Local Governments fall short of compliance to rules regulation and
guidelines and adherence to internal controls which discredits the municipality. Therefore there is
need to always and continuously appraise internal controls and their compliance.
Technical Description
The project will involve continuous mentoring, inspection of departments, divisions, schools, health
units to enhance financial discipline. It will also involve regular visits to local governments and other
institutions to examine books of accounts and visit sites of projects under implementation.
Benefits: To promote proper utilization of Government resources and compliance with laws and
regulations.
Plan of Operation: The Internal audit staff shall carry out routine audits and field visits of projects
under implementation according to the annual work plan.
148
signed.
Production No. of Reports filed Files Quarterly Head of Internal
of Quarterly reports Audit
reports produced
Objective
To advice management on the progress of implemented projects and to verify the effective, efficient
and economic use of resources.
Background
It is a common occurrence for government projects to be mismanaged. The Internal Audit Function is
mandated to carry out value for money reviews to enhance accountability of the funds and also to find
out if the objectives of the project were achieved.
Technical Description
The project will involve continuous mentoring, inspection of departments, sub-counties, schools,
health units to verify if the projects were implemented properly. It will also involve regular visits to
local governments and other institutions to examine books of accounts and visit sites of projects
under implementation.
Benefits: To check proper utilization of Government resources and compliance with laws and
regulations.
149
Beneficiaries: Rukungiri MC, Divisions, Institutions and the public.
Plan of Operation: The Internal audit staff shall carry out routine audits and field visits of projects
under implementation according to the annual workplan.
150
SUB-SECTOR INTERNAL AUDIT
IMPLEMENTING AGENCY RUKUNGIRI MUNICIPAL COUNCIL
LOCATION HEADQUARTERS AND DIVISIONS
PROJECT TITLE PREPARATION AND SUBMISSION OF REPORTS
PLANNED EXPENDITURE 1,800,000
SECURED FUNDS 1,800,000
RECURRENT EXPENDITURE 1,800,000
START DATE: JULY 2015
COMPLETION DATE: JUNE 2016
Objective
To provide timely feedback to management on the audit findings on the areas audited and give
recommendations on issues that require management action.
Background
Ever since the decentralization policy started in 1993, the central government has continuously been
committed to developing Local Governments through development programs such as LGDP, PAF,
NAADS and Local Government management and service delivery. All these programs have rules
regulations and guidelines which must be complied with before accessing them.
Management needs to be advised on the course of events on time so that necessary action is taken.
Therefore there is need to report on those issues quarterly and when necessary.
Technical Description
It is a statutory requirement for Internal Audit to report to the Municipal Council and give copies to
other ministries and offices without and within the municipality.
Benefits: To provide information on the utilization of Government resources and compliance with
laws and regulations.
Plan of Operation: The Internal audit staff shall carry out routine audits and field visits of projects
under implementation according to the annual work plan.
151
Monitoring and Evaluation Plan:
Project Indicator Means of Source of Time Frame Responsible
Activity verification verification officer
Preparation No. of Reports files Quarterly Head of Internal
and reports produced Audit
submission produced and filed.
of quarterly and
reports submitted
audited
Objective
To build capacity of the Internal Audit staff
Background
Since the accounting profession is dynamic, the audit staff need to be trained on how to manage the
new changes from time to time. All Local Government Internal Audit Departments are members of
the LOGIAA (Local Governments Internal Auditors Association and therefore there is need to attend
workshops and AGMs.
152
Technical Description
The Association holds 1 AGM and 1 workshop every financial year.
Benefits: The Internal Auditors are kept updated of the changing issues that help them in carrying out
their work.
Beneficiaries: Internal Audit, Rukungiri Municipal Council, Divisions, Institutions and the public.
Plan of Operation: The Internal audit staff shall carry out routine audits and field visits of projects
under implementation according to the annual work plan.
153