You are on page 1of 22

Industrialised Building

System
(IBS)

Definition
The Industrialised Building Systems (IBS)
is a construction process that utilises
techniques, products, components, or
building systems which involve
prefabricated components and on-site
installation.

1
Introduction
 All building components such as wall, floor slab,
beam, column and staircases are mass produced
either in factory or at site under strict quality
control and minimal on site activities
 Mechanisation of the building processes
 E.g. of completed buildings in Malaysia: HUKM
University Hospital, Selayang Hospital, Kuala
Lumpur Tower, IKEA Damansara

Structural Category of IBS


Based on CIDB:
Group 1: Pre-cast Concrete Framing,
Panel and Box Systems

 Includes precast concrete columns,


beams, slabs, walls
 3-D components e.g. balconies, staircases,
toilets, lift chambers
 Lightweight precast concrete and
permanent concrete formworks
4

2
Group 1

Balcony

Beams
5

Pre-cast
Concrete
Components

3
Structural Category of IBS
Group 2: Steel Formwork Systems

 E.g. tunnel forms, tilt-up system


 beams/columns moulding and
 permanent formworks

Group 2

Tilt-up system

4
Structural Category of IBS
Group 3: Steel Framing Systems

 Steel framing system e.g. steel trusses,


columns, beams and portal frame system

Structural Category of IBS


Group 4: Prefabricated Timber
Framing Systems
 Prefabricated timber framing systems
consists of prefabricated timber
trusses, beams and columns

10

5
Structural Category of IBS
Group 5: Block Work Systems

 Blockwork system includes interlocking


concrete masonry unit (CMU)
 Lightweight concrete blocks

11

Pre-cast Concrete
 Concrete cast
into desired
shapes prior
to placement
in a structure

12

6
Pre-cast Concrete

13

Prestressed Concrete

14

7
Advantages of Pre-cast concrete
system (1)
 High level mechanisation thus precision
 No delay due to bad weather and manpower
 Application of modular design in standardising
dimensions
 Work done concurrently at factory and at site
thus speed up construction
 Low site workers requirement due to simplified
construction methods
 Quality controlled and highly aesthetic end
products
 Reduction of construction materials at sites
 Save costs 18

Advantages of Pre-cast concrete


system (2)

 Reduction / elimination of conventional timber


formworks
 Reduction / elimination of props
 Reduction of construction wastes
 Cleaner sites
 safer construction sites
 Faster completion of construction projects
 Cheaper total construction costs made possible
due to all of the above
19

8
Examples: IBS
 The construction of Police Station in
Senawang Negeri Sembilan:
Comprises of 1 unit of Police Station Office
Block, 4 units of Class F Quarters and 2
Units of Class G Quarters and the External
works

22

THE CONSTRUCTION OF QUARTERS G


 The Block comprises of 5 Storey Building
as shown in the picture

QUARTERS G

23

9
NUMBERS OF PANELS USED

Precast Wall Precast Slab


Level Block Block Block Block G2
G1 G2 G1

1 91 91 0 0
2 94 94 102 102
3 94 94 102 102
4 94 94 102 102
Upper 1 1 0 0
Roof
468 468 408 408 24

CONSTRUCTION PROCESS USING PRECAST PANELS

PILING

PILE CAP
cast insitu

STUMP cast insitu

GROUND BEAM cast insitu

FLOOR SLAB
cast insitu

COLUMN

INSTALLATION OF CONCRETE WALL PANEL


precast PROCESS REPEATED FOR
SUCCESIVE FLOOR

INSTALLATION OF FLOOR SLAB CONCRETE PANEL


precast

cast insitu CONCRETE TOPPING ON FLOOR SLAB 25

10
PILING WORK FOR FOUNDATION

26

PREPARATION OF COLUMN STUMP (CAST INSITU)


28

11
29

CONSTRUCTION OF GROUND BEAM (CAST INSITU)

Dowel
Bar

32

12
‘MOULD’ FOR THE PRECAST CONCRETE PANEL WAS FABRICATED IN
THE FACTORY ACCORDING TO THE DESIGN SPECIFICATIONS
INCLUDING REQUIREMENTS FOR ELECTRICAL INSTALLATION

33

CASTING PROCESS IN A FACTORY

35

13
36

COMPLETED WALL PANELS

39

14
PANELS TO BE TRANSPORTED TO CONSTRUCTION SITES
40

THE USE OF FULL TIME CRANE FOR THE HOISTING AND INSTALLATION OF PANELS

41

15
ONE CRANE AND 5 SKILLED WORKERS WERE USED FOR THE INSTALLATION
OF THE PRECAST CONCRETE PANELS
44

WORKS ON INSTALLATION OF WALL PANELS USING A CRANE

45

16
Installation of Precast Panels

DOWEL BARS WERE SLOT TO THE HOLE SLOT UNDERNEATH THE PANEL FOR CONNECTION
46

PANELS WERE HOIST THROUGH PROPER HOOKS AND FIXED


THROUGH THE PANEL CONNECTION SLOTS 47

17
50

CONCRETE JOINTS BETWEEN COLUMN AND WALL PANELS

CONCRETING OF THE JOINTS USING CONCRETE CHIPPING OF


GRADE 25

51

18
GROUTING OF THE JOINTS BETWEEN WALL AND COLUMN
53

INSTALLATION OF PRECAST FLOOR SLAB PANEL

56

19
FLOOR SLAB PANELS FIXED TO POSITION

57
BOTTOM VIEW

PREPARATION OF FLOOR SLAB CONCRETE TOPPING


(CAST INSITU)

ELECTRICAL CONDUITS AND RETICULATION PIPES ARE


INSTALLED AND FIXED INTO POSITION BEFORE CONCRETE
TOPPING WERE CARRIED OUT

58

20
ROOF TRUSS OF QUARTERS G

60

FINISHING AND FINAL TOUCH- UP

PAINTINGS

61

21
QUARTERS G NEARLY COMPLETION

62

22

You might also like