Jobsite Details
Location: Daund, Maharashtra
Length: 1.3 km
Width: 5.2 m
Depth: 225 mm
Authority: PMGSY
Execution:
Sai Tech Infra / RoadstaB: 700m
Base Seal: 600m
Equipment:
Wirtgen WR240
Streumaster SW16MC
Hamm 3520
Company Use
BC 40 mm
Premix Carpet 25 mm
Stabilized
WMM 2 75 mm Base Layer 225 mm
(Cement+Additive)
75 mm E=3000 MPa
WMM 1
GSB 200 mm
GSB 150 mm
Company Use
Microprocessor controlled
Cement spreading
Quantity: 3.6% by weight
Spread rate: 18 kg/m²
Equipment: SW16MC
Cement
Spreader
Company Use
Step 2: Stabilization
Additive dosage:
RoadstaB: 100ml/m³
Base Seal: 750ml/m³
Water spraying: 5-6%
Equipment: Wirtgen
Stabilizer-cum-Recycler
WR240
Step 3: Pre-Compaction
Pre-Compaction with 20
Ton Padfoot Compactor
Process
Step 4: Grading
Final Compaction
with 11 Ton Smooth
Compactor
Followed up with
water-curing for 3
days
Company Use
Stabilized Surface
Company Use
Final Surface