Professional Documents
Culture Documents
FUNCTION
It is generally used as a base course of Flexible Pavement.
WMM provides a uniform and strong support, high resistance to deformation
and distress.
53.00mm 100
45.00mm 95-100
26.50mm –
22.40mm 60-80
11.20mm 40-60
4.75mm 25-40
2.36mm 15-30
75 micron 0-5
Grading Curve for WMM-Morth V:
Quality Control Tests and Frequency
Relevance IS Frequency of
Tests Performed Limits
Code Tests
IS 2386 (Part4) /
AIV/Wet AIV 1/1000 m³ As by Engineer
IS5640
Los Angles
IS 2386 (Part4) 1/1000 m³ ≤30%
Abrasion Value
MDD & OMC IS 2720 (Part8) 1 test per source As per material
Spreading/Paving of WMM:
If the GSB layer surface is found to be dry, water shall be sprinkled before
laying of WMM.
While constructing Wet Mix Design, arrangement shall be made for the lateral
confinement of Wet Mix where WMM is laid on the outer edge of carriageway.
Control pegs shall be fixed at every 10m along CL on both sides of the bed in
such a manner that they are not distributed by paver movement.
Required level shall be marked on the pegs with suitable vertical offset and
string wire shall be fixed over the pegs to hold the sensor of paver.
The string wire shall be tightened by using hand winch.
The paver shall be set over the GSB layer considering loose thickness and
shall be kept 15-17% extra than compacted thickness.
Paver shall be check for skid and sensor before unloading WMM mix.
Special care is required for cambering and grade to be maintained.
Compaction:
Test trail shall be done to check the number of passes required for achieving
98% of FDD and approved from clients.
The number of passes shall be made as:
Plain Pass- 1, Low vibration- 2, Plain Pass- 1
Rectification:
Surface Finish:
Surface level- The level of finished layer shall not vary from the project design
level for a particular layer.
Tolerance on surface levels: ±10mm.
For checking compliance with the above requirement, measurements of the
surface levels shall be taken on a grid of points placed at 6.25m longitudinally
and 3.5m transversely along the pavement. The average of 10 measurements
shall not be more than 3mm above the permitted limit.
Productivity
Wet Mix Macadam productivity: 25000 m³/Month/team/shift
Paver productivity : 60 m³/hr
Roller productivity : 60 m³/hr
Note:
The above details are considered for 5km lead and 8-10 hr of working time.
For WMM 160 TPH plant is considered for production.