Professional Documents
Culture Documents
SYLLABUS
Energy Sources: Location and Characteristics of Fossil and Nuclear Fuel. Fuel Processing
and Environmental Safety Limitations.
Nuclear Power Plant: Schematics of Nuclear Power Plant; Brief Treatment of Fission and
Fusion Reaction and Expected Yield.
Hydro Power Plant: Principles of Energy Conversion Using Water. Criteria for Siting Hydro
Plant. Elements of Hydro-Electric Power Plant, Types of Hydraulic Turbines, Performance
and Efficiency Characteristics; Technical Description of Hydro Power Schemes in Ghana.
Brief Treatment of Pumped-Storage Schemes.
Per Unit Notation: Reduction of System Values of Power Systems to Per-unit With
Reference to Base Values. One Line and Impedance Diagrams.
Transmission Line Parameters: Generalised line parameters (A B C D). Short, Medium and
Long Line Equations. Natural Load. Losses of Transmission Lines. Computer-based
Solutions to Problems to be encouraged.
1
1 INTRODUCTION TO POWER GENERATION
The alternate method of generating electricity without the use of prime mover consists of
magneto hydro-dynamics, thermionic and thermoelectric generation, but all these method are
still in experimental stages.
The prime mover to which the alternators or generators are coupled , in turn, looks on the
following for sources for energy.
These are energy from water, fossil fuels (such as coal, oil and natural gas) and nuclear
fission. The fossil fuels may also be called Chemical Energy Sources.
1.2.1.1 Water
The bulk of installed electrical energy generation capacities in Ghana are at hydro power
stations at Akosombo and Kpong. The potential energy of water is harnessed to turn a
hydraulic turbine to produce electricity.
Coal, natural gas and oil are a major source of energy for electric power generation especially
in most developed countries where these fuels are abundant. Natural gas is obtained from
deep wells sunk into the soil. Oil wells also yield gas in addition to the oil. The combustion
of coal, oil or natural gas in boilers produces steam at high temperatures and pressures which
is passed through steam turbines to produce power. Gases at high pressures and temperatures
obtained by burning fossil fuels can also be used directly to turn a gas turbine to produce
electrical power.
In nuclear reactors, 235U atoms fission after they have been bombarded with neutrons. The
difference in mass between 235U and the fission products is converted into kinetic energy and
heat in accordance with Einstein’s equation. The heat is used to produce steam to turn a
steam turbine.
Fusion is when smaller atoms join together to form bigger atoms. Heat is also produced
during fusion and there are no radiation problems. The fuel is also abundant in sea water but
the control of the reactor temperature – several hundred million degrees - is a problem.
2
1.2.2 Unconventional or Renewable Energy Sources
These are energy from the sun, rivers, tides, wind, or wood. They may also be called
Environmental Energy Sources. Technologies are being developed to harness these energy
sources for electricity generation because the world population is fast increasing and the
fossil fuels are getting depleted.
The sun is the source of almost all the energy on the planet: river-, tidal-, wind-, fuel wood-
and fossil fuel-energies can all be traced to the sun. The following technologies are being
developed to make use of solar energy in a more direct manner.
a) Using a conventional steam generation scheme, mirrors and lenses (called concentrators)
are used to concentrate solar energy in boilers to produce steam at 5000C to drive a
conventional steam turbine.
b) Photovoltaic Cells or Photocells are used to produce electricity directly from solar energy.
The cells consist of silicon or gallium arsenide wafers having efficiencies of 10% and 16%
respectively. Photocells produce potential differences of about 0.5V and current densities
of about 200A/m2 in full solar radiation.
c) In principle one can pump a liquid sodium/potassium mixture through pipes covered with
material which absorb and keep all incident radiation. The liquid metal could be heated up
to 5000C. With an accumulator filled with salt that melts during the day and gives out heat
during the night, we can run a conventional steam turbine.
Windmills (or wind turbines) are used as prime movers to generate electricity. Wind power
plants manufactured in Europe and the USA can be grouped into three scales of operation.
One can make use of heat from deep inside the earth crust as a source of energy. Thermal
energy from hot springs has been used to produce electricity in Italy since 1904. In northern
California, steam from wells sunk in a natural steam field called the Geysers is passed
through turbines to generate electricity. By deep boring to about 2km to reach hot volcanic
rocks water can be pumped down and the steam produced used to generate electricity
(Iceland).
The power in a wave is proportional to the square of the amplitude and to the period of the
motion (period of wave ≈ 5 to 10s). The sea motion can be converted into mechanical energy
in a number of ways. One method is by using the Salter cam (or duck) designed by Stephen
Salter of Edinburgh University for optimum power extraction. A wave entering sets the beak
of the duck into oscillation. Conversion of the float movement to electricity is difficult
because of the slow motions. One form of energy conversion being investigated is the use of
highly geared reciprocating alternator giving a variable frequency output.
3
1.2.2.5 Tidal Energy
The level of water in the large oceans of the earth rises and falls according to predictable
patterns. The main periods of these tides are diurnal at about 24 hours and semi-diurnal at
about 12 hours 25 minutes. The movement of the water produces tidal current which may
reach speeds of approximately 5m/s in coastal and inter-island channels. The best known
large scale tidal electricity generating plant is the 240 MW La Rance in France. The practical
devices for tidal flow power will be similar to river flow power systems.
The liquids which can be used are: fuel oil , crude oil ,petrol and paraffin oil . Out of these
generally fuel oil is used for firing the boilers; the other types of fuel are of better quality and
are used in internal combustion engines.
Figure 1.1 illustrates the conversion of heat energy into mechanical energy while Figure 1.2
is a line diagram of the thermal generating station. The scheme of generation can be divided
in two phases: i) Formation of steam in the boiler house ii) generation of electricity in the
generator room.
In the Boiler House, the fuel is burnt and the heat generated is used to convert water into high
pressure steam which is further superheated in the super heater. The superheated steam is
passed in the turbine to rotate the turbine blades, thus it converts heat energy into mechanical
energy. The pressure of the steam decreases and its volume increases. After imparting energy
to the turbine rotor it passes out of the turbine blades into the condenser. In the condenser the
cold water is circulated with the help of pump which condenses the low wet steam. This
condensed water is further supplied to low pressure water heater where the low pressure
steam increases the temperature of this feed water; it is then fed again into a high pressure
heater where the high pressure is used for heating . The method of taking out steam from
turbines for feed water heating is called bleeding of the turbines which increase the overall
efficiency .of the boiler. The cold water used in the condenser becomes too hot as it comes
out of the condenser; for it to be better used it is cooled by means of cooling tower.
The turbine in the generating room acts as the prime mover of the alternator which generates
electrical energy. The generator is connected through circuit breaker to the busbar. The
overall efficiency of the thermal station is 20 to 26% and the plant load factor varies from
39% to 44% depending on the plant capacity.
4
Fig 1.1: To illustrate the conversion of heat energy into mechanical energy
Coal storage
Coal
handling
Chimney
Ash storage
Ash storage Plant
Boiler
Air heater
Exciter
High pressure
feed water
Turbine
heater
Condenser Alternator
Boiler feed
water pump
Cold water
circulating
Lower pressure
pump
feed water
heater
Condensate
extraction Cooling Tower
pump
A diesel engine is a prime mover that obtains its energy from a liquid fuel generally known as
diesel oil and converts this energy into mechanical work. An alternator or a generator
coupled to it converts the mechanical energy developed into electrical energy. It is also
described as the compression ignition type power source in which the heat for igniting the
fuel charge is obtained from the compression of air in the engine cylinder before the fuel is
5
introduced into it .The main difference between diesel engine and steam turbine is that in the
first case chemical energy of combustion is released inside the cylinder while in the second
case the energy developed during combustion of fuel is first transferred into steam and this in
turn develops mechanical power in the turbine.. The diesel engines are most popular with
small generating stations and with consumers who will like to have their own power supply
for emergency reasons. They are also needed in medium sized power installation too either to
supply the peak load for small duration or for seasonal load.
At Fig 1.3 (a) the inlet valve opens and gasoline-air mixture flows into the cylinder as the
piston moves down;
At Fig 1.3 (b) all the valves are closed, the piston moves upward and compresses the gas; the
injection of fuel starts near the end of compression.
At Fig 1.3 (c) all the valves are closed ,firing of the spark plug ignites the gasoline-air
mixture, raising it to a high temperature
At Fig 1.3 (d) the gases, now at high temperature and pressure, expand against the piston and
forcing it downward the power stroke;
Exhaust
valve
(a) Intake (b) Compression (c) Ignition (d) Expansion (e) Exhaust
(power stroke)
Figure 1.3 Four-cycle internal combustion engines:
At Fig 1.3 (e) the exhaust valve opens, the rising piston forces the burnt gases out of the
cylinder through the exhaust pipe; the intake valve then opens, and the whole cycle repeats.
For diesel engines that are used for electricity generation are equipped with turbo chargers.
The charger compresses the air that is supplied into the combustion chamber. The amount of
air is therefore increased and the combustion is more complete. The energy used to compress
the air is more than compensated for by the increase in the engine capacity of about 15 to 20
percent of effective exhaust turbines.
6
1.4 The Gas Turbine
The installation consists of turbine, combustion chamber and a compressor driven by the
turbine. The compressed air is delivered to combustion chamber where the continuous
combustion of the injected fuel oil is maintained, the hot gases then drive the turbine.
The use of gas turbine as prime mover has certain advantages over steam plant, although with
normal running it is less economical to operate. The main advantage lies in the ability to start
and take up load quickly. Hence the gas turbine is coming into as a method for dealing with
the peaks in the system loads. A further use of a gas turbine is as a synchronous compensator
assists in maintaining voltage levels. Even on economic grounds it is probably advantageous
to meet peak loads by starting up gas turbines from cold in order of 2 sec rather running spare
steam engine continuously. Figure 1.4 show a schematic diagram of gas turbine plant
constructed to supply electrical power. Under every component is the pressure and
temperature of the gas after it has flowed through the component. The values may vary for
different constructions.
Figure 1.4 is a schematic diagram of a gas turbine. Air is sucked in through the Air Intake
(AI) and compressed in the Low Pressure Compressor (LPC) to a pressure of about 3.5-6bar.
Small gas turbines have only one stage of compression. For bigger plants built to last long,
the air is cooled in a heat exchanger and compressed further before it is fed into the
combustion chamber. The cooling reduces the volume of air to about a third of the original
volume. This reduces the strain on the High Pressure Compressor (HPC).
With the double compression the pressure is raised up to 10-15bar. Air at this pressure is fed
into the combustion chamber where the fuel (oil, gas, coal, etc.) is burnt to raise the
temperature to about 8000C. Temperatures above this will reduce equipment lifespan. At
this temperature and pressure the gas expands through the High Pressure (HP) turbine which
drives the HPC and on through the Medium Pressure (MP) turbine which drives the LPC.
The gas then expands through the Low Pressure (LP) turbine at much reduced pressure (2-
3bar) and temperature (400-5000C) towards atmospheric pressure. The LP turbine is the
power turbine and drives the generator over a mechanical coupling.
7
1.5 Prime Movers for Thermal Power Plants
All power stations use prime movers, and these are usually turbines that are used to turn the
generators. In small plants, the reciprocating-steam engine or the diesel engine is used. The
turbine consists of a single-blade or a ring of blades or a series of blades connected in tandem
or cascade to the same shaft.
The mode of controlling the power from a turbine is either by moving the blades, changing
the pressure and velocity of the steam (gas), changing the nozzle opening, etc. The mode of
control determines the type of turbine. For thermal stations, the turbines are either impulse or
reactive type. Modern turbines are a blend of the two types.
The power produced at a hydro power plant is a function of the head, the flow rate and the
efficiency of the plant. The governor maintains the speed of rotation and therefore the
frequency of the generator voltage constant. When the load increases the governor increases
the flow of water flowing through the turbine to match generation with demand.
There are three main types of hydro-power plants depending on the head of water, namely:
a) high-head station
b) medium-head station
c) low-head station
1.6.1 High-head Station
The head is in excess of 600m and the flow rate is low. High-speed Pelton turbines are used.
At a high-head plant the intake is at a distance from the power house and they are joined
together by the penstock. The amount of impounded water is usually small. They are found
in the Alps and other mountainous regions.
8
1.6.2 Medium-head Station
The head is between 60m and 600m. Medium-speed Francis turbines are used. The
generating station is fed by water held behind a dam. The dam is usually built across a river
bed in a relatively mountainous region. A great deal of water is impounded behind the dam.
A typical medium head plant is shown in Figure 1.5 below.
Figure 1.6 shows a typical low-pressure plant. The head is low and low-speed Kaplan or
Francis propeller turbines are used. The low-pressure plant must have high discharge (flow)
rate to produce an appreciable amount of energy. These generating stations often extract the
energy from flowing rivers (run-of-river stations). The turbines are designed to handle large
volumes of water at low pressure. The intake and the power house are built together and the
waterway is built for a high discharge.
9
1.6.4 Basic Components of a Hydro-Plant
a). Dam – made of earth, rock or concrete, and is built across riverbeds to channel water to
the power house and to create storage reservoirs.
b). Spillways – they are provided next to the dam to discharge water whenever the reservoir
level is too high or threatens to become too high.
c). Penstock – the system carrying water from the reservoir to the power house is generally
divided into two parts: non-pressure conduits which may be open canals or tunnels carved
through a rock. They feed one or more penstocks (huge steel pipes) which bring the water
to the individual turbines.
d) Scroll-case – it surrounds the runner. It receives water from the penstock and distributes
it uniformly around the circumference of the runner.
e). Wicket gates – Inside the scroll case, these adjustable gates control the amount of water
flowing into the turbine, thus regulating the turbine output power.
f). Draft tube – Water that has passed through the runner moves next through a carefully
designed vertical channel called draft tube. The draft tube improves the efficiency of the
turbine. It leads out to the tail race, bringing the water into the downstream river bed.
i) Hydro-power stations have much less running cost as compared to thermal power stations.
ii) They are relatively simple in construction, robust and require low maintenance.
iii) They respond to changing loads without much difficulty, and are thus used to meet peak
load requirements.
v) The water after turning the turbines can be used for irrigation, domestic water supply, etc.
vi) The plant is quite neat and clean.
i) High capital and other investment costs for generators, civil engineering works, etc.
ii) High cost of transmission lines.
iii) Power delivery dependent on the weather (rainfall, evaporation, etc.)
iv) Dam construction may lead to the destruction of forests, ecosystems, etc.
v) Dam construction may lead to the displacement of communities, etc. and may require
resettlement.
vi) Dam construction takes a relatively long time (5-10years).
The following points must be noted in the selection of a site for a hydro-power plant:
Water is allowed to fall through a height (called the head). The water falling through this
head gains kinetic energy which it then imparts to the blades of hydraulic turbines.
The available output power, P, is given as
10
P = gqh (1.1)
Where,
h: available head in (m), i.e., the height between the water level at intake and tail race
of the dam :
q: discharge or flow rate in (m3 /s) through the turbine
g: acceleration due to gravity = 9.8 m/s2
: density of water (in 1000 kg/ m3)
: total efficiency of the plant
[The rate of change of potential energy with time is given by m x g x h / s, where m = volume
per second x density x acceleration due to gravity]
Substituting the values of the density of water and the acceleration due to gravity, we obtain
Worked example
Example 1
A large hydropower station has a head of 324m and an average flow of 1370 m3/s. The
reservoir is composed of a series of lakes covering an area of 6400 km2. Calculate:
a) available hydropower
b) number of days this power could be sustained if the level of the impounded water were
allowed to drop 1m (assume no evaporation or precipitation, and neglect water brought in
by surrounding rivers and streams)
Solution 1
(a) The available hydropower is
volume 6400 10 6
t
flow rate 1370
4.67 10 6 s or 1298 h or 54 days
11
i) Pelton - > 600m head
ii) Francis - 60 – 600m head
iii) Kaplan - < 60m head
Figure 1.8: A diagram showing how flow rate is controlled in a Pelton turbine
12
1.7.2 The Francis Turbine
Water enters the Francis turbine (Figure 1.8) from a scroll-case that distributes water evenly
around the circumference of the turbine. The water is conducted to the turbine blades by the
wicket-gates. The flow rate is adjusted by controlling the wicket gate opening.
Figure 1.9: A Francis turbine runner rated 750MW being installed at the Grand Coulee Dam
1.7.3 The Kaplan Turbine
Kaplan turbines (Figure 1.9) are used for low heads especially when the flow rate is high.
For a Kaplan turbine both the wicket gate opening and the movable turbine blades can be
used to regulate the power output. This turbine has higher rotational rate and therefore the
generators are cheaper and the dimensions are smaller. The Kaplan turbine has better
efficiency for varying head and flow rates compared to the Francis turbine.
Typical efficiency curves for different turbines are shown in Figure 5.6 below.
13
1.8 Pumped-Storage Hydro Plants
Pumped-storage hydro-plants are designed to save fuel costs by serving the peak load (a high
cost load) with hydro energy and then pumping the water back into the reservoir at light load
periods (at a lower cost). These plants may involve separate pumps and turbines or, more
recently, reversible pump turbines.
The system consists of an upper reservoir and a lower reservoir connected by a penstock and
associated generating/pumping station. During power system peaks, the station acts like an
ordinary hydro power source, supplying electric power as water flows from the upper to the
lower reservoir. However, during light load periods, the alternator operates as synchronous
motor, driving the turbine as an enormous pump. Thus water flows from the lower to the
upper reservoir, thereby storing energy in preparation for the next system peak.
Storage reservoirs have limited storage capability and typically provide 4 – 8 or 10 hours of
continuous operation as a generator. Frequently, special interconnection arrangements may
facilitate pumping operations, where one purchases low-cost, off-peak energy. In some
systems, the systems operator will require a complete daily refill of the reservoir when there
is concern over the availability of capacity reserves. In those instances, economy is secondary
to reliability.
Peak power alternators have ratings between 50MW and 500MW. The pumped-storage
system has two advantages:
Nuclear power is now a well-established source of electricity world wide. The most common
types of reactors are light water reactors (Pressure Water Reactors and Boiling Water
Reactors). Worldwide there are currently about 430 reactors operating in 25 countries and
providing about 17 percent of the world’s electricity. The nuclear power station is a
latecomer to the league of energy production plants but it is fast becoming a very important
source as fossil fuels sources become depleted.
More than 40 million kWhs of energy can be produced from 1 tonne of natural uranium.
Over 16,000 tonnes of coal or 80,000 barrels of oil will need to be burned to produce the
same amount of energy.
1.10 Fission
Nuclear energy is released when a heavy nucleus splits into smaller atomic nuclei. Most
reactors that are in service today use uranium as fuel. Fissionable 235U makes up only 0.7%
of naturally occurring uranium. The rest is made up of 238U which is not fissile. 238U can
however mutate into plutonium-239 which is fissionable and can contribute up to half of the
energy produced in reactors. Before uranium can be used as fuel for reactors it is enriched
through diffusion or centrifugation to increase the 235U concentration to 2-3 percent.
When a 235U nucleus absorbs a neutron it becomes unstable and splits into new nuclei (Figure
1.11). The newly formed atoms are called fission products and are usually radioactive.
14
Figure 1.11: Diagram showing fission reactions
235
U n 148
La Br 3n
86
(200MeV)
uranium → lanthanum + bromine
The sum of the atomic mass unit (amu) on the right is less than atomic mass unit on the left.
Energy is therefore released according to Einstein’s equation
E mc 2 (J) (1.3)
By assigning atomic masses units to elements in the above fission reaction we obtain
The mass deficiency on the right hand side of the above mass equation is 0.207 a.m.u or
0.3436 10-27 kg ( 1 a.m.u = 1.66 10-27 kg =931 MeV ) . One 1 kg of Uranium contains
26.029 1023 atoms .
Using E mc we obtain the equivalent release of energy that may be obtained from one
2
Most of the energy produced during fission is in the form of kinetic energies of the fission
products. When the fission products collide with other atoms their kinetic energies are
converted to heat. Other fissile material used in nuclear power plants are Plutonium-239,
used in fast breeder reactors and Thorium-232.
1.11 Fusion
Energy is also released by fusion. An example is the fusion of two heavy hydrogen atoms to
produce helium.
1 H 2 1H 2 2 He3 n (4.03MeV)
15
1.12 Main Parts of a Nuclear Power Plant
Moderator – Slow (thermal) neutrons split uranium-235 nuclei more effectively than fast
neutrons. Moderators slow down neutrons without absorbing them. Slowing down the
neutrons makes it possible for them to initiate other fissions. The moderator may be ordinary
water (light water), heavy water or graphite.
Reactor – There are several types of nuclear reactors. The most important ones are:
The coolant is water kept under such a high pressure so that it cannot boil off into steam.
Ordinary (light) water or heavy water is used. For light water, one needs UO2 enriched with
2-4 % uranium-235 as fuel. Figure 1.12 shows a PWR. There are two closed circuits; the
primary circuit which includes the reactor and the secondary circuit which includes the
condenser and the turbine. The water that passes the reactor is warmed up to 3200C but due
to the high pressure (150bar) it does not boil. The hot water moves into the steam generator
where steam is produced in the secondary circuit. Efficiency of plant 30 – 35 percent.
The coolant is ordinary water boiling under high pressure releasing steam to drive the turbine
(Figure 5.9). The water is heated to a temperature of about 2900C (70bar). The steam is
dried before being released into the turbine. No heat exchanger is required. Enriched UO2 is
used as in any light water reactor. Efficiency of plant 30 – 35 percent.
16
Figure 1.13: A Boiling Water Reactor
Coolant is an inert gas such as helium or carbon dioxide. This reactor operates at high
temperature (typically 7500C), and so graphite is used as a moderator. The steam created by
the heat exchanger is as hot as that produced in a conventional steam boiler. Consequently,
the overall efficiency of these nuclear stations is about 40%.
It is able to generate heat and create additional nuclear fuel. The core of the nuclear fuel
consists of Plutonium-239. This is surrounded by a blanket of material containing Uranium-
238. No moderator is used and consequently, the fast neutrons generated by the splitting of
Plutonium-239 (239Pu) are absorbed by Uranium-238 which then transmutes to fissionable
Plutonium-239. The blanket is removed after some time to recover the substances containing
Plutonium-239 for re-use.
Figure 1.14 shows a typical FBR. The core is compact and the heat generated is high.
Sodium is used for effective cooling and the primary system may reach a high temperature of
5600C at one atmosphere. The whole reactor core is immersed in a sodium bath. Heat is
transferred to the secondary system in the heat exchanger. Steam is produced in the
secondary heat exchanger located in the steam generator.
17
Figure.1.14: A Fast Breeder Reactor (FBR)
The fuels are fed to the reactors in the form of rods or pellets. The energy density of fuels
used in the reactors is very small but this is still much better than fossil fuel.
Worked Example
Example 2
A fuel bundle of natural uranium dioxide has a mass of 22.2kg when first inserted into a
heavy-water reactor. If it releases an average of 372.5kW of thermal energy during its 19-
month stay in the reactor, calculate the:
a) total amount of heat (in J) released
b) reduction in weight (in g) of the bundle, due to the energy released
Solution 2
(a) The average power released is Pav 372.5 kW .
Total time in second is t 19 30 24 3600 49,248,000 s
Total amount of heat released,
H Pav t (372.5 103 J / s) 49,248,000 1.8345 1013 J
(b) Using the Einstein energy equation
E m c 2
E 1.843 1013
m 2.04 10 4 kg 0.204 g
c 2
3.0 10 8
2
10 Capital cost ($/kW) High (because of dam Lowest Highest (because of huge
construction or civil investment in building a
engineering works) nuclear reactor)
11 System operation and Lowest (it is simple and Higher (as compared to Highest (as skilled or well-
maintenance robust) hydro) trained staff is required to
handle equipment)
19
12 Fuel cost (including Practically nil because no Highest, especially Except hydro, it has the
transportation) fuel is required when the power minimum cost, because
stations are far from the small amount of fuel can
source of fuel (e.g. produce relatively large
1000MW requires 2.7 amount of power (e.g.
million tonnes of coal 1000MW requires 32.9
annually) tonnes of enriched uranium
annually)
13 Transmission cost Quite high, as these are Less than hydro, since Quite low, as these are
located quite far away they are generally located near load centres
from the load centres located nearer the load
centre
14 Environmental The cleanest, but dam Air pollution Clean source of power, but
impacts or factors produces effect on nuclear waste disposal is a
aquatic life in the river. major problem. There is
Lands (farm lands or the risk of radioactive and
inhabited areas) above heat pollution
dams are permanently
flooded
15 Site Ample quantity of water Where ample supply of Located nears the load
of sufficient head, water and fuel is centre. Easy transportation
possibility of constructing available, of nuclear fuel and
a dam economically to transportation facilities availability of cooling
store water and adequate. 800,000 to 1 water required. Thickly
availability of large million gallons/min populated areas are avoided
catchment area are required for a typical due to the risk of
decisive factors. 1000 MW unit radioactive pollution.
Transportation facilities
should also be available
a) Akosombo Hydro-Plant
20
b) Kpong Hydro-Plant
Tema = 110 MW
Kumasi = 25 MW
Before any project of building a power station is taken, the engineer should prepare the
following reports:
At the time of determining the probable load, the engineer should take into consideration the
future demand; he must survey and must be capable of predicting with quite accuracy the
load for the next five years. Then the probable load curve is drawn by carrying out an
electrical survey.
Fig. 2.1 represents a typical rectangular load curve for a private load for winter and summer.
The maximum peak load for summer is 700 kW and for winter, the peak load is 640 kW.
The total connected load of the building is 90 kW, or we say that the maximum demand of
the building is 90 kW. Hence the maximum demand is the total connected load. The building
may not be using all the light points, power points and the lift at a time. It will be very clear
that all the lamps and power points will not be working at the same time in practice. Assume
that, 300 lamps and 30 power points are worked at a time, so the average load of lamps and
power
The ratio of average load of power and light points to maximum demand
which is called the demand factor or maximum demand factor.
22
= = = .
Hence the maximum demand factor may be defined as the ratio of the average load to the
maximum demand.
10000
8000
6000
Load in
kW
4000
2000
P Q R S
6 pm 7 pm 8 pm 9 pm 10 pm 11 pm 12 pm
Fig 2.2 load curve to illustrate maximum demand
Hence whenever the maximum demand is to be mentioned it must be stated for what period
of duration it has been considered, i.e., if it is stated that the maximum demand is 6000 kW, it
has no meaning until and unless it is specified that it is for 15 minutes, or ½ an hour etc.
23
The average demand on the station is always referred in a particular period, say a day, a
month or a year which will give daily, monthly or yearly average demand. It is defined as the
ratio of kWh delivered by the station in a particular period divided by the hours in that period.
Category A = 5000kW
Category B = 900kW
Category C = 2000kW
Category D = 1000kW
Category E = 1100 kW
If the various categories were to take their supplies from the station as shown in figure 2.3
Then the maximum demand on the station will be between 6pm to 7pm and it is equal to
5000kW.
10000
8000
6000
Load in
kW
4000
A
2000
C
B D E
6 pm 7 pm 8 pm 9 pm 10 pm 11 pm 12 pm
Now if all the categories were to take their supplies at the same time as shown in fig 2.4
then the maxium demand on the station will be between 6pm to 7pm and it is equal to
10000kW = the sum of maximum demands of the individual category .
Hence the diversity factor of the station = . (This is a very poor diversity factor)
24
NOTE: The diversity factor must always be more than 1.0.
10000
B
E
8000
D
6000 C
Load in
kW
4000
A
2000
6 pm 7 pm 8 pm 9 pm 10 pm 11 pm 12 pm
a) It decreases the capital cost of the scheme, which will decrease the cost per unit.
b) The generators can be put to maximum use.
= (2.5)
Thus the load factor is also to be specified with period, whether it is daily load factor, or
monthly load factor.
The monthly load factor = (2.6)
From Fig 2.3, the number of units supplied can be obtained as follows:
Total energy supplied = load of Category A in kW number of hours from 6pm to 7pm +
load of Category B in kW number of hours from 7pm to 8pm + load of Category C in
kW number of hours from 8pm to 9pm+ load of Category D in kW number of hours
from 9pm to 10pm + load of Category E in kW number of hours from 10pm to 11pm =
= 5000 1 + 900 1 + 2000 1 + 1000 1 + 1100 1 = 10000 kWh.
25
The maximum demand of the station is 5000kW (Fig 2.3). Suppose the total daily loads
supplied by the station are as shown in fig 2.3 then the number of hours to be considered is 24
hrs. (This is because we normally mention either daily, monthly or yearly load factor.
Hence the daily load factor for the power station according to Fig 2.3 is
Similarly a higher load factor means more numbers of units generated per year, and the
maximum load factor will be 1; it will be at the instant when the maximum demand remains
throughout the year at all times. The cost of labour per kilowatt of energy generated decreases
as the number of units generated increases because the labour cost remains the same whether
the alternator is worked at 20%, 50%,or 100% load factor.
Thus the supply organizations should always try to improve the load factor as well as
diversity factor by inducing the consumers to use the electricity during off peak time and they
may be charged lower rates for such schemes.
when kW1, kW2, kW3 etc. are the kilowatt ratings of each generator and H1, H2, H3 etc. are the
number of hours for which they have worked. The plant factor indicates how best the plant
capacity has been utilized but it does not indicate the time for which the plant remained idle.
26
(2.8)
Thus the reserve capacity of the power reflects the reserve capacity of the power station.
= (2.9)
It may also be stated as the product of load factor and the demand factor, i.e.
(2.10)
(2.11)
Worked Examples
Example 3
A generating station has a maximum demand of 35,500 kW and has a connected load 65,000
kW. The number of units generated annually are 25.6 107. Calculate a) the load factor and
b) the demand factor.
Solution 3
Load Factor =
Assume that the station has a maximum capacity of the same as the maximum demand.
Example 4
A generating station supplies the following loads: 15,000 kW, 12,000 kW, 8,500 kW, 6,000
kW and 450 kW. The station has a maximum demand of 22,000 kW. The annual load factor
of the station is 48 percent. Calculate a) the number of units supplied annually b) the
diversity factor c) the demand factor .
Solution 4
Load factor =
27
=
= 0.48
b) Diversity factor =
= =1.903
= = 0.525 or 53.5%
Fixed Capital
Running Capital
The cost incurred as freight, cartage, labour etc., to bring the equipment from the
manufacturer’s premises to the site of erection are to be taken in account into the capital cost
of the plant.
The cost of implements to be purchased for erection purposes and the cost of supervision,
book keeping, managerial work etc, for the purchase of equipment up to the instant it can be
commissioned must also be added to the capital cost of the equipment.
28
2.12 Annual Cost
The economy of the project is not judged from total investment made for it, but from the
actual cost. The annual cost can again be subdivided into the following two heads:
a) Running Cost or Operational Cost – which is dependent upon the manner and extent to
which the equipment is being used.
b) Fixed Charges – which comprise the annual charges on the assets covered under fixed
capital to be taken into account.
a) Property tax levied on the generating station building and substation building etc.
b) Tax to be paid to the municipal corporation for the use of streets, roads etc.
c) Tax to be paid to government as public utility tax for inspection purposes etc.
d) Income tax.
These may vary from 1 to 2 per cent of the capital cost of assets over which the taxes are
being paid.
ii) Insurance Charges – the following premiums are to be paid to the insurance company:
a) To cover the risk of fire to the buildings. b) To cover accidental breakdown.
c) Worker’s compensation.
iii) Depreciation or sinking fund – after a certain time the equipment is to be replaced due
to the following reasons:
a) Physical – this is due to reasons that the plant has worn out and has become unfit for
further use.
b) Functional – it can be further subdivided into the two parts:
(i) The capacity of the plant has become inadequate due to the growth of load
(ii) The plant has become obsolete due to the new technological improvements.
2.13 Tariff
By tariff one means the rules or rates framed for supply of electricity to the different
consumers. For fixing a tariff the following points should be considered.
29
1. The annual cost of production.
2. Services rendered.
3. Ability of the consumer to pay.
4. The tariff should involve simple calculations.
2.14 Simple Type of Tariff. It is the simplest form of tariff and can be derived as
(2.12)
It does not discriminate between different types of consumers, hence everybody is sharing
equal burden of tariff and total charges.
The main defect in this type of tariff is that the cost per unit calculated will be higher.
The flat tariff differs from the simple tariff in the sense that the different types of consumers
(such as domestic, industrial, public etc) are charged at different rates. The rates for each type
of consumer is arrived at by taking into account its load factor and diversity factor. Such
tariff has an advantage that it can be understood by the consumers easily. The main drawback
in this tariff is that it is very difficult to derive at the load factor and diversity factor to be
used in deciding the tariff.
In this type of tariff the main consideration to be made is that as the number of units
generated are increased the cost of generation per unit decreases, hence the consumer having
large demand of number of units has to pay less as compared to the consumer having lower
demand. Say, for example, in a domestic load –
30
1. A fixed amount dependent upon his connected load irrespective of the fact that he
may use electricity or not, to cover the annual fixed charges and
2. Energy charges dependent upon the number of units consumed by him.
The drawbacks with this type of tariff is that if the consumer uses electricity sparingly and,
say, for most of the period he is out of station, unnecessarily he will have to pay the fixed
charges.
i) kVA maximum demand tariff. The maximum demand of the consumers is measured in
kVA and not in kW. This compels the consumers to work their plant at improved power
factors since low factors will increase their maximum demand.
ii) kWh and reactive kVArh tariff. For this type of tariff both kWh and kVArh of a consumer
are charged separately. If kVArh of a consumer is less he is to pay less and for low power
factors his bill will be higher, automatically the consumer will try to improve his power
factor.
iii) Sliding scale or average power factor tariffs. Under this kind of tariff an average p.f. say
0.8 lagging is assumed as reference. in order to penalize a consumer having low power
factor, he may be surcharged for each 0.01 by which the p.f. falls below the reference
figure and a discount is allowed if the p.f. is above this figure.
Worked examples
Example 5
Determine the thermal efficiency of a thermal power station and its coal bill per annum from
the following data :
Maximum demand = 20,000 kW; Coal consumption = 0.876 kg / unit
Boiler efficiency = 85%; Turbine efficiency = 90%; Price of 1 tonne of coal = ¢29.53 Load
Factor of 40%.
Solution 5
Thermal efficiency of a power station is given as:
Thermal efficiency = Boiler efficiency Turbine efficiency = 0.85 0.90 = 0.765 or 76.5%
Load factor =
31
Example 6
A power station is to supply four regions of load whose peak values are 10,000 kW, 5,000
kW, 8,000 kW and 7,000 kW. The diversity factor of the load at the station is 1.5 and the
annual load factor of the station is 60%. Calculate the maximum demand on the station and
the annual energy supplied from the station, suggest the installed capacity and the annual
energy supplied from the station, suggest the installed and the number of units taking all
aspects into consideration.
Solution 6
Maximum demand =
= = = 20,000 kWh
Load factor =
Select three similar units each of 10,000 kW capacity, because it will necessitate the
minimum number of spare parts to be stored, at the same time two units can supply the
present maximum demand and the third unit can be taken out for maintenance or during
breakdown without any disruption in supply.
Example 7
A generating station has got a maximum demand of 50,000 kW. Calculate the cost per kWh
delivered from the following data:
i) Capital cost = GHC 95 10 5
ii) Annual cost of fuel and oil = GHC 9 10 5
iii) Taxes, wages and salaries = GHC 6 10 5
The rate of interest and depreciation is 10%. Annual load factor is 50%
Solution 7
Capital cost = GHC 95 10 5
Since the rate of interest and depreciation is 10%, then
32
=> = 0.5 50000 8760 = 21.9 107
Example 8
A 20,000 kW generating station has the following generating cost
The caloric value of the coal burnt is 54.5 10 5 cal / kg . The cost of fuel is 55 GHC per
tonne. Assume plant heat rate 29.0 10 5cal/kWh at 100% capacity factor. Calculate the
generating cost/kWh at 100% capacity factor. Interest and depreciation is 10%.
Solution 8
Base the solution on per kW.
Example 9
A consumer is offered electricity at the following tariff:
GH¢ 70 per kVA of his maximum demand plus 5 pesewas per unit consumed. The consumer
has an aggregate motor load of 250 kW at power factor of 0.8 lagging. Calculate the
consumer annual bill for a load factor of 100%.
Solution 9
Annual load factor = = 1.0
33
= 250 8760 1 = kWh
Example 10
An industrial consumer is offered electrical energy from a) private oil engine generating
station b) public supply undertaking, calculate which scheme will be economical for the
consumer having a maximum demand of 2,000 kW of 0.8 p.f lag and 40% load factor for
each case:
Private Plant:
Capital cost GHC 1209; cost of fuel oil GHC 70 per tonne, fuel consumption 0.3 kg /kWh;
cost of lubricating oil 0.15 pesewa / kWh generated, cost of repairs 0.2 pesewas / kWh
generated ; Wages GH¢ 30000 per annum . Rate of interest and depreciation is 12%
Solution 10
Private Plant
Number of units consumed annually = 0.40 8760 2000 = 70.08 105 kWh
Other running charges = (0.15 + 0.25 + 0.2) pesewas / kWh = 0.6 pesewas / kWh
Total running charges = (147.168 103 +42.048 103) = GHC 189.216 103
34
Total annual cost in private plant scheme = 189,216 +144000 + 30000 = GHC 363.216 103
1.785 pesewas
Cost of maximum demand per unit = . =
Note: On comparing the cost per unit it will be observed that the public supply undertaking
will be cheaper to the consumer.
Example 11
Calculate the minimum two-part tariff to be charged from the consumer of a supply
undertaking from the following data: Generating cost per kWh is 3.6 pesewas; Generating
per kW of maximum demand is 50 GH¢; Total energy generated per year is 4380 10 4
kWh; Annual charges for distribution are GH¢125,000; Diversity factor for the distribution
network 1.25; total loss between station and consumer is 10%
Solution 11
Annual number of units generated = 4380 10 4 kWh; load factor of the station = 50%
Diversity factor =
35
= 1.25 10000=12,500 kW
Since 10% is the loss between the generating station and the consumers, so maximum
demand is met with 12,500 0.9 kW
In a two part tariff, one part covers the fixed cost and the other covers the generating cost.
Hence two part tariff is GHC 55.56 per kW of maximum demand plus 3,6 pesewas per unit.
Example 12
Two systems of tariff are available for a factory working 8 hours a day for 300 working days
in a year.
a) High voltage supply at GHC 4.50 per month per kVA of maximum demand.
b) Low voltage supply of 5.00 per month per kVA of maximum demand plus 5.05 pesewas
per unit.
The factory has an average load of 200 kW at 0.8p.f and a maximum demand of 250 kW at
the same p.f. The high voltage equipment cost GHC 50.00 per kVA and losses can be taken
as 4%. Interest and depreciation charges amount to 12%. Calculate the difference in the
annual cost between the two systems
Solution 12
Annual charge for maximum demand = 325.5 4.5 12= GHC 17,550.
Low Voltage
36
Now there is no loss of energy as no equipment is used by the consumer
Example 13
An industrial consumer has a choice between low voltage supply and high voltage supply at
the following tariff.
Low voltage supply GHC 47 per kW of maximum demand plus 4 pesewas per kWh.
High voltage supply GHC 45 per kW of maximum demand plus 3.5 pesewas per kWh.
In order to have the high voltage supply the consumer must have his own transformer and
switchgear which cost GHC 100 per kW. The losses in the transformation are 3% at full load.
Calculate the number of working hours per week above which the high voltage supply will be
cheaper for the consumers. Assume 50 working weeks per year. The normal rate of interest
and depreciation is 10%
Solution 13
Let the consumers load be 1,000 kW. Losses in the transformer = 3%
Let H be number of hours per week for which the consumer takes the supply.
1000 50
Number of units metered on the high voltage side = = 51500 H
0 7
The annual cost of the consumer when he takes supply high voltage = Fixed charges +energy
51500 35
charges +cost of high voltage equipment = + 1030 4.5 +10300)
100
= 46,350 +1802.5H + 10300 = 56650 +1802.5H
The total annual cost of the consumer when he takes low voltage = Fixed charges + energy
37
50 1000
charges = 1000 4.7 + = 47000 +2000H
100
In order that the two system may cost the consumer the same
Example 14
An electric supply system has a maximum load of 50 MW. The annual expenses of the
system are
i) Generation = GHC 750,000
ii) Fuel = GHC 2,800,000
iii) Transmission = GHC 245,000
iv) Distribution = GHC 2,150,000
v) Repairs = GHC 300,000
The number of units generated per year are 400 106 kWh .The consumers have an
aggregate maximum demand of 75MW. Evaluate a two part tariff to be charged from the
consumers. Assume that the fixed charges for generation, fuel, transmission, distribution and
repairs are 85%, 15%, 90%, 95% and 40% respectively. Losses in transmission and
distribution are 10%.
Solution 14
3 05 105
=> Fixed charges per unit = = GHC 46
75 103
015 10
Total running charges per unit = = 0.778 pesewas
3 107
Hence the two part tariff is GHC 46 per kW of maximum demand plus 0.778 pesewas per
kWh
38
Example 15
An electric supply undertaking has a maximum demand of 80MW with an annual load factor
of 50%. The capital cost of transmission is GHC 1,800,000 with a diversity factor of 1.4. T he
capital cost of transmission is GHC 2,000,000 with a diversity factor of 1.25. The efficiency
of the transmission system is 85% and that of distribution is 88%. The generating cost
inclusive of capital cost is GHC 75 per kW of maximum demand plus 2 pesewas per kWh.
Calculate the annual cost per kW of maximum demand and the cost per kWh supplied
a)at substation b) at the consumers premises.
Solution 16
Maximum demand of the station = 80 MW= 80 103 kW.
Total annual capital cost of generating 80 103 = 80 103 75= GHC 6,000 103
=> The sum of maximum demand of the substation = 1.25 80 103 = 100 103 kW
Total annual capital cost up to substation = Total capital cost of generating and transmission
= (6000 103 + 2000 103) =GHC 8,000 103
000 103
Capital cost per kW of maximum demand at substations = = GHC 80.
100 103
Cost of the units generated = 2 pesewas. Since efficiency is 85% , the cost of units at the
substation = = 2.35
0 5
Total cost incurred up to the consumers = Capital cost of generation + capital cost of
transmission + capital cost of distribution = GHC 6,000 103 + 2000 103 +1,800 103
= GHC 9,800 103
=> The sum of maximum demand of the substation = 1.40 100 103 = 140 103 kW
00 103
Cost per kW of maximum demand on the consumers premises = GHC = GHC
1 0 103
39
70.0.
Example 17
A hydroelectric station operates under a mean head of 30 m. The reservoir employed has a
catchment area of 3.5 108 m2. The rainfall in this area is 125 cm per annum. Determine the
capacity of the station for which it should be designed. Assume that 30% of the rainfall is lost
due to evaporation etc, 5 per cent of the head is lost in penstock , turbine efficiencies as 85%
,alternator efficiency as 90% and load factor as 50%.
Solution 17
Total quantity of water available in the whole year = Area in m2 rainfall in m actual
percentage of rainfall available = 4 108 1.25 10-2 0.70 = 3.5 108 m3.
where Q = flow rate in m3/ sec; g =acceleration due to gravity = 10 m /sec2 ; η = efficiency
of the system ; H = available head of water in the dam ; = density of water = 1000kg / m3
1
=> Installed plant capacity = η
load factor
1
= 11.1 0.727 30 1000 10 = 4,841,820 W = 4841820 W
05
3
= 4.842 10 kW.
EXERCISES
1. A choice is to be made in the following two electric supplies:
a) Public supply having a tariff of GHC 30 per kVA of the maximum demand and 8 pesewas
per kWh consumed.
b) private electric supply having a capital cost of GHC 10,000, cost of fuel burnt 20 pesewas
per kWh, cost of repairs and maintenance 1.5 pesewas per kWh , cost of storage 1.3pesewas
per kWh , the annual wage GHC 117,000 per annual . The annual interest and depreciation
is 12%. If the maximum demand is 1,800 kVA for a load of 33%; find out the most economic
scheme.
2. A consumer has a maximum demand of 3,500 kW at 0.8 p.f lag and a load factor of 40%
one or other of the following tariff
40
Tariff A
For first 500 kW GHC 70.00 per kW
For next 500 kW GHC60.00 per kW
For next 1,000 kW GHC 50.00 per kW
For next 1,000 kW GHC45.00 per kW
For all in excess GHC 40.00 per kW
Plus energy charges of 8 pesewas per kWh
Tariff B
GHC 50 per kW of the maximum demand plus energy charges of 6 pesewas per kWh. At the
stated load factor, find out the most economical tariff and the saving thus made. Also draw a
graph showing at total cost of supply in each against the maximum demand. From the graph
find out the load factor at which both system are equally economical.
3. Calculate the two part tariff on the basis of GHC per kVA of maximum demand and
pesewas per unit of energy charges for 80000kVA power station at the rate of GHC 250 per
kVA under the following two conditions:
Case I Case II
Maximum demand 32,000 kVA 40,000 kVA
Load factor 25% 40%
Coal burnt per unit 0.5 kg 0.4 kg
Wages, salaries etc GHC 190,000 GHC 200,000
Running charges GHC 35,000 GHC 40,000
p.f 0.8 0.8
4. A 100 h.p. motor is required for operation with a pump which is put in operation for 3,000
hours in a year. Two motors of same output are available namely:
The rate of interest and depreciation is 10 per cent and cost of energy 5 pesewas per kWh.
Compare the cost of two motors.
5. Compare the annual cost of having an electric supply of 2000 kW at a p.f of 0.9 lagging
with a load factor of 30 % from
a) Diesel generating plant having a plant cost of GHC 400,000, Cost of fuel oil GHC 100 per
ton , fuel consumption per kW generated is 0.75kg, and the other over head charges per kWh
generated is 5 pesewas , annual wages are GHC 14,400 and rate of interest and depreciation
is 10%.
b) From a public supplying company whose tariff is GHC 60 per kVA of maximum demand
plus 10 pesewas per kWh.
6. Calculate the generating cost per kWh delivered for a 60,000kW generating station for the
following detailed expenses:
Capital cost = GHC 200,000; Annual cost of fuel oil, wages and salaries GHC 150,000.
The annual load factor is 40% and the annual rate of interest and depreciation is 12%.
41
7. A supply is to be provided to a factory having a maximum demand 300 kW at 40% load
factor. Compare the cost of providing this load
a) a public supply having a tariff of GHC 70 per kW plus 5 pesewas per kWh consumed .
b) For a diesel plant costing GHC 240 per kW, annual cost of transformers switchgear etc is 1
pesewa per kWh, annual wages are GHC 6,500 cost of fuel and oil is 2 pesewas per kWh.
The annual rate of interest and depreciation is 12 %.
8 Calculate the two part tariff for one Electric Supply undertaking having the following data:
No of units generated = 500 105 kWh; Maximum demand: 150000kW
Cost of generation = GHC 30 105; Cost of transmission line =GHC 600 104
Cost of distribution = GHC250 104; Cost of fuel = 500 104. But of these 10% and 8% 5%
and 90% are running charges, the remainder is fixed charge. The loss of energy in
transmission and distribution is 10% if the load factor of the station is raised to 50% for the
same maximum demand, calculate the percentage saving in the overall cost per kWh.
9. The work cost of a power station per kWh with an annual output of 180 million units at a
load factor of 50% Are follows
Coal = 0.3 pesewas; Salaries and wages = 0.20 pesewas; Repairs and maintenance= 0.22
pesewas, oil stores and water 0.28 p
The station capital cost is GHC120 per kW of maximum demand. If the rate of interest and
depreciation is 10%, calculate the average cost per unit.
10. The owner of a new factory obtains power supply from a private oil engine generating
station and a public supply. Calculate the average price per unit his supply will cost him in
meach case using the following data: the maximum demand =800kW, load factor =30%,
supply tariff = 120 per kW of maximum demand plus 3 pesewas per unit. The capital cost of
plant required for supply is GHC 75000; Capital cost of plant required for private generating
station = GHC 1 million, Cost of fuel =GHC63 per tonne, fuel of consumption =0.02kg per
unit generated. The other costs of the private plant are:
Lubricating oil, stores and water = 0.075 pesewas per unit; Wages = 0.225 pesewas per unit;
Repairs and maintenance = 0.15 pesewas per unit
Assume interest and depreciation =10%.
The economic load dispatch problem involves two different problems. The first of these is the
unit commitment or pre-dispatch problem, wherein it is required to select optimally out of the
available generating sources to operate to meet the expected required load and provide a
specific margin of operation reserve over a specified period of time. The second aspect of
economic load dispatch is the online economic dispatch wherein it is required to distribute the
load among the generating units actually paralleled with the system in such a manner as to
minimise the total cost of supplying minute -to- minute requirement of the system.
Consider a simplified performance curve of boiler turbine –generator unit as shown in Fig 2.5
42
Fuel input in
million BTU per
hour
Pmin Pmax
Output in MW
From the graph, heat rate is defined as the ratio of fuel input to the corresponding power
output and hence the units are million Btu per MWh. From the heat rate curve, another
characteristic known as the incremental fuel curve can be obtained.
Which means it is a ratio equal to a small change in input to the corresponding small change
in output. Now as the incremental quantities tend to zero, incremental fuel tends to
Where F is the fuel input in million Btu per hr and P is the power output in MW. The units
associated with fuel rate, are therefore, million Btu per MWh and the incremental fuel cost is
expressed in terms of GHC per MWh which is obtained by multiplying the incremental fuel
rate by the fuel cost in GHC per Btu.
Incremental production cost consists of the incremental fuel cost plus the incremental cost of
labour, supplies, maintenance and water. Since it is difficult to express them exactly as a
function of an output and also since they form generally a small fraction they will hitherto be
considered equal to the incremental cost of fuel.
The increment efficiency is defined as the reciprocal of the incremental fuel or incremental
cost and is given as
43
2.17 Economic Dispatch Neglecting Losses
Min FT = ∑ (2.4)
Subject to
=∑ (2.5)
Where FT is the total fuel input to the nth unit, PD is the total load demand and Pn is the
generation of nth. By making use of the Lagrangian multiplier, the auxiliary function is
obtained as F = FT + λ (PD – ∑ n) (2.6)
Differentiating F with respect to the generation Pn and equating to zero gives the condition
for optimal operation of the system.
= +
Thus –λ=0
Since FT = F1+ F2+…+ Fn, = =λ
= ... = =λ (2.7)
The incremental production cost of a given plant over a limited range is represented by
= Fnn Pn + fn (2.8)
The equation (2.7) means that the machines be so loaded that the incremental cost of
production of each machine is the same. It is to be noted here that the active power generation
constraints are taken into account while solving the equations which are derived above. If
these constraints are violated for any generator it is tied to the corresponding limit and the
rest of the load distributed to the remaining generator units according to the equal incremental
cost of production. The simultaneous solution of equations (2.5) and (2.7) gives the economic
operating schedule. Therefore any good technique for solving a set of linear equations can be
used but since the inequality constraints have been taken into account, the following iterative
method is used:
44
1. Assume a suitable value of λ(0). This value should be more than the largest intercept of the
incremental cost characteristics of the various generators.
2. Compute the individuals generations P1,P2,…,Pn corresponding to incremental cost of
production from equations (2.7). In case generations at any of the buses are violated
during that iteration and remaining load is distributed among the remaining generators.
3. Check if the equality,
∑ = PD is satisfied
4. If not, make a second guess λ1 and repeat the above steps. The selection of λ1 in this step
must of course be guided by the result in step (3). For a example if we find that the total
generation is less than PD then correct value of λ to be selected would be
If equality is satisfied, the generations as calculated in step (2) give the optimum operating
strategy.
Worked example
Example 18
Minimum load on each unit is 10MW; total load to be supplied is 150MW. Determine the
operating schedule.
Solution 18:
Assume λ = . (more than the largest of the intercepts ( , and 1.5) Determine generations P1
and P2.
P1 = = MW P2 = MW
Since generation is greater than the demand, therefore next approximation of the λ should be
less than 2.8. Also since load demand is 150MW, the difference between PD and Pn is not
much. Therefore, value of λ should not be very much different from 2.8 Let it be 2.7.
With this, the generations are 58.4 + 80 = 138.4MW, which is less than the demand.
Therefore, next approximation of λ should be greater than 2.7; say it is 2.75.
Corresponding to this, generations are 62.5 + 83.4 =145.9 MW i.e. the generations are
smaller than the demand. Next approximation to λ = .7 gives generations as 65 + 85.4 =
150.4 MW. It is to be seen here that the generations are converging as better approximations
to λ are chosen and finally a value between 2.77 and 2.78 will give the optimal generation
schedule.
45
It can be seen that this method does not sense the location of changes in the loads. As long as
the total load is fixed, irrespective of the location of loads, the solution will always be the
same and in fact for this reason the solution may not be feasible in the sense that the load
voltages may not be within specified limits.
In case of an urban area where the load density is very high and the transmission distances
are very small, the transmission loss could be neglected and the optimum strategy of
generation could be based on the equal incremental production cost as outlined above.
Whereas if the energy to be transported is over relatively larger distances with low load
density, the transmission losses in some cases may amount to 20% to 30% of the total load
and it then becomes very essential to take these losses into account when developing an
economic dispatch strategy.
Before an optimum strategy for load scheduling is derived, the need for inclusion of losses is
further stressed by the following example.
Consider Fig. 2.6 which consists of two identical generators i.e. generators with identical
incremental production cost. If generator 2 has a local load, according to equal incremental
production criterion, the total load must be shared equally by both generators, i.e. each
generator should supply half of the total load. The common sense tells us that it is more
economical to let generator 2 supply most of the local load because generator 1 has to supply
in addition to the load, the transmission losses also. Therefore, the criterion of sharing load by
Incremental production cost does not hold good under such situation and a strategy must be
evolved which takes into account the transmission losses also.
2
1
R+jX
Load
Min FT = ∑ (2.9)
Subject to PD + PL - ∑ =0 (2.10)
Where PL is the total system loss which is assumed to be a function of generation and the
other term have their usual significance.
F = FT + λ (PD + PL ∑ )
46
The partial differential of this expression when equated to zero gives the condition for
optimal load dispatch, i.e.
= +( – 1) = 0 or
+ =λ (2.11)
Here the term is known as the incremental transmission loss at plant n and λ is known as
the incremental cost of received power in GHC per MWh.
The equation (2.11) is a set of n equations with (n+1) unknowns. Here n generations are
unknown and λ is unknown. These equations are known as coordination equations because
they coordinate the incremental transmission loss with the incremental cost of production.
To solve these equations the loss formula equation (2.12) is expressed in terms of generations
and is approximately expressed as
PL = ∑ ∑ (2.12)
Where Pm and Pn are the source loadings, Bmn the transmission loss coefficients. The formula
is derived under the following assumptions:
1. The equivalent load current at any bus remains a constant complex fraction of the total
equivalent load current.
2. The generator bus voltage magnitudes and angles are constant.
3. The power factor of each source is constant.
= 2∑ (2.13)
Also
= FnnPn + fn (2.14)
FnnPn + fn + ∑ λ (2.15)
Pn(Fnn + λBnn) = - λ (∑ - fn + λ
47
∑
Pn = ( 2.16)
1. Assume a suitable value of λ0. This value should be more than the largest intercept of the
incremental production cost of the various generators.
2. Calculate the generations based on equal incremental production cost.
3. Calculate the generation at all the buses using the equation
∑
Pn =
It is to be noted that the powers to be substituted on the right hand side during zeroth iteration
correspond to the values as calculated in step 2. For subsequent iterations the values of
powers to be substituted correspond to the powers as calculated in the previous iteration. In
case any of the generations violates the limit the generation of that generator is fixed at the
limit violated.
4. Check if the difference in power at the all generator buses between two consecutive
iterations is less than a pre-specified value. If not, go back to step 3.
5. Calculate losses using the relation PL = ∑ ∑ and calculate
∑ - - ]
6. If P is less than €, stop the calculation and calculate the cost of generation with these
values of powers.
7. Update values of λ and go back to step 3 . .
Worked Example
Example 19
Consider a simple two plant system.
Assume that the loss formula coefficient in 1/MW units are given by
m n Bmn
1 1 0.0015
1 2 -0.0005
2 2 0.0025
Also assume
48
Solution 19
Now P1 = : P2 =
P1 = = =
P2 = = =
= 0.01P2 +2 or P1 = = 60 MW P2 = =110 MW
Substituting these values of generation in the expression for P1 and P2we get
P1 = = 49.77 MW
P2= =54,61MW
P1 = = 41.68 MW
P2= = 52.53MW
P1=41.38 P1 = 41.37
P2=52.50 P2 = 52.50
49
In the above problem 𝛌 is given and we are asked to find out the operating schedule.
Normally in an actual problem, the load demand is given and we are asked to find out the
economic schedule. To understand the utility of the coordination equation let say that the load
to be met is 160MW. With loss coefficient and the incremental production cost given to the
problem above, we are asked to determine the economic operation schedule.
P1 = = and
P2 = =
Starting with P2= 105 , The powers from this equations are
At this juncture let us give a thought to our solution. Since P1+P2<160, this value of 𝛌 = 2.55
is not correct and since P1+P2 160 therefore 𝛌 should be far greater than 2.55. Let this
value be 5.0. With this value of 𝛌 P2 = 350 from the ICP equation, and coordination equation
becomes
P1 = =
P2 = =
Starting with P2= 350MW, the values of P1 and P2 in various iteration using the coordination
equation are
50
Again we should give a thought to our solution . This time the sum of generation
Let this value 𝛌 =3.75. With this value of 𝛌 the coordination equations are
P1 =
P2 =
Since the difference between the two consecutive generations is less than 0.1MW, we stop
here and since P1+P2 =189.51 MW which is not far off from the load of 160 MW. We
therefore evaluate the losses:
This is 3.2 MW more than the actual demand therefore, we cannot terminate here .We are
guided by the PD calculated for assuming a suitable value of . Since PD calculated is more
than the actual one, therefore we take a lower value of . It will be found out that
P1 = ; P2 =
And with P2 = 219 MW as initial value, the generations during various iterations are
P1 = 95.86 MW
P1 = 89.41 MW
Another possibility is that we may take the transmission losses into account but they need not
be coordinated. If we don’t coordinate the losses with the incremental production cost, the
generation schedule so obtained will be costlier as compared to when they are coordinated.
An illustration with the help of previous example will make clear the advantage of the
coordination of losses.
The set of equations when losses are included but not coordinated will be
0.001P1+2 = 0.001P2+1.5
P1 + 200 = P2 + 15 P2 = P1 + 50
Neglecting the higher value as the higher value is much more than the total load on the
system. P2 = 73.6 + 50 = 123.6 MW
Comparing the cost between the two, it is seen that cost with losses coordinated is less than
when they are not coordinated and the difference in cost is
436.06 – 411.74 = GHC 24.32 per hr.
+λ =λ or = λ (1 - ) or (
or (2.17)
Where Ln is the penalty factor of the plant n and is given by
52
Ln = (2.18)
Since the penalty factor has been derived from the coordination equation, the solution of the
problem using penalty factor gives precisely the same results.
Worked Examples
Example 20
Determine the economic operating schedule and the corresponding cost of the generation if
the maximum and the minimum loading on each unit is 100 MW and 25 MW, the demand is
180 MW and the transmission losses are neglected. If the load is equally shared by both the
units , determine the saving obtained by loading the units as per equal incremental production
cost.
Solution 20:
(b) If the load on each unit is 90 MW, the cost of generation will be
53
F1 = GHC 5340/hr F1 = GHC 4875/hr
Example 21:
Determine the incremental cost of the received power and the penalty factor of the plant
shown in Fig. E.19.2 below if the incremental cost of production is 0.1P1 + 3Rs per
MWh
load
PL = 2MW PD=8MW
P1=10MW
Solution 21:
The penalty factor =
Example 22
A two-bus system is shown in Fig. 2.8. If a load of 125MW is transmitted on plant 1 to the
load a loss of 15.625 MW in is incurred. Determine the generation schedule and the load
demand if the cost of the received power is Rs. 24/MWhr. Solve the problem using the
coordination equations and the penalty factor method approach. The incremental production
cost of the plants are
1 2
P2
P1
Load
Fig. 2.8.
54
0.025P1 + 15 0.05P2 + 20
Solution 22:
Since the load is at bus 2 alone, therefore the losses in the line will not be affected by
generator of plant 2.
λ =λ
0.025P1 + 15 + λ 0.00 P1 = λ
0.025P1 + 15 + 0.048P1 = 24
0.073P1 = 9 P1 = 123.28MW
0.05P2 + 20 = 24 or P2 = 80 MW
The solution using penalty factor is as follows: The penalty factor for plant 1 is
= 24
= 24
P1= 123.28MW
Similarly, since is zero, L2 = unity, i.e. the incremental cost of received power equals
the incremental cost of production.
55
0.05P2+ 20 = 24 or P2 = 80 MW
Example 23
Assume that the fuel input in Btu per hour for units 1 and 2 are given by
The maximum and minimum loads on the units are 100MW and 10MW respectively.
Determine the minimum cost of generation when the following load (Fig. 2.9) is supplied.
The cost of fuel is Rs. 2 per million Btu.
150MW
50MW
Fig 2.9
Solution 23:
0.048P1 + 8 0.08P2 + 6
(i) When load is 50MW ; For economic loading the conditions are
= and P1+P2 = 50
56
= P1=78.126MW and P2=71.874MW
EXERCISES
1. Incremental cost fuel cost is GHC per megawatt hour for two units in a plant are given by
0.1P1 + 20
0.12P2 + 16
The minimum and maximum load on each unit is to be 20 MW and 125MW respectively.
Determine the incremental fuel cost and the allocation loads between units for this minimum
cost when loads are i) 100MW ii) 150MW . Assume both units are operating.
2. Determine the saving in fuel cost in GHC per hour for the economic distribution of a total
load of 200MW between the two units of plants described in problem 1 compared with
equal distribution of the same load.
3. A system consists of two plants connected by a tie and a load is located at plant two. When
100MW are transmitted from plant one a loss of 10MW takes place on the T-line . Determine
the generating schedule at both the plant and the power received by the load when λ for the
system is GHC 25 per megawatt hour and the incremental fuel cost are given by the equation
0.031P1 + 17 GHC/ MWh ; 0.06P2 + 19 GHC/MWh
4. If the power received by the load in the previous example is 200 MW, determine the
savings in GHC per hour obtained by coordinating rather than simply including the
transmission loss and not coordinating the loading of the plant.
0.1P1 + 22 ; 0.12P2 + 16
where F is in GHC per hour and P is in MW. If both units operate at the same at all time and
maximum and minimum load on each unit are 100 MW and 20 MW respectively. Determine
the economic operating scheduling of the plant for loads 40 MW, 60 MW, 120 MW, 160
MW and 180 MW neglecting the transmission losses.
The loss coefficient of the system are given by B11= 0.005 , B12=-0.0012 and B22 = 0.002.
The load to be met is 200MW, determine the economic operating schedule and the
corresponding cost of generation, if i) the transmission line losses are coordinated ii) the
losses are located but not coordinated.
57
3.1 Single line diagram
A very practical way of representing a power system is by means of simple symbols. The
following points are worth noting:
Some standard symbols for various apparatus are shown in the table below.
Table 3.1: Major Components in an Electrical Power System and their Symbols
1 Generator
1 Transformer
2 Lightning Arrester
3 Current Transformer
4 Circuit Breaker
Capacitor Voltage
5
Transformer
6 Disconnect Switch
58
7 Voltage Transformer
8 Switching
Arrangement/Substation
9 Distribution Transformer
The purpose of the one-line diagram is to supply in concise form, significant information
about the system. The amount of information included on the diagram depends on the
purpose for which the diagram is intended.
Figure 3.2 is a one-line diagram of a very simple power system.
59
Figure 3.2: Single line diagram of a simple power system
Two generators, one grounded through a reactor and one through a resistor, are connected to
a bus and through a step-up transformer to a transmission line. Another generator, grounded
through a reactor, is connected to a bus and through a transformer to the opposite end of the
transmission line. A load is connected to each bus. On a one-line diagram, information
about the loads, the rating of the generators and transformers, and reactances of the different
components of the circuit, is often given.
G1 G2
Generating
Generating Stations
medium voltage
11 kV - 25kV
Transmission
stations
Extra High voltage Britain
Transmission 275 kV - 400kV
345 kV - 765kV
USA
Transmission
345 kV - 400kV Interconnecting
substations
Britain G3 Generating
High voltage 132 kV medium voltage
sub -transmission 11 kV - 25kV
115 kV (USA) Tie line
Transmission
substations
Medium voltage
Primary
distribution
33 kV , 11kV, Heavy Industry
6.6kV medium voltage
Distribution
substations
Distribution
Low voltage
Secondary
distribution small Industry
415 V/ 240V, ,Residence,Commercial
.
Fig 3.3 A single line diagram of a generating, transmission and distribution system
60
G1 G2
Generating
Generating Stations
medium voltage
11 kV - 15kV
Transmission
stations
High voltage
Transmission
161 kV
Interconnecting
substations
High voltage
sub -transmission
33 kV
Transmission
substations
Medium voltage
Primary
distribution
33 kV , 11kV, Heavy Industry
6.6kV medium voltage
Distribution
substations
Low voltage
Secondary
distribution small Industry
415 V/ 240V, ,Residence,Commercial
Fig 3.4 A single line diagram of a generating, transmission and distribution system in Ghana
3.5 Sub-transmission/Distribution
The sub-transmission networks usually have a loop structure but the distribution networks are
normally radial. Most of ECGs major substations have double bus with bus tie (coupler)
breaker arrangement. Most of the distribution networks have single bus arrangements
(3.4)
In electrical engineering the three basic quantities are voltage ,current and impedance . If any
two of them are selected as the base or reference values the third one will have a base or
reference value depending upon the other two eg. If V and I are the base voltage and current
in a system , the base impedance of the system is fixed and is given by Z=
The rating ot the equipment in a power system are given in terms of operating voltage and the
capacity in kVA . Therefore it is found convenient and useful to use voltage and kVA as the
the base quantities.
Let Vbase be the base Voltage and kVAbase be the base kilovolt amperes, then
V p.u = (3.5)
I base = (3.6)
63
I p.u = = (3.7)
= (3.10)
This means that per unit impedance is directly proportional to the base kVA and inversely
proportional to square of base voltage . Normally per unit impedance of various equipment
corresponding to its own rating voltage and kVA are given and since we choose one common
base kVA and Voltage for the whole system ,therefore it is desired to find out the base
voltage and kVA . If the individual quantities are Zp.u old . kVA old and Vold and the
common base quantities Zp.u new, kVA new, Vnew, then
Zp.u new = Z p.u old ( (3.11)
The per unit value of an equipment corresponding to its own rating is given by
Z = (3.12)
where Z -absolute value of the impedance of the equipment
With per system there is less chance of making mistake in phase and line voltages, single
phase or three phase quantities.. Also per unit impedance of a transformer is the same
whether refered on to the primary or secondary side of the transformer which is not the case
when considering absolute value of impedance. This is illustrated below
Let the impedance of the transformer be Zs, then
Zp = Zs ( (3.13)
Where Vp and Vs are the primary and secondary voltages of the transformer
Now Zp p.u = = Zs ( = =
= Zs = Zs = = Zs p.u (3.14)
Hence per unit impedance of a transformer referred to primary side Zp pu is equal to the per
unit impedance referred to the secondary side Zs pu.
The base values in a system are selected in such a way that the per unit voltages and current
in system are approximately unity. Sometimes the base kVA is equal to the sum of ratings of
the various equipment on the system or equal to the capacity of the largest unit.
The different voltage levels in a power system are due to the presence of transformers.
Therefore the procedure for selecting the base voltage is as follows.
A voltage corresponding to any part of the system could be taken as the base and the voltages
in the other parts of the circuit separated from the original part by transformers are related
through the term ratio of the transformer. If the primary side is Vpb then on the secondary side
of the transformer Vsb=Vpb
Where Ns and Np are the turns of the transformer on the secondary and primary respectively.
64
3.7.1 Advantages of P.U. Method
1. It represents results in more meaningful data when the relative magnitudes of similar
circuit quantities can be compared directly.
2. It facilitates solution of circuits at different voltage level and power ratings.
3. It is independent of voltage changes and phase shift through ‘impedance’.
4. Manufacturers quote pu impedance values on the base of ratings on equipment nameplates.
5. Per unit impedance of any transformer is the same when referred to either the primary or
the secondary side.
6. Per unit values of similar power equipment lie within narrow ranges and it is relatively
easy to select.
7. The use of 3 is eliminated in 3-phase calculations, simplifying the calculations.
8. The product of two quantities expressed in per unit is expressed in per unit itself.
9. The driving or source voltage usually can be assumed to be 1.0pu for fault and voltage
calculations.
10 There is less chance of confusion between single-phase and three-phase power or between
line-to-line and line-to-neutral voltage.
11. Per unit impedance of a transformer in a three-phase system is the same regardless of the
type of winding connections.
Worked Examples
Example 24
Convert 2 into per unit on an 11 kV, 1000 kVA base.
Solution 24
kVbase 2 112
Base impedance Z base 121
MVAbase 1
Z actual 2
Per unit of 2 = Z pu 0.0165
Z base 121
Example 25
An 11kV 15MVA generator has reactance of 0.015 referred to its ratings. The new bases
chosen for calculations are 110 kV and 30 MVA. Calculate the new pu reactance.
Solution 25
2
MVAnew base kVold base
X pu new X pu old
MVAold base kVnew base
2
30 11
0.15
15 110
0.003 pu
Example 26
A single-phase 400/200V 10kVA transformer has a reactance of 2 referred to its high side.
Calculate the per unit reactance of the transformer.
65
Solution 26
HV side kVbase ( hv ) 0.4 kV
kVbase(hv) 2 0.4 2
Z base ( hv ) 16
MVAbase 0.01
Z actual ( hv ) 2
Z pu ( hv ) 0.125 pu
Z base ( hv ) 16
LV side kVbase (lv ) 0.2 kV
2
kVbase (lv ) 0.2 2
Z base (lv ) 4
MVAbase (lv ) 0.01
2
N
2
200
Z actual (lv ) Z actual ( hv ) lv Z actual ( hv )
N hv 400
0.5
Z actual (lv ) 0.5
Z pu (lv ) 0.125 pu
Z base (lv ) 4
Therefore Z pu(lv) Z pu( hv) , that is, for transformers, per unit reactance is the same on both
sides.
Example 27
A 100MVA 33kV 3-phase generator has a sub transient reactance of 15% . The generator is
connected to the motors through a transmission line and transformers as shown in fig 3.
The motors have rated inputs of 30MVA, 20MVA and 50MVA at 30kVwith 20% sub
transient reactance,. The three phase transformers are rated as 110MVA, 32 kV/ 110kV .
with leakage reactance 8%. The line has reactance of 50 ohms .Using the generator rating as
the base quantity in the generator circuit, determine the base quantities in other parts of the
system and evaluate the corresponding p.u values..
30 MVA, 30kV/
kV, 20%
100 MVA,
33kV, 15%
j 50Ω
Y Y
20 MVA, 30kV/
kV, 20%
50 MVA, 30kV/
kV, 20%
Fig 3.5
Solution 27
66
Assuming base values as 100MVA and 33kV in the generator circuit, the per unit reactance
of the generator will be 15 %. The base value of the voltage in the line will be
33 = 113.43 kV
In the motor circuit the base voltage is 113.43 =33kV
The reactance of the transformer is given as 8% corresponding to 110MVA 32kV . Therefore,
corresponding to 100MVA and 33kV, the per unit reactance will be (using equation 3.11)
ZT p.u = 0.08 ( = 0.06838 p.u
the per unit impedance of the line ZL= = 0.3886 p.u
J0.3886 J0.06838
J0.06838 p.u p.u
p.u
J0.3305
p.u
J0.5509
p.u
J0.826
J0.15 p.u
p.u
1 3
2
Fig 3.6
Example 28
Obtain the p.u impedance (reactance ) diagram of the power system in fig 3.7 for a short
circuit study choose a common MVA base of 30 and a voltage base of 33kV line –line on
the transmission line .The reactance data of the system components are as follows
Generator 1 : 30MVA, 10.5 kV, X= 1. Ω ; Generator 2 : 15MVA, . kV, X= 1. Ω
Generator 3 : 5MVA, . kV, X= 0.5 Ω ; Transformer1 : 15MVA, 33/ 11 kV,
X= 15. Ω/ ph ; Transformer2 : 15MVA, 33/ . kV, X= 1 Ω/ ph
Transmission line : 20.5/ ph ; Load A : 15MVA, 11 kV, 0.9 lagging p.f
Load B : 15MVA, 6.6 kV, 0.85 lagging p.f
67
15 MVA, 33 /
30 MVA, 15 MVA, 33 /
11kV, 15.2Ω
10.5kV, 1.6Ω 6.2kV, 16Ω
j 20.5Ω
Y
G1
T2 25 MVA,
T1 6.6kV, 0.56Ω
Load A
15 MVA, 11 kV
0.9 lagging p.f
Load B
15 MVA, 6.6
kV 0.9 lagging
p.f
Fig 3.7
Solution 28
If the voltage base for the transmission line is 33kV then the base voltages on generator 1 and
2 side of the circuit are 11kV and 6.2kV respectively. The p.u reactances of the various
components are as follows
Transmission line Z L p.u = 20 = 0.564 p.u
Transformer ZT1 p.u = 15.2 = 0.418 p.u ; Transformer ZT2 p.u = 16 = 0.44 p.u
Generator ZG 1 p.u = 1.6 = 0.396 p.u ; Generator ZG 2 p.u = 1.2 = 0.936 p.u
Generator ZG 3 p.u = 0.56 = 0.437 p.u
J0.564
J0.418 J0.44 p.u
p.u
p.u
J0.956 J0.437
p.u p.u
J0.316
p.u
2 3
G2 G3
1 G1
Fig 3.8
4.1 General
In the early days of the transmission of electric power, conductors were usually copper, but
aluminium conductors have completely replaced copper because of
i) the much lower cost and
68
ii) lighter weight of an aluminium conductor compared to a copper
of the same resistance and the fact that an aluminium conductor has a larger diameter than a
copper conductor of the same resistance is also an advantage. With a larger diameter, the
lines of flux originating on the conductor will be farther apart at the conductor surface for
the same voltage. This means a lower voltage gradient at the conductor surface and less
tendency to ionize the air around the conductor. Ionization produces the undesirable effect
called corona.
Symbols identifying different types of aluminium conductors are as follows:
AAC all-aluminium conductors
AAAC all-aluminium-alloy conductors
ACSR aluminium conductor, steel-reinforced
ACAR aluminium conductor, alloy-reinforced
Aluminium-alloy conductors have higher tensile strength than the ordinary electrical-
conductor grade of aluminium.
ACAR has central core of higher-strength aluminium surrounded by layers of electrical-
conductor-grade aluminium. The ACSR consists of a central core of steel strands surrounded
by layers of aluminium strands. A typical steel-reinforced aluminium cable (ACSR) has 7
steel strands forming a central core, around which are two layers of aluminium strands. There
are 24 aluminium strands in the two outer layers. Such an ACSR conductor is specified as 24
Al/7 St, or simply 24/7. See Fig 4.1
69
lines cost at least 8 times as much as overhead lines, and 20 times as much at the highest
voltage.
70
Uniform distribution of current throughout the cross-section of a conductor exists only for
direct current. As the frequency of alternating current increases, the non-uniformity of
distribution becomes more pronounced. An increase in frequency causes non-uniform current
density, and the alternating current tends to be confined to the surface of the conductor. This
effect is called skin effect. The equivalent resistance is called the AC resistance, Rac .
The skin effect depends on the following factors:
a) Nature of material b) diameter (increases with diameter) c) frequency (increases with
frequency) d) shape of wire (less for stranded conductor than for solid conductor)
Worked Example
Example 29
Calculate the resistance of 304.8 m of solid round aluminium alloy conductor of diameter
7.35 mm at 200C and 500C. The temperature coefficient of the conductor at 200C is 0.00403.
Solution
l 304.8
At 200C, the resistance is R20 3.22 10 8 2
0.204
A 7.35 10
3
2
At C, the resistance is R R20 1 20. Therefore the resistance at 500C is
0
L=2 ( ⁄ + In ( ) = 4 ( ⁄ + In ( ) (4.5)
where d = distance between the conductors r = radius of conductor
For a three phase conductors arranged as shown in fig 4.2
The inductance L per phase is half that of a single-phase two-wire ( two conductors) line L =
2 ( ⁄ + In ( ) (4.6)
71
2r
d
d
d
Fig 4.2 A typical arrangement of three phase conductors
Daa
a C
D
aA
b B
c A DAA
For the arrangement shown in fig 4.3 ,the inductance per conductor can be calculated as
follows:
⁄
The self GMD of a phase ( a ) Dsa =
The self GMD of a phase ( b ) Dsb = (Dbb DbB DBb DBB ⁄
⁄
The self GMD of a phase ( c ) Dsc =
72
⁄
Therefore the self GMD (abc) =Ds (abc) =
⁄
The Mutual GMD (between phases) ( ab ) DMab =
⁄
The Mutual GMD (between phases) ( ac ) DMac =
⁄
The Mutual GMD (between phases) ( ac ) DMbc =
⁄
Therefore the Mutual GMD (abc) =Ds =
L=2 (In ( )
The concept of Self and mutual geometric distances (self GMD and mutual GMD ) can also
be used to calculate capacitance. The capacitance of a conductor with respect to the neutral is
C= = (4.10)
Note here Daa = r but not 0.7788r ( because the original formula capacitance per conductor
to neutral does not contain ⁄ )
load
VS VR
74
parameters are lumped or uniformly distributed if the shunt admittance is neglected, since the
current is the same throughout the line in that case.
The circuit is solved as a simple series AC circuit. Since there are no shunt arms, the current
is the same at the sending and receiving ends of the short line and thus
IS=IR (short line) (4.11)
The sending-end voltage V s is the phasor sum of the receiving-end voltage VR and the line
drop IRZ where Z R jX is the total series impedance of the short line. Thus
VS= VR +IRZ = VR + IR (R+ jX) = VR+ IRR+ j IR X (4.12)
With VR as the reference phasor and IR = IR∟-ƟR
Where ƟR is the phase angle between VR and IR; IR is supposed to be lagging behind VR)
We obtain VS = VR∟0 + (R+jX) IR∟-ƟR = VR∟0 + ZL∟-ƟL IR∟-Ɵ (4.13
Also Vs = VR(1+j0) + (R+jX) (Icos ƟR- jIR sin ƟR) = VR(1+j0) + IRRcos ƟR+ j( IR Xcos ƟR-
IRRsin ƟR) = VR + IR Rcos ƟR + IR X sin ƟR + IRX cos ƟR - IR R sin ƟR
=> Vs2 = (VR + IRRcos ƟR+ IR Xsin ƟR ) 2 + (IRXcos ƟR-IRRsin ƟR)2 (4.14)
=>√ (4.15)
The second term of equation 4.14 is negligible except at low leading p.f .
Neglecting the second term of equation (4.14) gives
Vs = (VR + IRRcos ƟR+ IR Xsin ƟR ) (4.16)
Given PR, QR,VS and VR not known then from equation 4.16
Vs = VR + IRRcos ƟR+ IR Xsin ƟR , we obtain
Vs = VR + R+ X => VSVR=VR 2+RPR + XLQR
=> 0 = VR2-VSVR+RPR+XLQR
√
=> VR = (4.17)
Worked Example
Example 30
A 3 –phase 50 HZ transmission line have conductors of sections 90 mm2 and effective
diameter of 1 and are placed at the vertices of an equilateral triangle of side 1metre. The line
is 20 km long and delivers a load of 10MW at 33kV and p.f 0.8. Neglect capacitance and
assume temperature of of 20 oC. Determine the efficiency and the regulation of the line
Solution 30
75
The inductance of the line = L = 2 ( In ( )=2 In ( )
=10.59 H / metre.
Inductance of 20 km length of line = 2.119
Inductive reactance = 2 𝞹 50 2.119 = . 5Ω
Now resistance of copper conductor at 20oC is per metre when the section is 1 mm2
Resistance = = 3.83 Ω
Efficiency = = 0.9479
To determine the voltage regulation we determine the sending end voltage
VS = (VR cos ƟR + IRR ) + j(VR sin ƟR + IRX)
= (19052 0.8 +218.68 3.83) +j(19052 0.6 + 218.65 6.65) = 16079 + j12885
= 16079 +j12885
VR = 20605 volts
Since it is a short line ,three phase transmission the voltage regulation will be
% Voltage regulation = 100 = 8.15%
Example 31
An overhead transmission line delivers 5000kW at 22kV at 0.8 p.f lagging . The resistance
and reactance of each conductor is Ω and Ω respectively . Determine a)the voltage
b) the percentage voltage regulation c ) the transmission efficiency.
Solution 31
CosƟR = 0. SinƟR = 0.6 ; VR = = 12,700 kV ( per phase)
√
76
sending end line voltage = √ 13815.2 =23.929kV
Example 32
A three phase line delivers 3600kW at a p.f of 0.8 lagging to a load . If the sending end
voltage is 33kV ,determine a) the receiving end voltage , VR b) line current c)
transmission efficiency . The resistance and reactance of each conductor is 5.31 and 5.54
Solution 32
√
VR = ; VS= ;
√
PR=3.6MW ; QR = 3.6 = 2.7 MW
PR per phase = = 1.2 MW ; QR = = 0.9 MW
√
√ √
VR = = 18.4365Kv
ii) Line losses on the three phase = 3 I2R = 3 81.362 5.31 = 105.45kW
77
R/2 L/2 R/2 L/2
Is
Vc IR
I C
VS Y =jωC
VR
R L
IS IL IR
I A
VR
Y/ 2 =jωC / 2 I B
load
VS
Y / 2 =jωC / 2
The – network is in more general use but there is little difference in accuracy between the
two. From the - network, we obtain (all quantities are complexors).
From the – network,
IB = YVR, IA = YVS (4.20)
IL =IB + IR = IR + YVR (4.21)
IS = IA + IL
= IA + IB + IR
= IR + YVR + YVS (4.22)
Also
[ ]=[ ][ ] (4.25)
On no load, IR = 0 and
78
VS = VR (1+ YZ) (4.26)
Hence, the magnitude of the VR on no load
| |= | | (4.27)
IB = IL = IR + VRY (4.28)
Worked Examples
Example 33
Using the nominal- method find the sending end voltageVS, the receiving end voltage ,VR
and transmission efficiency of a 250 km 3- , 50Hz transmission line delivering 25MVA at
0.8 pf lagging to a balanced load at 132KV. The parameters of the line are as follows:
Resistance = 0.11 km-1 ; Inductance = 1.24mH km-1 ; Capacitance = 0.0094 F km-1
Solution33
R = 0.11 250 = 27.5 ; XL = 100 (1.24 10-3) 250 = 97.4
Z = R + jX = 27.5 + j97.4 = 101.2 74.2o ; Y = j314 0.0094 250 = 7.38 10-4 90o
V. R = % = 12.3%
(iii)IL = IR + VRY
= 109.3(0.8 – j0.6) + j
79
= 96.4%
C. Long Line:
Here the distributed parameters are used. i.e. the parameters are considered to be uniformly
distributed throughout its length.
R L R L R L R L
IS
IR
VS C C C
VR
Treatment based on distributed parameters yields the following equations for conditions at
the load.
[ ] [ ][ ]
Example 34
80
A 275kV 3- transmission line of length of 482km is rated at 840 A. The value of resistance,
inductance and susceptance per phase per km are 0.077 , 1.05mH, 3.6 respectively.
The receiving end voltage is 275kV when full load is transmitted at 0.85 p.f lagging.
Calculate the sending end voltage using
(a) nominal -network
(b) approximately long line equation and
(c) the exact long line
Solution34
IL = IR + charging current
= (714 – j442.5) + ( )
√
= 720 – j436 + j141 = (714 – j295) A
= 74200 + j104137.5
VS = 15900 + ILZ
| | = 255395.5 V
= 255kV
VS line = √ (255) 442kV
(b) Using approximately long line equations, consider only the first two terms of the series
expansion of the hyperbolic function.
YZ = j [37.5 + j160] = -0.284 + j0.0666
1+ = (1- )+j
= 0.858 + j0.033
249kV
VS = √ (249) = 431kV
=√ =√
=
= 0.062 + j0.54
ZC = √ =√
= 304.19 -6.6o
Cosh (0.062 + j0.54) = 0.86 + j0.031
Sinh (0.062 + j0.031) = 0.053 + j 0.5 = 0.5145 84.05o
VS = VR cosh + ZC sinh (IR)
= 159 (0.86 + j0.03) + (304.19 -6.6o) (0.51 o
) 0.84 - 31.79o kV
= 159 (0.86 + j0.03) + 131.46 45.66o kV
= 228.85 + j94.18 = 247kV Vsline = 247√ 428 kV
In a four-terminal passive network, the voltage and current on the receiving and sending end
are related by the following pairs of equations
(4.29)
(4.30)
Where A, B, C, D are constants of the network. The transmission line is also a four-terminal
network and it is now desired to find these constants for short transmission line.
Before these constants are determined it is desirable to understand what these constants are.
From equation (4.29),
|
This means A is the voltage impressed at the sending end per volt at the receiving end when
receiving end is open. It is dimensionless.
|
B is the voltage impressed at the sending end to have one ampere at the short circuited
receiving end. This is known as transfer impedance in network theory.
From equation (4.30)
|
C is the current in amperes into the sending end per volt on the open-circuited receiving end.
It has the dimension of admittance.
|
82
D is the current at the sending end for one ampere of current at the short circuited receiving
end. The constants A, B, C, and D are related for a passive network as follows:
AD – BC = 1
This relation provides a good check on the values of those constants. The sending end voltage
and current can be written from the equivalent network as
(4.31)
(4.32)
Comparing the coefficients of the equation (4.31) and (4.32) with equations (4.29) and (4.30)
respectively, the constants for short transmission line are
A=1
B=Z
C=0
D=1
Checking the values of A, B, C, and D with the relation
AD – BC = 1
1 · 1 - Z· 0 = 1
The ABCD constants can be used for calculation of regulation of the line as follows:
Normally the quantities P, and at the receiving end are given and of course the
ABCD constants. Then determine sending end voltages using relation
To determine the no load voltage at the receiving end, equation (4.29) is made use of
⁄
% regulation =
Is thus evaluated.
To determine % of transmission, the following relation is made use of:
100
Example 4.1: Determine the voltage at the generating station and the efficiency of the
transmission for the following 1-phase system:
Transformer ratio 2 kV/11kV. The resistance on l.v. side = 0.04 and h.v. side 1.3.
Reactance on l.v. and h.v. side 0.125 and 4.5
Solution: The transmission line equivalent impedance when referred to l.v. side will be
( ) ( )
83
Transformer impedance = 0.04 + 1.3 ( ) ( )
= (0.083 + j0.273)
= (2000
= 2168 volts
84