TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
Please check ( ) the appropriate box that corresponds to the type of assessment.
Periodic Exam: ( ) MIDTERM ( ) FINALS
Course Learning
Outcome Outcome Topics Taxonomy Test Items/Questions
Ref No. Ref No
CO1 LO1.1 Gather and use Remember 1. Which of these is not one of the constraints of a project?
customer insights
to - Scope
guide product
strategy. 2. - Resources
Analyze the
financial, =Team
competitive, and
growth prospects - Budget
for a sector. 3.
Define and
prioritize a
minimum viable 2. Which of the following is not correct about initial phase of a project?
solution.
= The cost associated at the beginning of the project is highest.
3. The project you are managing has nine stakeholders. How many channel of communications
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
-9
-8
- 45
= 36
- Contract
- Status meeting
5. A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term
can BEST describe the difference of $5,000?
- Cost Variance
- Management Overhead
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
- Schedule Variance
7. Which of the following is the most important element of Project Management Plan that is
useful in HR Planning process:
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
8. Which of the following types of Organizational Charts can be BEST used to track project
costs :
9. Which of the following is not true for a Responsibility Assignment Matrix (RAM):
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
- Performance Analysis
- Quality Metrics
= Process Analysis
- Quality Audits
- Performance Measurements
2..A planning phase for an engineering component generated 80 engineering drawings. The QA
team randomly selected 8 drawings for inspection. This exercise can BEST be described as
example of:
- Inspection
=. Statistical Sampling
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
- Flowcharting
- Control Charting
3. Andrew has joined as the Project Manager of a project. One of the project documents
available to Andrew lists down all the risks in a hierarchical fashion. What is this document
called?
- List of risks.
4.During which stage of Risk planning are risks prioritized based on probability and impact?
- Identify Risks
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
- Project Officer
- Project Stakeholder
Apply 1.Which of the following does NOT generate changes to the Project documents:
= Define Activities
- Sequence Activities
= Define Activities
- Sequence Activities
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
3.A schedule activity may begin 10 days before the predecessor activity finishes. This is an
example of:
= Finish-to-Start
- Start-to-Finish
- Start-to-Start
- Finish-to-Finish
4.Sam Consultancy is planning to buy ten desktops for $1500 each from a leading computer
store. Which type of contract will get signed in this case?
= Purchase Order
- Fixed cost
5.Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get
clarification on the work that needs to be performed. Which phase of Project Management is in
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
progress.
=Conduct Procurements
- Plan Procurements
- Control Procurements
- Close Procurements
Analyze
LO1.2 Analyze the Remember 1.Following is not a faced income bearing security_________
financial, -preference shares
competitive, and
=equity share
growth prospects
for a sector. - public deposits
-debentuures
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
= implicitly expressed
-not a physical objective
-social acceptability
2. Fishbone diagram___________
-identify economy
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
3. Capacity planning__________
- increases waste
-increase cost
=save time
-increase production
LTD-4F.4.092622.11
AIMS
Pasay City,
TEST SPECIFICATION
Philippines _____Trimester / A.Y. _______
Apply
5. Which one of the following is NOT a part to study under Market Appraisal?
=Government
-Customers
-Competitors
-Middlemen
LO2.1 1Define and Remember 1. What is to be prepared as a first step to avail finance for a new project?
prioritize a -Promoter’s bio-data
minimum viable
=Project Repor
solution.
-Detailed Report
-Summary
-Reversal
-Modification
=All of the above
4. Traditionally Indian Business had shortage of inputs like Power, Foreign Exchange,
Important Raw Material, Supply of Agricultural Raw materials etc.
-False
=True
5 With respect to a project resources refer to____________
-Machinery
-Man power
-Materials
=All of the above
-RBI
=Government of India
-Supreme Court of India
Apply
- Econometric Method
5.. Delphi Method is which type of Demand Forecasting Method?
-Time Series Projection
=Qualitative
-Causal
-None of these